Loading...
HomeMy WebLinkAbout2024-02-07-tcc-facilities-master-plan-vol-1+ Master Plan Volume I February 2024 +PLANNING 253 College Level Planning 255 3G8P Planning Concepts 257 Campus Level Planning 261 South Campus 262 Northeast Campus 264 Northwest Campus 266 Alliance West Site 268 Southeast Campus 270 Trinity River Campus 272 Trinity River Campus East 274 TCC Connect 276 PRIORITIZATION 279 Prioritization Rationale 281 Master Plan Recommendation — Northeast Campus 284 Master Plan Recommendation — South Campus 288 Campus Level Prioritization 291 South Campus 292 Northeast Campus 334 Trinity River Campus East 48 TCC Connect 50 RESEARCH 53 College Level Research 55 Academic Programs and Initiatives 56 Demographic Study 58 Labor Market Study Process 68 Campus Level Research 75 South Campus 76 Northeast Campus 98 Northwest Campus 120 Alliance West Site 142 Southeast Campus 164 Trinity River Campus 186 Trinity River Campus East 208 TCC Connect 230 INTRODUCTION 1 Mission and Vision 2 Master Plan Vision 4 Master Plan Scope of Services 5 Planning Process 7 LEARNING 13 College Level Background 15 Service Area Context 20 Regional Context 22 College History 24 Current Planning and Design Initiatives 29 Campus Level Background 35 South Campus 36 Northeast Campus 38 Northwest Campus 40 Alliance West Site 42 Southwest Campus 44 Trinity River Campus 46 Northwest Campus 364 Alliance West Campus 390 Southeast Campus 404 Trinity East Campus 428 Trinity River Campus East 460 TCC Connect 468 ACKNOWLEDGMENT 485 Table of Contents Volume I +SUB SECTION TITLE SUB SECTION TITLE SUB SECTION TITLE SUB SECTION TITLE Introduction f 3 + SUB SECTION TITLE SUB SECTION TITLE NORTHWEST CAMPUS Ongoing construction as part of bond projects involved in the campus redevelopment. Tarrant County College 2022 Master Plan Study Tarrant County College (TCC) engaged Corgan to prepare a master plan that provides a holistic view, preparing the College for the future. This master plan study provides an opportunity to reflect upon its history and heritage, assess its current conditions and needs, and incorporate the 3 Goals and 8 Principles (3G8P) to align with TCC’s vision. The master plan provides a broad framework to guide campus development in terms of building infr astructure, program access, and transit. The master plan aligns the College’s mission and vision with the standards defined through the 3G8P. Through this framework, it coordinates near-term facility development and maintenance decisions with a long- term perspective for both the campuses and the college. The master plan implements a framework for how TCC can develop its campuses acr oss the college over the course of the next 20 years. This framework considers the best possible use of the College’s resources to achieve the goals of its students, local industries, and community partners. This is a flexible document to guide development while understanding that priorities may change over time. The master plan provides the College with a clear understanding of the sense of place at each c ampus. The framework for each campus defines an achievable vision that celebrates the distinct purpose at each campus. 4 5 + VOLUME I INTRODUCTION Mission and Vision One College — Three Goals, Eight Principles Role and Scope Tarrant County College implements its mission through a clearly defined set of programs, services, and partnerships that include: — University transfer programs — Workforce education programs — Technical programs — Customized training — Developmental courses — Adult literacy courses — Community education and engagement and community services Values STUDENT SUCCESS Belief in providing quality instruction, resources, and support services to assist our students in achieving their lifelong goals. ACCESS Belief in providing educational opportunities for all members of the community. EXCELLENCE Belief in providing outstanding quality in educational programs, administrative support, and services to its students, faculty, and staff. DIVERSITY Beliefs that the College should reflect the diversity of the community. Tarrant County College (TCC) is committed to providing guided pathways for students that help them achieve their educational goals. VOLUME I INTRODUCTION INNOVATION AND CREATIVITY Belief in cultivating a learning environment that evaluates and incorporates emerging technologies and methodologies to enhance the quality of instruction and administrative support for our students, faculty, and staff. 3G8P Tarrant County College is committed to providing guided pathways for students that help them to achieve their educational goals. In doing so, TCC engaged in a visioning process during the 2016-2017 year to determine its future focus. The College worked with a national consulting firm, Ayers Saint Gross (ASG) and held 25 visioning sessions. 3 GOALS One College TCC will function as one College to provide a consistent and successful student experience. Student Ready College TCC will put students at the core of all programs and services, so that they are welcomed, engaged, and suppor ted inside and outside the classroom. Serve the Community TCC will serve the community and be its first choice for partnership. 8 PRINCIPLES Learning Commons Learning commons are an integrated component with the college level active learning experience and foster greater student engagement by meeting student needs in a dynamic and flexible environment. Libraries are undergoing physical and programmatic changes and are less about books and more about supporting learning activities. Integrated Instructional Learning Environments The College embraces a culture of teaching and learning as the foundation of its mission, and suppor ting innovation in space, technology, and teaching practices serves as the core for student learning and success. To that end, the transformation of learning spaces be yond the traditional format to accommodate additional learning experiences such as experiential and active learning environments, help better support the learning needs of students. Integrated Student Success Model The College dedicates significant resources focused on student success including faculty and staff, spaces, equipment, and technology. Successful integration of resources is fundamental to the learning experience, so that the College is a welcoming environment for students that promotes learning. Student Experience A student-ready College provides an experience for students that is welcoming, simple to under stand, provides a clear pathway, and breaks down barriers. Streamlined processes which are more student-centric ensure that students get through the door on their desired pathway more quickly. High Schools Building and maintaining strong P-20 partnerships is essential for the student pathways to success. The dual enrollment (Early College High Schools) and dual credit partnerships with local school districts supports the student transition to college. Scheduling and Facility Utilization A student-centered schedule of classes is offered and supports student access and suc cess. Campus Character and Quality A student-ready College provides a welcoming and easily navigated experience for students and us es spaces effectively to maximize the student experience. Workspace Environments Redesigned workspace environments will promote more collegiality, enhance spatial qualit y, provide flexibility and increased efficiency, and support a culture of collaboration. 6 7 + VOLUME I INTRODUCTION Master Plan Vision Guiding Principles SERVE THE COMMUNITY Collaborating with community partners benefit everyone. Valuable partnerships can be developed through the Early College High School on each campus and other local universities. EQUITY IN STUDENT EXPERIENCE The College provides a uniformly excellent experience for students across all campuses. FUTURE FOCUSED The master plan analyzes the future and envisions the possibilities at each campus while building on the base of existing projects. CELEBRATE ACCOMPLISHMENTS Due to the history of the College and each campus, diverse programs are established at each campus, each having their own unique identity. The vision for each campus celebrates these efforts while investing in them further. ACADEMIC EXCELLENCE The academic experience of the College is important — successful academic initiatives and technical programs are elevated through the master plan. The master plan re-envisions development across the College to celebrate the unique identities and diverse programs at each campus. VOLUME I INTRODUCTION Master Plan Scope of Services College Level Analysis The master plan team was charged with providing a comprehensive master plan that is prioritized, phases, and implemented over time. The master plan defines existing conditions and issues across the College and considers the numer ous factors that influence the planning scenarios proposed. These factors include, but are not limited to: — Current and projected capital improvements and academic initiatives — Demographic analysis — Workforce trend analysis — Academic analysis — Campus space utilization analysis — Facility condition assessment The master plan team developed and reviewed multiple planning scenario options based on thes e factors. These planning scenarios strive to meet the objectives of the College’s Capital Improvement Program and consider the best possible use of the College’s facilities. During this process, the master plan team worked with both the individual campuses, their stak eholders, as well as with members of the College’s Real Estate and Facilities team. Additional guidance was provided by the College’s program manager and the consultants that make up the master plan team. The master plan team defined campus and program concepts to increase the depth and validity of the proposed cost models and sequencing. The framework considers multiple planning scenario options, providing opportunities and challenges t o develop and maintain the College’s campuses over the next 20 years. The framework guides future decision making while remaining flexible as priorities and needs change. 8 9 + VOLUME I INTRODUCTION Firm Discipline Corgan Master Planning, Architecture FPC Utilization, Demographics, Planning Manning Architects Associate Architect CCS Cost Estimating Coleman & Associates Landscape Architecture Pacheco Koch Civil Engineering, Traffic, Parking Ponce Fuess Structural Engineering Jones DBR MEP Engineering, Fire Protection DataCom Design Group Information Technology Learning Research Planning One College, One Master Plan Planning Planning Prioritization VOLUME I INTRODUCTION Planning Process Master Plan Development Corgan’s master plan process incorporates the master plan scope of services into different task groups. These task groups acknowledge the possibility of overlap between the services included in the master plan and the iterative process that comes with developing a comprehensive master plan. LEARNING The Learning task group focuses on understanding the College’s current and projected campus improvements. Additionally, the master plan team gathered additional information regarding the College and each of the campuses, which involved the following categories. Context The master plan team investigated not just each of the College’s campuses, but also how those c ampuses fit into the surrounding community. Included in this context were the campuses’ interiors, including any ongoing projects or construction. A core tenet of the master plan is to treat these ongoing projects as though they are complete, and an understanding that the projects were successful in resolving the challenges they were seeking to address. The master plan team also examined how each campus fits into the context of the College's goal for “One College” and the existing inequities that exist between each campus. Vision and Goals The master plan team considered the College’s mission and vision as well as the standards laid out by the established 3G8P . These tenets were considered in their application and implementation over both the near term and the 20-year planning horizon. Facilities Assessment The facilities assessment, which was completed as the master plan was developed, created a gr oundwork for understanding the existing conditions of the College’s physical assets. This information played a key role in grounding the planning scenarios as the master plan developed frameworks for each campus. Information and Data Assembly To understand the College’s existing conditions, the team engaged with baseline information pro vided by TCC. This information was not limited to just physical facilities, but also included program information and existing deficiencies that had been identified and that the College was seeking to address. 10 11 + VOLUME I INTRODUCTION RESEARCH The Research task group focuses on the internal and external drivers to the master plan. The Research effort sought to ground the master plan in factual data and quantifiable information to expedite decisions and provide context and rationale for the planning scenarios and recommendations. Demographic Analysis Demographic analysis of the College’s service area provides insight int o the growth and characteristics at both a college and campus level. Understanding scenarios for enrollment growth effects the planning scenarios and the potentials of different campuses and programs. Labor Market Analysis TCC places an emphasis on preparing students for the workplace. Corr elating programs the College offers to trending jobs in distinct categories provides a clear connection between success in academics and success in the workplace. Academic Initiatives and Analysis Evaluating the College’s current academic program as well as student enr ollment in each informs the investment in future programs. An exploration of these metrics can also help pinpoint both areas where the College has seen success and should continue to invest, but also areas where there is potential for growth and where further investigation should occur. Further discussions with both the campus stakeholders and College administrators offer insight into the unique pedagogies that are present at TCC and how success is determined. This creates a deeper understanding of potential changes, challenges, and new ways to continue to elevate TCC. Space Utilization Analysis By analyzing existing spaces on each campus as well as its utiliz ation, the College can understand not only which spaces are underperforming, but also which are performing above and beyond. Identification of these spaces and further analysis can reveal whether the issues are linked to a lack of technology and outfitting that impacts the pedagogical potential of a space or whether a space or facility is inadequate for certain programs. Functional Adequacy Investigations into the pedagogy and teaching environments outlined in 3G8P pr ovides insight into specific spaces and buildings that would benefit from 21 st century teaching modalities. The master plan considers the College from both a near-term context and a 20-year viewpoint. The functional adequacy of certain spaces and buildings may increase the urgency to address those issues in the master plan prioritization. Gap Analysis Producing the master plan at the college level allows for the inequities bet ween campuses to surface. Gap analysis identifies these inequities between campuses and synthesizes them into accommodated needs in the master plan. Gaps are also identified as College faculty and staff communicate areas that are lacking currently. PLANNING The Planning task group focuses on the holistic consideration of planning alternatives that consider the effects of each design and planning decision. These alternatives are reviewed for the effect that it may have on the development in the near-term and over the 20-year horizon of the master plan. The master plan ensures that the development of the planning scenarios are highly- integrated and coordinated with the prioritization at the campus and college level. VOLUME I INTRODUCTION Planning Scenarios The master plan team considered a variety of different planning scenarios at both the campus and college level. The master plan team approached each potential planning scenario with the following understanding: — The framework that the master plan provides should be flexible enough to change with priorities o ver time. — The master plan framework considers that there is not just one correct answer but r ecommends employing the best correct answer. During this process of evaluating planning scenarios, the master plan team engaged in multiple w orking review sessions with both the College’s Real Estate and Facilities team as well as stakeholders at each of the campuses. These work sessions were highly participatory and provided valuable feedback regarding goals of each campus. Campus Character The master plan’s starting point is “first, do no harm” to the existing campus form, fr amework, and massing. A core tenet of the master plan is that the most valuable asset that the College has in its possession is its existing space. While partial demolition and replacement is recommended by the master plan, it is based on the facility assessment and is always data driven. Existing Building Condition The master plan considers the mature nature of many of the College’s campuses and focuses on the existing space inventory in the framework for the future development for each campus. A paramount tenet of the master plan is to ensure that the highest and best used is made of the College’s existing resources. The master plan prioritizes and recommends based on the facility assessment how existing buildings might be re-purposed or renewed through clear and logical phasing plans. Or, where the findings indicate otherwise, new buildings are implemented to replace aging facilities or to address growth and program specific needs. Campus Infrastructure The master plan framework also considers the impact of these future developments on campus infrastructure, plant capacity, parking, drainage, landscape, and integration with the urban framework. PRIORITIZATION The Prioritization task group embraces the understanding that master plans are about defining the time and cost that is required to achieve certain goals established by the College or uncovered by the master plan team. The master plan ensures that the development of the planning scenarios are highly-integrated and coordinated with the prioritization at the campus and college level. Phasing The master plan considers the overlapping of a conceptual phasing plan onto each planning s cenario. The primary parameters that inform the phasing in addition to the prioritization are: — Sequencing of new construction versus remodeling. — Minimizing disruption of campus operations and safety. Cost The master plan applies preliminary cost to each planning scenario to provide additional inf ormation to order priorities. The cost models consider escalation factors to provide a relationship between cost and time. Schedule and Budget The master plan proposes a list of implementable priority projects and a delivery schedule to achieve those. Remaining projects are planned over the course of the 20 year horizon. - + SUB SECTION TITLE SUB SECTION TITLE SUB SECTION TITLE SUB SECTION TITLE Learning c 15 +SUB SECTION TITLE SUB SECTION TITLE TARRANT COUNTY COLLEGE CAMPUSES Tarrant County College has nine campuses, eight of which were included in the scope of the master plan. College Level Background The college level Learning sub-section focuses on establishing the College, its service areas, and background context. This included gaining an understanding of past, current, and projected improvements and any long-term planning or design initiatives that the College was engaged in. The master plan team investigated not just each of the College’s campuses, but also how thos e campuses fit into the surrounding community. Included in this context was the history of the College as a whole and how it connects into its service area and region. The master plan team considered the College’s mission and vision, as well as the standar ds laid out by the established 3G8P. These tenets were considered in their application and implementation over both the near term and the 20-year planning horizon. Existing conditions were realized through baseline information provided by the College. This inf ormation was not limited to just physical facilities, but also identified program information and existing deficiencies that the College was wanting to address. By evaluating this information, the master plan team had a preliminary understanding of the College’s approach to address current and future needs. 16 17 + VOLUME I LEARNING SOUTH CAMPUS Library and campus green, central campus elements. SOUTH CAMPUS Year Constructed: 1967 Campus Size: 145.40 acres in South For t Worth Building Inventory: 36 Buildings, 687,601 SF Campus President: Dr. Lufkin Student Enrollment: 7,475 students Signature Programs: — Architecture T echnology, Computer-Aided Drafting, Construction Management — Automotive — Electronics Technology — Gaming — Heating, Air Conditioning, and Refrigeration — Teacher Education — Welding NORTHEAST CAMPUS Clock tower at the Student Union, a defining campus landmark. NORTHEAST CAMPUS Year Constructed: 1968 Campus Size: 186.79 acres between North Richland Hills and Hurst Building Inventory: 23 Buildings, 665,862 SF Campus President: Dr. Ayers-Palmore Student Enrollment: 9,968 students Signature Programs: — Child Development — Dental Hygiene — Information Technology — Teacher Education — Visual Arts — World Languages VOLUME I LEARNING NORTHWEST CAMPUS Marine Creek Lake, an important part of the campuses character. NORTHWEST CAMPUS Year Constructed: 1975 Campus Size: 187.50 acres in North F ort Worth Building Inventory: 38 Buildings, 523,460 SF Campus President: Dr. Blankenbaker Student Enrollment: 7,372 students (shared with Alliance West Site) Signature Programs: — Aviation — Criminal Justice — Danc e — Fire Technology — Horticulture — Nondestructive Inspection, Testing, and Evaluation ALLIANCE WEST SITE Front entry to the site at Alliance Airport. ALLIANCE WEST SITE Year Constructed: 1991 Campus Size: 40.41 acres in North F ort Worth Building Inventory: 2 buildings, 164,060 SF Campus President: Dr. Blankenbaker Student Enrollment: 7,372 students (shared with Northwest Campus) Signature Programs: — Aviation — Avionics — Logistics and Supply Chain Management — Nondestructive Inspection, Testing, and Evaluation — Welding Technology 18 19 + VOLUME I LEARNING SOUTHEAST CAMPUS View of front entry and barrel vaults, important initial campus elements. SOUTHEAST CAMPUS Year Constructed: 1996 Campus Size: 162.15 acres in Southeastern Arlington Building Inventory: 14 Buildings, 635,965 SF Campus President: Dr. Coppola Student Enrollment: 8,537 students Signature Programs: — Culinary Arts — Dietetics — Drama/Theater — Engineering — Hospitality Management TRINITY RIVER CAMPUS Rotunda and circle drive that define the primary campus visitor experience. TRINITY RIVER CAMPUS Year Constructed: 2003 Campus Size: 39.9 acres in downtown Fort Worth Building Inventory: 1 Building Complex, 965,360 SF Campus President: Dr. Madison Student Enrollment: 5,908 students (shared with Trinity River Campus East) Signature Programs: — GIS Technology — Healthcare Professions — Sign Language Interpreting VOLUME I LEARNING TRINITY RIVER CAMPUS EAST View of the campuses central path and connection to surrounding urban fabric. TRINITY RIVER CAMPUS EAST Year Constructed: 2011 Campus Size: 8.75 acres in downtown Fort Worth Building Inventory: 5 Buildings, 134,364 SF Campus President: Dr. Madison Student Enrollment: 5,908 students (shared with Trinity River Campus) Signature Programs: — Healthcare Professions — Nursing TCC CONNECT Students engage with the campus through both physical and digital identities. TCC CONNECT CAMPUS Year Constructed: 2015 Campus Size: Single floor of Trinity River Campus West Fork Building Inventory: TRWF floor 2 — 30,290 SF Campus President: Dr. Morales Student Enrollment: 14,763 students across the college Signature Programs: — eLearning — Weekend College 20 21 +VOLUME I LEARNING TARRANT COUNTY COLLEGE CATCHMENT AREA Dallas, North Central Texas, Tarrant WDAs VOLUME I LEARNING Service Area Context Tarrant County Located in the north central area of Texas, Tarrant County is an urban area. Fort Worth serves as the county seat to a population of approximately 2.1 million citizens. Tarrant County is a member of the North Central Texas Council of Governments. Tarrant County's roots lie in the 'Old West' and much of the county’s heritage can be traced to the era of the cowboy and the cattle drives that passed through Tarrant County. Tarrant County is one of 254 counties in Texas which were originally set up by the State to serve as decentralized administrative divisions providing state services and collecting state taxes. The decades of the 1950s and 1960s brought phenomenal gr owth to Tarrant County. The county transportation network was greatly improved during this period. The Dallas-Fort Worth Turnpike (later part of Interstate Highway 30) opened in 1957. In 1960 Fort Worth and Arlington were connected by Spur 303, and Interstate 30 West was functional by 1964. Finally, when the 1970s saw the completion of the Dallas-Fort Worth International Airport, Tarrant County was truly linked with the world at large. The 1980s witnessed more growth for Tarrant County. In the early 1990s the c ounty economy was tremendously diverse, with more than 1,000 factories and a strong agricultural base. In spite of its urban growth, Tarrant County still maintained the atmosphere of a frontier county. Opportunities abounded, and people were proud of the advantages that progress had brought, while admiring the people of the past and preserving a western spirit. Today, much of the flavor and attitudes that are the history of Tarrant County live on. The frontier has changed, but not the pioneering spirit. Tarrant County's western heritage sits side by side with its internationally renowned cultural district. Tarrant County's economy is one of the most vibrant and diverse in the nation and is leading the r egional resurgence in business re-locations and expansions, retail development and new housing construction. Once tied to the oil rigs and cattle ranches of west Texas, today Tarrant County's businesses reach around the globe and the County's airports are among the country's foremost international gateways. Today, much of the flavor and attitudes that are the history of Tarrant County live on. The frontier has changed, but not the pioneering spirit. 22 23 +VOLUME I LEARNING DOWNTOWN FORT WORTH Aerial view of Fort Worth Convention Center, circa 1969. DOWNTOWN FORT WORTH Aerial view of Fort Worth. DOWNTOWN FORT WORTH View of the Trinity River and TCC's Trinity River Campus. VOLUME I LEARNING Regional Context Dallas-Fort Worth Metroplex DEMOGRAPHICS The Dallas-Fort Worth Metroplex is the most populous metropolitan area in both Texas and the southern United States. The region also functions as the economic and cultural hub of North Texas. In 2016, the Dallas-Fort Worth Metroplex had the highest annual population growth in the United States. WORKFORCE The cities of Dallas and Fort Worth are the two central cities of the metroplex, with Arlington being a third economically important city; it is a center for sporting events, tourism, and manufacturing. The Texas farming and ranching industry is based in Fort Worth, though the area's ec onomy is diverse. Several major defense manufacturers, maintain significant operations in the metroplex, primarily on the "Fort Worth side." They are concentrated along State Highway 170 near I-35W, commonly called the "Alliance Corridor" due to its proximity to the Fort Worth Alliance regional airport. Location, transportation, and a large, diverse labor pool keep DFW a prime destination for relocating and expanding businesses. EDUCATION As the College looks to partner with businesses and other institutions, the Dallas- Fort Worth Metroplex is an active and growing area. The Dallas-Fort Worth Metroplex comprises the highest concentration of colleges and universities in Texas. In 2020, Dallas–Fort Worth was recognized as the 36 th best metropolitan area for STEM professionals in the U.S. TRANSPORTATION Much of the growth can be attributed to building various forms of transportation strategically ahead of actual need, beginning with the DFW International Airport. The airport set the region to be recognized as a national crossroad. RECREATION North Texas is home to 124 museums, 180 golf courses, 1,000 miles of off-street trails, 2,000 public parks, dozens of lakes, two world-class zoos, and thousands of restaurants and other recreational opportunities. The Fort Worth Stockyards is a historic district where the past comes to life and western culture thrives. Fifteen professional and e-sports teams call North Texas home. 24 25 + VOLUME I LEARNING College History 1965 to Today Tarrant County College was established by a county-wide election on July 31, 1965, as Tarrant County Junior College, the name change coming in 1999. The South Campus opened in 1967, followed by Northeast (1968), Northwest (1976), Southeast (1996), Trinity River Campus (2009) and TCC Connect Campus (2015). The Erma C. Johnson Hadley Northwest Center of Excellence for Aviation, Transportation and Logistics opened in Fall 2014 at Alliance Airport as part of the Northwest Campus. The College is governed by a seven-member Board of Trustees elected for staggered six-year terms in single member districts. Enrollment growth has been steady throughout recent years. The South Campus, at 4,772, had the lar gest opening-day enrollment of any community college in the nation up to that time. Overall credit student enrollment passed the 20,000 mark in 1980 and exceeded 50,000 in the fall of 2011. Recently, TCC was named the seventh-largest college or university in Texas. TCC celebrated its Golden Jubilee in 2015, by recognizing 50 years since the college was established. 1960s Unlimited optimism matched with boundless energy marked TCJC’s first five years. Under the guidance of the Board of Trustees, Dr. Joe B. Rushing and his team created a curriculum, built, and staffed two campuses, received full accreditation, and — most important — began the tradition of providing knowledge, skills, and the hope of a better future to the people of Tarrant County. 1967 — South Campus Dedication Governor Connally indirectly spurred the formation of TCJC in 1963 when his T exas Commission on Higher Education called for more junior colleges, including one in Fort Worth. Another Connally panel, the Committee on Education Beyond High School, included founding Board of Trustees President Jenkins Garrett. 1967 — South Campus Opens The Board of Trustees, on December 1, 1965, selected the campus site, engaged Morris Parker and Mervyn Croston and the lead architects, and declared that the campus would open for “…began the tradition of providing knowledge, skills, and the hope of a better future to the people of Tarrant County.” VOLUME I LEARNING classes in September 1967 — only 21 months away. The accelerated design process yielded a plan for 23 buildings, all but two being single-story and thus quicker to build. The contractor brought the job in on time, and classes began on September 18, 1967. 1969 — Northeast Campus Project The 188-acre site, which lay across the border bet ween Hurst and North Richland Hills, was purchased for $2,500 per acre. With all buildings running up to two months behind schedule, the College was forced to adopt a plan whereby Northeast students would attend classes on South for the fall 1968 semester. 1970s It was a decade of growth, with enrollment almost 20,000 by 1979. The College welcomed two campuses in 1976 — the Northwest Campus and a college level administrative building. It was also a time of change on the Board of Trustees. By decade’s end, only two of the original seven trustees, Dr. May Owen and Dr. Ardis Bell, remained. 1971 — Bonds Fund Expansion The $21 million package, second in the college’s hist ory, was to fund the construction of the new Northwest Campus and expansion at South and Northeast. 1974 — Northwest Campus Ground-breaking Land for the campus, 193 acres on the east end of Marine Cr eek Lake, was donated to the College years earlier by F. Howard and Mary D. Walsh. The original gift was to consist of 150 acres, but 50 acres turned ORIGINAL TCJC BOARD OF TRUSTEES Dr. May Owen, Jenkins Garrett, John Finn, Delbert Adams, Edward Hudson, Dr. Ardis Bell, Rev. Haynes out to be in a floodplain and thus not suitable for buildings. 1975 — TCJC is Ten Years Old The 10-year span saw the passage of two bond elections, the building of t wo campuses with a third nearing completion, an enrollment increase from 4,272 to more than 16,500, an increase in the annual budget from $1.8 million to $22.6 million, and full accreditation by the Southern Association of College and Schools’ Commission on Colleges. 1975 — Northwest Campus Construction Designed by the architectural firm of Preston Geren and Ass ociated, the campus was all under a single roof except for the D Wing which housed the physical SOUTH CAMPUS Aerial view of South Campus under construction, circa fall 1967. education facilities, and the slender Maintenance Building . 1976 — Northwest Campus Dedication The campus was planned to have been ready for class es the previous September, but the opening was delayed. The delay turned out to be a blessing in disguise as Northwest proved to be the only college or university campus to open in the Bicentennial year of 1976. 1980s Enrollment kept growing. The fall of 1980 total of 22,026 made TCJC the largest college or university in Tarrant County. A third bond election provided needed expansion. The big change was at the top when Dr. 26 27 +VOLUME I LEARNING NORTHEAST CAMPUS Aerial view of Northeast Campus, circa 1969. Joe Rushing retired as chancellor and C.A. Roberson was appoint ed. 1983 — May Owen Center Dedication The College’s administrative offices outgrew their leas ed space in the Electric Service Building in downtown Fort Worth, so in 1981 the board purchased parcels of land on either side of Throckmorton Street just to the north of Lancaster Avenue and built the 40,000-square-foot facility that has served the College administration ever since. 1985 — TCJC Turns Twenty Reflecting on the anniversary, Chancellor Joe B. Rushing wr ote this for the August 1985 issue of Momentum: "Excellence cannot be achieved with NORTHWEST CAMPUS Aerial view of Northwest Campus under construction, circa 1975. good facilities alone; excellence can only be achieved with good people ." 1990s TCJC came to Arlington with the opening of the Southeast Campus in 1996. Enrollment surged, but state funding failed to keep pace, and tuition and taxes increased. There was a new chancellor, with Dr. Leonardo de la Garza coming on board in 1997 to replace the retired C.A. Roberson. The most dramatic change was in the name itself as the College became Tarrant County College in 1999. 1996 — Southeast Campus Construction Tarrant County Junior College had pretty much left the s outheast part of the county alone, but the need for a campus in the burgeoning Arlington-Mansfield ar ea could no longer be ignored. The two cities’ combined population jumped from 94,311 in 1970 to 181,720 in 1990. A 123-acre tract was purchased in 1987, but construction had to wait on the partial completion of Texas 360 south of I-20. Finally, in 1992, voters passed a fourth bond election to fund the building of the campus, make additions to the other three campuses, and spend $3.1 million on a new computer system. The campus opened in fall 1996 with an enrollment of 3,993 students. It was designed for 5,000 students, but quickly exceeded that number. By 2000, Southeast was second in enrollment only to Northeast Campus. 1999 — TCJC Becomes TCC The board had discussed the change for some time but was hesitant t o buck tradition. But a survey of faculty, staff, and students showed that 71 percent wanted a name change. 2000 s The 2000s were dominated by the building of a fifth TCC campus in downtown Fort Worth. The initial, ambitious concept had to be curtailed, but the College was able to buy the RadioShack complex, most of which became the Trinity River Campus. Elsewhere, TCC was re-accredited for another 10 years and the first facilities master plan was completed. 2002 — Fire Service Training Center Opens The FSTC, sitting on 23 acres, was hailed at the time as the most t echnologically advanced facility in the country. It features a live-fire disaster city replicating elements found in every community, including VOLUME I LEARNING landscaped residential streets, homes, businesses, an apartment/hotel complex, warehouse, high-rise building, and a fire station. The facility also has a large pad for driver training, a swift-water rescue channel, and a 48,000-square-foot classroom building. 2004 — Plans for a Downtown Fort Worth Campus What began as a brainstorming session about expanding the May Owen Center, morphed into an ambitious plan for an additional TCC Campus in downtown Fort Worth. Designed by world-class architect Bing Thom of Vancouver, the plan featured educational complexes on both sides of the Trinity River connected by a pedestrian footbridge. The photo shows the model looking from north to south with part of the North Main Street Bridge and the Tarrant County Courthouse complex at the top right. The model was unveiled on October 29, 2004, and ground was broken on June 10, 2005. Unforeseen issues with the siting along Trinity River and coordination with the different governing bodies lead to the decision to only build on the South side of the Trinity River. The portion on the south bank of the river would eventually survive as Trinity River Campus East. 2008 — Secret Negotiations with RadioShack In late 2007, TCC officials did not know when, or even if, the College would get permission from the Army Corps of Engineers to build part of the proposed downtown Fort Worth campus on the levee north of the Trinity River or to build a bridge linking it with the south portion. Trustee Bobby McGee, who advocated exploring other possibilities, discovered that the German consortium that was leasing part of the RadioShack complex to the west of the proposed campus might be interested in selling it instead. Very delic ate, very secret negotiations stretched into the next year but finally, on June 25, 2008, the board voted to authorize Chancellor Leonardo de la Garza to enter into agreements to buy the property. After about $80 million worth of remodeling, three of the five buildings opened in fall 2009 as the Trinity River Campus. 2009 — Trinity River Campus Opens By early 2009, renovation of the portion of the RadioShack c omplex that was to become TCC Trinity River Campus progressed to the point where the first administrators could move in. The new campus opened its doors to students that fall with an initial enrollment of 3,717. By the fall of 2013, there were 8,849 students, many of them enrolled in the health professions programs housed in Trinity River Campus East, and still others as part of the early college high school made possible by a partnership with the Fort Worth ISD Texas Academy of Biomedical Sciences. 2010 – PRESENT Recent years have seen fundamental changes brought about by a new and inexorable drive for student success. With Erma Johnson Hadley as the prime mover, TCC plunged into a whirlwind of initiatives — Achieving the Dream, common course learning materials, and consolidation of alternative learning venues under the banner of TCC Connect. 2013 — Trinity River Campus East Opens After the TCC Board of Trustees agreed in 2008 to purchase the RadioShack complex to be the Trinity River Campus, there remained the question of what to do with the partially completed south SOUTHEAST CAMPUS Southeast Campus under construction, circa 1996. TRINITY RIVER CAMPUS Trinity River Campus when it was RadioShack's headquarters. 28 29 +VOLUME I LEARNING VOLUME I LEARNING portion of the original design. Options included restoring the bluff leading down to the river, selling the building, or completing the construction. The first was economically and ecologically unfeasible. The second, because the basic design was that of an educational facility, was likewise unlikely. The problem with the third was cost. An extra $103 million was needed to finish the project. In the end, the board voted to approve the expenditure, and Trinity River Campus East opened in 2011 as both an educational and architectural marvel. 2015 — TCC Connect Opens TCC Connect is the sixth campus of the Tarrant Count y College, opening in 2015. This campus is commonly known as the virtual campus but offers more than traditional virtual campuses. The campus offers two teaching modalities: eLearning and Weekend College. The TCC Connect Campus was named a Top 60 Best Online Community Colleges and Trades Schools of 2022 — Intelligent.com TRINITY RIVER CAMPUS EAST Model of original plan by Bing Thom for TRCE. TCC CONNECT Ribbon cutting ceremony for TCC Connect in 2015. Current Planning and Design Initiatives Ongoing Construction Efforts 2019 BOND PROGRAM Tarrant County College Bond Project In November 2019, Tarrant County voters approved TCC’s $825 million bond pr oposal to fund a plan that will construct, improve, renovate, and equip buildings throughout the six-campus college. An additional $12 million will be added to the Northwest Campus redevelopment to support the Early College High School program. Northwest Campus Re-Development The windstorm that caused severe structural damage to campus buildings in 2016 has led t o a redevelopment budgeted at $352 million, part of the $825 million bond program authorized by the voters of Tarrant County in 2019. The site plan shows that all to remain from the prior campus core will be W ACB, WHPE and WBSA, which houses the maintenance and physical plant functions. These will be “re-skinned,” given new exteriors so as to blend with the four new buildings, which are named Buildings 1, 2, 3, and 4. Building 1 will be on the northwest corner of the core campus, midwa y between WACB and WHPE. Its three levels will contain the early college high school as well as science labs. Building 3 will be to the southeast of WACB with a park-like plaza to the north reaching to Building 1. It will be on two levels and will house art, music and general-purpose classrooms. Building 4 will be to the south of Building 3 with the two connected by an enclosed bridge on the second level. The Learning Commons will be located here and will retain its view of Marine Creek Lake. Also in Building 4 will be the bookstore, food services and a multipurpose center. Building 2, extending east and north of Building 4 with another enclos ed bridge linking them, will have most of the student development services functions and a large student gathering atrium with a spectacular “learning stair.” Other student services will be on the second level, as will testing areas and faculty spaces. Administrative offices and more faculty space take up the third level along with general classrooms. With this building, TCC Northwest seems to have achieved the always-sought-after but never-quite-realized “One-Stop Shop” for student services. In November 2019, Tarrant County voters approved TCC’s $825 million bond proposal to fund a plan that will construct, improve, renovate and equip buildings throughout the six- campus college. 30 31 + VOLUME I LEARNING NORTHWEST CAMPUS RE-DEVELOPMENT Projected rendering by Gensler+Huckabee. SOUTHEAST CAMPUS EXPANSION Projected rendering by Perkins and Will. Instead of sending students to buildings scattered across a campus, they can be not just dir ected, but escorted to whatever is needed next. There’s a practical side, as well. “It’s about building for flexibility,” Blankenbaker said. “The elements that make up each building have been informed by the work of the eight Principle Advisory Panels. From formal to informal student learning spaces, faculty and staff neighborhoods, Learning Commons and the student welcome center – this vision of TCC Northwest is modern, flexible, accessible and most importantly, student-ready.” Building 1 is due to be completed by March 2023 and will provide “swing space” for facilities displaced by the demolition of WTLO, WSTU and WFAB, which is to begin in July, 2023. Building 2 is due to be completed by May, 2023. Acknowledging the impact of the campus construction projects, Dr. Blankenbaker said, “w e are not just building TCC Northwest, we are building for the future of Tarrant County College and the community we serve.” Southeast Campus Expansion The TCC Southeast project, budgeted at $142 million, is part of an $825 bond program appr oved by Tarrant County voters in November 2019. Preliminary work began in March, with a projected completion date of September 2024. All in all, the campus will gain about 100,000 square feet and will be large enough to accommodate enrollment through 2030. The new buildings will account for about 100,000 square feet of the total, and 234,000 square feet of the present structure will be renovated. The new buildings will “bookend” the campus and provide the needed quality outdoor spac e by partially enclosing the grassy area outside ESED and the rose garden area outside the library. The new look and functionality are grounded in the values inherent in the College’s 3G8P and that the project’s mission is to deliver a plan providing accessibility, efficiency, connectivity, integration, innovation, flexibility, transparency, and invitation. Work planned outside the primary campus footprint will include the removal of six temporary structures to the east, and the gravel parking lot will be expanded and paved, helping to alleviate a problem that has existed at Southeast since it opened. VOLUME I LEARNING NORTHWEST CAMPUS RE-DEVELOPMENT Projected rendering by Gensler+Huckabee. SOUTHEAST CAMPUS EXPANSION Projected rendering by Perkins and Will. NORTHWEST CAMPUS RE-DEVELOPMENT Re-development of the Northwest Campus including demolition, renovations, infrastructure, and new construction. Current Stage: Construction Project Opening: December 30, 2025 Current Budget: $352,000,000 SOUTHEAST CAMPUS EXPANSION The project consists of the renovation and expansion of Tarrant County College’s Southeast Campus. The renovation scope will include selective structural renovation, major renovation, and finish level renovation to address campus needs and college level initiatives, and to fit contextually within the overall design concept to create a new campus identity. The renovation will also include selective façade and building envelope updates. Current Stage: Construction Project Opening: August 31, 2024 Current Budget: $151,200,000 32 33 +VOLUME I LEARNING EMERGENCY POWER INSTALLATION Southeast Campus upgrade in progress. EMERGENCY POWER INSTALLATION College-wide backup power for lighting, IT, and critical infrastructure life safety systems. Current Stage: Planning/Programming Project Opening: December 31, 2023 Current Budget: $37,293,000 WAYFINDING PROGRAM Monument sign at Northeast Campus. WAYFINDING PROGRAM Through a series of workshops with students and employees, the CCQ and Real Estate teams identified four key priorities to improve the on-campus experience: increase visibility of the TCC brand, create cohesive orientation and wayfinding, clarify connection points (like parking lots) and develop a consistent naming system, or nomenclature, for buildings and classrooms. Current Stage: Construction Project Opening: December 30, 2025 Current Budget: $352,000,000 VOLUME I LEARNING NORTHEAST CAMPUS SEWER REHABILITATION Infrastructure project at Northeast Campus. NORTHEAST CAMPUS SEWER REHABILITATION This project is to replace all in ground sewer mains at Northeast Campus that are over 50 years old and are nearing the end of their life cycle. Current Stage: Construction Project Opening: — Current Budget: $2,528,500 NTAB AND SACA – SACD RENOVATIONS Exterior photo of NTAB Building at Northeast Campus. NTAB AND SACA – SACD RENOVATIONS This project seeks to bring poor and fair as well as previously upgraded basic condition classrooms in line with the IILE Principle as part of the 3G8P efforts for both Northeast Campus NTAB building and the South Campus SACA – SACD buildings. Refinish of the existing hallways and common spaces as well as necessary ADA updates to restroom facilities are also planned as part of the project scope. A Fire Sprinkler system will be added to the entire NTAB facility. Current Stage: Construction Project Opening: February 28, 2023 Current Budget: $8,155,220 34 35 + SUB SECTION TITLE SUB SECTION TITLE SOUTH CAMPUS Aerial view of South Campus under construction, circa fall 1967. Campus Level Background The campus level Learning sub-section focuses on each campuses’ history and context. The history of each campus is the foundation for their identity and how the local community perceives it. This background establishes an understanding of past, current, and projected improvements and any long-term planning or design initiatives of the campus. The master plan team investigated not just each of the College’s campuses, but also ho w those campuses fit into the surrounding community. Included in this context were the campuses’ interiors, including any ongoing projects or construction that the College was engaged in. A core tenet of the master plan is to treat these ongoing projects and construction as though they are complete, and an understanding that the projects were successful in resolving any issues that they were seeking to address. The facilities assessment, which was completed as the master plan was developed, cr eated the groundwork for understanding the existing conditions of the College’s physical assets. This information included physical facility background, program information, and existing deficiencies that had been identified and that the College was seeking to address. 36 37 + VOLUME I LEARNING VOLUME I LEARNING South Campus students promoting the $21,000,000 bond that eventually funded TCC's expansion. South Campus Campus History Voters of Tarrant County formed the Tarrant County Junior College District in a bond election on July 31, 1965. The Board of Trustees, on December 1, 1965, selected the campus site, engaged Morris Parker and Mervyn Croston and the lead architects, and declared that the campus would open for classes in September 1967 — only 21 months away. When the architects protested that the deadline could not be met, they were told to start work or face replacement by another firm. The accelerated design process yielded a plan for 23 buildings, all but t wo being single-story and thus quicker to build. The construction contract was awarded on August 19, 1966, to McCann Construction of Fort Worth for $8,617,455. Using a novel plan that divided the project into four color-coded segments, each with its own crew and supervisor, the contractor brought the job in on time, and classes began on September 18, 1967, as the board promised. Center of Excellence for Energy Technology under construction. Aerial view of South Campus, circa 1975. The South Campus, at 4,772 students, had the largest opening- da y enrollment of any community college in the nation up to that time. Over the next several decades, the campus would continue to grow in enrollment and quantity of buildings to include instructional spaces, technical buildings, and an Early College High School. In addition, several recent building renovations, and planned renovations in the SELE and the STEC, are working to implement IILE standards, increase student spaces, and update infrastructure in the remaining original campus buildings. The South Campus offers a multitude of programs including: ar chitecture technology, automotive, computer-aided drafting, construction management, electronics technology, gaming, heating, air conditioning and refrigeration, and welding. As the first and oldest campus of Tarrant County College, the South Campus is comprised of numerous single-story and a few multi-story buildings. Having a high quantity of smaller buildings created a typical college campus feel, encouraging a network of paths and green spaces between the buildings with all parking on the exterior of the campus. 38 39 + VOLUME I LEARNING Aerial view of Northeast Campus. Dr. Rushing (former Chancellor) and Donald Anthony (former President) at TCJC Dental Lab. Aerial view of Northeast Campus, circa 1969. VOLUME I LEARNING Northeast Campus Campus History The second of the six Tarrant County College campuses to be developed, the Northeast Campus, opened its doors to students in Spring 1969. The 186.79-acre triangularly shaped property, which lies across the border between Hurst and North Richland Hills, was purchased for $2,500 per acre. Albert Komatsu was the architect, and McCann Construction, which was to build the South Campus, also won the contract for Northeast with a bid of $6,913,333. McCann had slightly more time for the Northeast project, but a seven-week strike by the Iron Workers Union and a spate of bad weather cost him 124 work days. With all buildings running up to two months behind schedule, the College was forced to adopt a plan whereby Northeast students would attend classes on South for the fall 1968 semester. Even when the majority of the campus opened in spring 1969, physical education classes were conducted in a nearby church gym. The campus is bordered by several major thoroughfares which pr ovide five access points to the campus; the main entrance is located on Harwood Road. The initial campus was comprised of 14 buildings serving student, staff and faculty functions plus eight support buildings. The academic and support buildings are lar gely concentrated in the center of the campus with surrounding surface parking lots. Over the past few decades several of the original campus buildings ha ve received minor renovations to support changes in curriculum and functional needs. However, the majority of renovations completed to date have entailed mechanical and life safety projects. The most recent academic building, the Technology and Arts Building (NTAB), was constructed in 1985. Some college buildings are also located on the property, one of which provides space for an Early College High School. While these projects helped to provide additional academic space and necessary repairs, there remains a need on the campus for updated, flexible, student-centric spaces. Growth space should also be incorporated into the campus master plan. Over the past decade, enrollment has remained constant near 13,000 students with a peak of over 17,000 students. Future population growth is projected within the catchment and service area. The Northeast Campus is the second oldest campus within the college and shares the College’s commitment to being One College, Student Ready, and Serving the Community. 40 41 + VOLUME I LEARNING Aerial view of Northwest Campus under construction, circa 1975. Dr. Rushing (former Chancellor) at Northwest Campus groundbreaking ceremony, circa 1974. Aerial view of Northwest Campus. VOLUME I LEARNING Northwest Campus Campus History The Northwest Campus was initially comprised of five buildings constructed in 1975. Land for the campus, 193 acres on the east end of Marine Creek Lake, was donated to the College years earlier by F. Howard and Mary D. Walsh. The original gift was to consist of 150 acres, but 50 acres turned out to be in a floodplain and thus not suitable for buildings. Designed by the architectural firm of Preston Geren and Associated, the campus was all under a single roof except for the D Wing, which housed the physical education facilities, and the slender Maintenance Building to its left. The traffic circle is in a corner formed by Administration Wing extending upward and C Wing extending to the left. The node is just to the right of the C Wing, with A Wing extending toward the top left and B Wing jutting right, toward the lakefront. Over time, the campus added several additional structures, including a F ire Service Training Center, a Technical Building with an Air Hangar, a Criminal Justice Center, and a Firing Range. While the newer structures on the campus helped to meet additional program needs and student growth, the five original buildings received only minor renovations and have not undergone any major renovations, classroom reconfigurations, or ADA upgrades. In addition, in 2016 the c ampus experienced severe storm damage. This storm damage and the need for updated teaching and support spaces, technology, and configuration updates created the basis for a Campus Redevelopment Project initiated in 2019 by the passing of an $825 million dollar bond package. The Northwest campus received $320 million dollars of this funding for a needed redevelopment project. This project saw the demolition of the original five buildings and construction of four new buildings. The new buildings, slated for completion in late 2025, provided the campus with updated teaching spaces, an Early College High School, a state-of-the-art theatre, an inclusive Learning Commons, faculty and staff neighborhoods, and a consolidated onboarding experience for students. While these projects helped fill a significant need in the academic core of the campus there was no construction or renovation projects related to the technical facilities on campus. Future campus enrollment growth was also not included in the bond project construction. The Northwest Campus has focused on putting students first for over 40 years. As teaching methodologies, technology, and student needs continue to change, so have the space needs of the educational facilities that support those functions. 42 43 + VOLUME I LEARNING VOLUME I LEARNING Aircraft utilized by the Commercial Pilot program. Alliance West Site Site History The Erma C. Johnson Hadley Northwest Center of Excellence for Aviation, Transportation and Logistics, formerly known as the TCC Aviation Center, opened in Fall 2014 at Alliance Airport as part of the Northwest Campus. The newly renovated 164,060-square- foot facility at the Alliance Airport provided TCC with the ability to expand into the aviation field and related fields, supporting a large component of the northern Texas economy. Project cost neared $20 million, including the purchase, design, and renovation of the building. The credit programs include aviation maintenance technology, pr ofessional pilot , logistics and supply chain management, nondestructive inspection, testing and evaluation, and welding technology. The non-credit programs include project management professional exam preparation, remote pilot certific ation test prep, and SHRM essentials of human resources. In addition to the academic pr ogr ams provided, Corporate Services relocated to a portion of the third floor of Alliance West in 2018 with an expansion and full renovation of the third floor in 2020. Corporate Services utilizes the renovated space to work with businesses, community members, economic development organizations, and industry associations to further develop the workforce of Tarrant County. As aviation and logistics employment needs accelerate, an educated workforce will be required to fill positions in two of North Texas’ most rapidly growing industries. The Northwest Campus Center of Excellence for Aviation, Transportation, and Logistics reflects the college’s desire to educ ate future pilots, aircraft mechanics and logistics professionals. Faculty leading the Aviation Career Education Academy Camp. Opening of the Northwest Campus Center of Excellence for Aviation, Transportation, and Logistics. 44 45 + VOLUME I LEARNING VOLUME I LEARNING The “bridge” connecting the main building and Science and Academic Building. Southeast Campus Campus History While Tarrant County Junior College continued to expand within Tarrant County from its dedication of the South Campus in 1967 and construction of two additional campuses, Northeast and Northwest, and the addition of the May Owen Center it had pretty much left the southeast part of the county unserved. However, the need for a campus in the rapidly expanding Arlington-Mansfield area was becoming harder to ignore as the two cities’ population had almost doubled in 20 years growing from 94,311 in 1970 to 181,720 in 1990. A 123-acre tract was purchased in 1987, but construction had to wait on the partial completion of Texas 360 south of I-20. Finally, in 1992, voters passed a fourth bond election to fund the building of the campus, make additions to the other three campuses, and spend $3.1 million on a new computer system. Opening in the fall 1996, the campus was able to fill an overwhelming need in the area enrolling 3,993 students in the fall semester. By the fall of 2000 the campus was only second in enrollment to the Northeast Campus and had already outgrown its 5,000 student capacity. Southeast Campus under construction, circa 1996. Front entry of Southeast Campus. Over the next decade the campus would continue to grow reaching an enrollment nearing 13,000 students in 2009 while still operating in its originally facility. Portable buildings were provided to help ease the crowding while a new 120,000-gross-square-foot Science and Technology Building began construction. The new facility opened in 2010 providing much needed instructional and science lab spaces. As growth in the area continued the campus would take the initiative to fill another need in the community. The 30,000-gross-square-foot Early College High School opened its doors to its first semester of Fort Worth ISD students in 2015. Growth on the campus reached a high point in 2013 with over 15,000 students. Ov er the next several years the campus experienced consistent enrollment and an ever present need for more space. Passing of the $825 million Tarrant County College Bond Program in 2019 allowed the Southeast Campus to construct two new buildings, a Student Success Building and an Academic Building. In addition, a portion of the instructional space, Onboarding areas, and the Learning Commons also received updates and functional renovations. As a higher institution of learning, TCC’s Southeast Campus’ most capital- intensive aspect of its institution is its buildings. Space is an asset and a tool for delivering the educational mission, vision, values, and pedagogy for students on the Southeast Campus. 46 47 + VOLUME I LEARNING Aerial view of downtown Fort Worth and Texas Electric Power Plant, razed for construction of TCC’s downtown campus. View of the primary urban connection at the Trinity River Campus to downtown Fort Worth. RadioShack Headquarters (now Trinity River Campus) under construction. VOLUME I LEARNING Trinity River Campus Campus History In 2005, RadioShack opened its new 38-acre corporate campus in downtown Fort Worth, designed by HKS Architects. In late 2007, TCC officials did not know when, or even if, the College would get permission from the Army Corps of Engineers to build part of the proposed downtown Fort Worth campus. Trustee Bobby McGee, who advocated exploring other possibilities, discovered that the German consortium that was leasing part of the RadioShack complex to the west of the proposed campus might be interested in selling it instead. Very delicate, very secret negotiations stretched into the next year but finally, on June 25, 2008, the board voted to authorize Chancellor Leonardo de la Garza to enter into agreements to buy the property. Remodeling and reconfiguration of the newly acquired property cost an estimated $80 million for the first phase. By early 2009, renovation of the portion of the RadioShack complex that was to become TCC Trinity River Campus progressed to the point where the first administrators could move in. The architectural firm, Jacobs, designed the campus reconfiguration while Beck Construction supported renovation. The new campus opened its doors to students that fall with an initial enr ollment of 3,717. By the fall of 2013, there were 8,849 students, many of them enrolled in the health professions programs housed in Trinity River Campus East, and still others as part of the early college high school made possible by a partnership with the Fort Worth ISD Texas Academy of Biomedical Sciences. The campus opened portions of the remaining buildings in 2011, totaling 965,360 square feet. The campus is made up of three six-story buildings, a commons building, the Tarrant County Idea Store, and a multi-level parking garage. The Trinity River Campus is comprised of two physical locations; Trinity River Campus and Trinity River Campus East. The campuses, separated by only a half mile, are easily accessible by road or a beautiful walk along the adjacent West Fork Trinity River path. The Trinity River Campus offers a number of general education programs supporting careers in the STEM disciplines while also providing signature educational paths in areas such as sign language. 48 49 +VOLUME I LEARNING Trinity River Campus East under construction as seen from the Trinity River that the campus faces. Model of original plan for Trinity River Campus East by Bing Thom Architects. Aerial view of Trinity River Campus East under construction, circa 2016. VOLUME I LEARNING Trinity River Campus East Campus History What started out as a brainstorming session about possibly expanding the May Owen Center eventually morphed into an ambitious plan for a TCC campus in downtown Fort Worth. Designed by world-class architect Bing Thom of Vancouver, the plan featured educational complexes on both sides of the Trinity River connected by a pedestrian footbridge. The design was unveiled on October 29, 2004, and ground was broken on June 10, 2005. Unfortunately, clearance to build on the north side levee and to sink columns into the river could never be obtained, and the plan for the northern part of the campus was scrapped. The portion on the south bank of the river would eventually survive as Trinity River Campus East. After the TCC Board of Trustees agreed in 2008 to purchase the RadioShack c omplex to be the Trinity River Campus, there remained the question of what to do with the partially completed south portion of the original design. Options included restoring the bluff leading down to the river, selling the building, or completing the construction. The first was economically and ecologically unfeasible. The second, because the basic design was that of an educational facility, was likewise unlikely. The pr oblem with the third was cost. An extra $103 million was needed to finish the project. In the end, the board voted to approve the expenditure, and Trinity River Campus East opened in 2011 as both an educational and architectural marvel. The campus is comprised of four main buildings and is strategically located in downtown Fort Worth near the Fort Worth medical district. Trinity River Campus East offers a simulation hospital, which pr ovides real-world experience to students, reduced impact on clinical sites increased exposure to bedside care situations, and increased opportunities for collaborations and internships. The programs provided at the campus continue to grow as they graduate licensed graduates who are work ready. The high- demand graduates continue to fill an ever-increasing need in the Tarrant County economy — Healthcare. Trinity River Campus East focuses on providing quality healthcare programs as its main educational focus. The programs provided at the campus continue to grow as they graduate licensed graduates who are work ready. 50 51 + VOLUME I LEARNING TCC Connect is located in the West Fork Tower of the Trinity River Complex. The TCC Connect Campus provides students both and eLearning and Weekend College option. Carlos Morales cuts the ribbon on the Tarrant County College Connect Campus. VOLUME I LEARNING TCC Connect Campus History TCC Connect is the sixth campus of the Tarrant County College, opening in 2015. This campus is commonly known as the virtual campus but offers more than traditional virtual campuses. The campus offers two teaching modalities: eLearning and Weekend College. The Connect Campus was named a Top Leader of 60 Online Community Colleges for 2022, by Intelligent.com. eLearning gives students the opportunity to learn in real-time and the distanc e-learning format makes it easier to pursue higher education goals while balancing life responsibilities. The program provides students maximum flexibility in their education and offers 13 fully online associate programs, 24 certificates, and more than 220 online college credit courses in multiple fields including Accounting, Business, Small Business Management, Office Technology, and others. Online courses can be taken in 16-week, 8-week, or monthly-start course lengths Weekend College is designed to allow students the ability to join a c ohort and complete a college degree or transferable core curriculum by attending hybrid classes on the weekends. Students can choose to attend class on Friday or Saturday on a seven-week class term allowing the ability to balance family and work responsibilities with education. TCC Connect provides alternative educational modalities to students through eLearning and Weekend College. TCC Connect is designed to provide online and accelerated learning options to propel you to a successful position in the workplace or move you into a dream career. eLearning gives students the opportunity to learn in real-time and the distance- learning format makes it easier to pursue higher education goals while balancing life responsibilities. +VOLUME I RESEARCH VOLUME I RESEARCH Research c 55 + VOLUME I RESEARCH TCC TRANSFER FAIR Student participating in a Transfer Fair, exploring the future degree pathways that an education from TCC has created. College Level Research The college level Research sub-section focuses on the impact of regional and service area trends on the College both near-term and over the 20-year master plan horizon. This effort grounded the master plan in factual data and quantifiable information to expedite decisions and provide context and rationale for college level recommendations. Through the development of this research for at the college level, the following factors shaped the pr ofile of each campus: — Demographic analysis of the College’s service area provides insight into the college and c ampuses’ growth and characteristics. By understanding these scenarios, enrollment growth effects campus and program potential. — TCC’s commitment to its students and its community is clear in the emphasis in pr eparing students for the workplace. Correlating programs the College offers to trending jobs provides a connection between academics and the workplace. — Evaluation of the College’s current academic programs and student enrollment in each pr ovides an understanding of which programs require further investments. This pinpoints areas where the College has seen success and should continue to invest, and also areas needing growth and further investigation. — Producing the master plan at the college level allows for the inequities between campuses to surface and synthesized into the master plan. 56 57 +Academic Programs and Initiatives Supporting Student Success VOLUME I RESEARCH Academic Programs and Initiatives Supporting Student Success ACADEMIC ADVISING Academic advisors collaborate with students to help them achieve academic and personal success. Advisors are available for face to face, phone or remote virtual appointments. Students may schedule an appointment or walk-in to see an advisor. CAREER SERVICES TCC provides a variety of services to help students and alumni in developing job search skills and in locating employment. The College also works with employers to promote job opportunities for students and alumni with the training and educational experience needed to fill positions in a wide variety of technical and occupational areas. DUAL CREDIT PROGRAMS TCC's Dual Credit Program is a way students can earn college credit while attending high school. Dual Credit students take college-level courses taught by fully credentialed faculty. These courses satisfy high school graduation requirements and provide college credit at the same time. When Dual Credit students graduate from high school, they may have already completed transferable college credits. EARLY COLLEGE HIGH SCHOOL Early College High Schools (ECHS) are usually located on or near a college campus and provide high school students who might not otherwise consider attending college the opportunity to graduate with a high school diploma and 60 college credit hours. GUIDED PATHWAYS A pathway is a group of degree and certificate programs in a career area. The programs share similar interests and skills. Pathways are like road maps. They help students navigate education to reach their destination: a career. PROFESSIONAL CERTIFICATION TESTING CENTER TCC's state-of-the-art testing facility offers high-stakes certification and licensure exams for professional, government, and corporate agencies. TCC also proctor exams for students enrolled in a college or university online course locally and throughout the United States. The Professional Certification Testing Center's mission is to promote student success, serve the community, and excel at administering exams in a secure, high-quality, service-oriented manner. VOLUME I RESEARCH SCHOLARSHIPS The TCC Foundation administers a variety of scholarships, including general Foundation scholarships, community, faculty/staff development and school district partnerships. Academic program scholarships are also available with various award criteria. These awards generally require a specific major. SERVICE LEARNING Service learning promotes leadership, social, and civic responsibility and student involvement as part of a college education. Students participate in an organized service activity that combines academic study, community service, and reflection. STUDENT ACCESSIBILITY RESOURCES The Student Accessibility Resources (SAR) Office provides resources to help students take charge and succeed in their education. Services are provided to any student who is disabled as defined in Section 504 of the Rehabilitation Act and the Americans with Disabilities Act (ADA). SAR offices are located on each campus. SUPPLEMENTAL INSTRUCTION Supplemental Instruction (SI) is a free peer-led program that can help students succeed in historically difficult courses. The guided study sessions encourage students to collaborate with others while also teaching what to learn and how to learn it. With each session, students develop critical thinking, teamwork, and communication skills. TRIO STUDENT SUPPORT SERVICES TRIO Student Support Services (TRIO SSS) is a federally funded program created more than 50 years ago to help students who are first generation, low-income, or students who have a documented disability successfully earn a college certificate and/or degree. VETERANS SERVICES TCC was named a Top School by the 2018 Military Advanced Education and Transition (MAE&T) Guide to Colleges and Universities, and ranked as the number two community college in the nation by the Military Times magazine award, Military Times Best: Colleges 2018, formerly known as Best for Vets: Colleges. TCC offers quality support and services to help veterans succeed with their education, as well as their career and life beyond. EARLY COLLEGE HIGH SCHOOLS High school students engaged in the higher education experience. SUPPLEMENTAL INSTRUCTION Students engaged in teaching and helping other students. 58 59 + VOLUME I RESEARCH HISTORIC AND PROJECTED POPULATION ESTIMATES College Catchment Area VOLUME I RESEARCH Demographics Study Service Area Trends Facility Programming and Consulting (FPC) was engaged as a component of the master planning team to provide analysis of the student population at all its campus locations, while focusing on the enrollment, programs, and population makeup of the main campus. As part of the master planning effort, FPC provided high level population projections of the region, including the Tarrant County College service area and the taxing district. Analysis includes calculating the compound annual growth rate (CAGR) to better understand where higher/lower growth rate is anticipated in the next decade. In addition, an enhanced demographic study of each campus, including TCC Connect, was provided, which includes: — Diagrams overall college density by student residence by loc ation, zip code, and by census block. — Identifies the “catchment area” for the college (catchment area is the ar ea/boundary derived by calculating the cumulative 80% of all students enrolled at Tarrant County College from the top student resident zip codes). — Identifies change in growth of the projected age 18 to 64 population of s ervice area over the next ten years by census block group. — Data on student enrollment and residence. To understand curr ent and future demographics at the college, FPC used historic and five-year projected demographic data to obtain a 10-year projection utilizing a simple trend analysis. — Unless noted otherwise, data and maps found in this section capture students who were reported to be associated with a specific campus; this data includes all learning modes: on- campus, exclusively 100% online, and/or a combination (hybrid) of both. This is an un-duplicated headcount. — A market study with related detailed information on race, ethnicit y, income, education, and other data for the catchment area, for the college is also provided. The combined data from the labor market study and the demographic analysis helped to inform various components of the master plan. Demographic analysis of the College’s service area provides insight into the growth and characteristics at both a college and campus level. Understanding scenarios for enrollment growth effects the potentials of different campuses and programs. This analysis grounded the master plan in quantifiable information for the planning recommendations. 60 61 +VOLUME I RESEARCH VOLUME I RESEARCH MARKET SUMMARY MARKET SUMMARY College Catchment Area College C atchment Area 62 63 +VOLUME I RESEARCH VOLUME I RESEARCH EDUCATION SUMMARY SHARE OF POPULATION BY AGE COHORTS, 2011 – 2031 College Catchment Area College Catchment Area 64 65 +VOLUME I RESEARCH VOLUME I RESEARCH 2010 POPULATION AGE 18 – 64 2021 POPULATION AGE 18 – 64 ZIP Code Analysis ZIP Code Analysis 66 67 +VOLUME I RESEARCH VOLUME I RESEARCH 2031 POPULATION AGE 18 – 64 POPULATION GROWTH AGE 18 – 64, CAGR 2021 – 2031 ZIP Code Analysis ZIP Code Analysis 68 69 + VOLUME I RESEARCH TARRANT COUNTY COLLEGE CATCHMENT AREA Dallas, North Central Texas, Tarrant WDAs VOLUME I RESEARCH Labor Market Study Process Education to Workforce Analysis COLLECT AVAILABLE DATA BY OCCUPATION Data collected from Texas Workforce Commission (TWC) for each of the three Workforce Development Areas (WDAs) with which Tarrant County College borders and/or intersects: — North Central Texas — Dallas County — Tarrant County IDENTIFY THE TOP 20 OCCUPATIONS Occupations chosen which require education of an Associates Level Degree or less for each of the following categories: — Highest Aggregate Job Change — Highest Annual Growth — Highest Annual Turnover — Highest Average Annual Wage CORRELATE TWC OCCUPATIONS WITH TARRANT COUNTY COLLEGE HISTORIC ENROLLMENT/AWARD DATA (2015-2020) Information provided by Tarrant County College and the Office of Institutional Research and Effectiveness, supplemented by THECB data, compared across all three WDAs. CIPs were associated with TWC SOC. IDENTIFY REMAINING OCCUPATIONS Occupations for which Tarrant County College offers degree/ certificate programs, but which did not “make the cut” based on selected criteria for top 20 occupations. These occupations were not included in the study. All of Tarrant County College’s average enrollment and award totals by program were linked to occupations using the National Center for Education Statistics SOC to CIP crosswalk. This links programs that Tarrant County College offers to in-demand jobs in the local community. 70 71 +VOLUME I RESEARCH VOLUME I RESEARCH HIGHEST PAYING OCCUPATIONS Dallas, North Central Texas, Tarrant WDAs FASTEST GROWING OCCUPATIONS 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs 72 73 +VOLUME I RESEARCH VOLUME I RESEARCH OCCUPATIONS ADDING THE MOST JOBS 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs OCCUPATIONS WITH THE GREATEST ANNUAL OPENINGS 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs 74 75 + VOLUME I RESEARCH TRINITY RIVER CAMPUS VISIT Master plan team visiting the Trinity River Campus, touring the Idea Store and exploring the connection between the campus and downtown Fort Worth. Campus Level Research The campus level Research sub-section focuses on the impact of existing conditions specific to each campus. This included visits to each campus by the master plan team and meeting with campus leadership and stakeholders to gain valuable background on perceived successes and opportunities for improvement. This effort provided context and rationale for the master plan’s college level recommendations. Through the development of this research for each campus, the following factors shaped the pr ofile of each campus: — Demographic analysis of the campuses service area provides insight into the growth and char acteristics for both campus facilities and specific programs. — Correlating programs the campus offers to trending jobs in distinct categories pr ovides a clear connection between success in academics and the workplace. — Evaluation of the College’s academic programs and student enrollment in each pr ovides an understanding of which programs need to have further investments. — Analysis of the existing space on each campus and its utilization. Further analysis can reveal potential sources and generate different planning scenarios. — Gap analysis identifies these inequities between campuses and synthesizes them into needs t o be accommodated into the master plan. Gaps were also identified during meetings with campus leadership and stakeholders. 76 77 + VOLUME I RESEARCH VOLUME I RESEARCH Central campus green and public space. South Campus Campus Background The first and oldest campus apart of Tarrant County College, the South Campus, is comprised of numerous one and two story buildings. Having a high quantity of smaller sized buildings allowed the campus to create a more typical college campus feel, creating a network of paths and green spaces between the buildings with all parking on the exterior of the campus. However, the minimal square footage of many of the buildings has created functional and operational challenges on the campus and the quantity of front facing buildings creates a challenge for future students to locate the “front door” of the campus. Looking towards the future, all new construction, existing building renovations, and functional reconfigurations should further the campus’ mission to produce career-ready graduates. The master plan team’s tour with the campus President and their faculty and staff established a backgr ound of the campuses identity and the direction that the campus leadership had in mind. The history of the campus and the identity that has been established was deemed integral to the success of the campus in the future. However, aging infrastructure was recognized as being Automotive Building shop space. Library and campus green, central campus elements. a limiter for both student and community engagement. Future program gro wth is also constrained by current available facilities and the lack of an accessible experience for potential students. The master plan programming for the future of the South Campus should include the construction of new facilities aimed at meeting the curr ent and future needs of technical programs, general instruction, and the creation of an Onboarding Building consolidating student enrollment and support services. While the overall square footage of the existing campus building stock is sufficient to support current enrollment, the size, configuration, and functionality of a portion of the space does not. Changing pedagogy, section size, and program needs has led to the need to evaluate some existing buildings in terms of their ability to be renovated and support changing instructional needs. This evaluation has identified campus buildings which may be better served by demolition and replacement rather than renovation. “Our faculty and staff work efficiently and effectively for the sole purpose of serving students and helping to make a difference in their lives, and together we ensure that they are prepared for further education and productive careers. Here students will find a place that opens its doors to all individuals who are eager to learn, in an environment where ideas are openly exchanged, and diverse perspectives are respected and appreciated. In the end, we want our students to excel.” — Dr. Lufkin 78 79 + VOLUME I RESEARCH VOLUME I RESEARCH SOUTH CAMPUS SITE PLAN Master Plan Landscape Plan South Campus Key Campus Statistics Year Constructed: 1967 Campus Size: 145.40 acres in South Fort Worth Building Inventory: 36 Buildings, 687,601 SF Campus President: Dr. Lufkin Student Enrollment: 7,475 students Signature Programs: — Architecture Technology — Automotive — Computer-Aided Drafting — Construction Management — Electronics Technology — Gaming — Heating, Air Conditioning, and Refrigeration — Teacher Education — Welding 0' 100' 200' 400' North GAP ANALYSIS Gap analysis identified inequities between campuses and synthesized them into needs to be accommodated into the master plan. Work sessions with faculty and staff at each campus helped identify deficiencies and desired improvements. The work session with the campus faculty and staff provided an opportunity for an iteration of the phases to be reviewed and the campus priorities to be stated. This opportunity yielded the valuable feedback that the campus was lacking in: — A defined front entry. — A consolidated “One-Stop Shop” for students with Onboarding, student services, and a W elcome Center. — The importance of the campus identity and the strong campus framework were also reiterated. Both of these were identified as being integral to the campus’ character and quality. +JOE B . R U S H I N G R O A D C . A . R O B E R S O N B O U L E V A R D CA M P U S D R I V E VOLUME I RESEARCH VOLUME I RESEARCH LEGEND Good Facility Condition Fair Facility Co ndition SECH Poor Facility Condition SBSW Critical Facility SBSA SHPE Condition SBSP SNUR SELT SETC SETC SAUT SSCI SCLC SHSC SELE SACA STEC SBUS SACB SMTH SACR South Campus Facility Condition Assessment Report Based on the facility condition assessment provided by Jacobs, the critical buildings on this campus were built around 1967 and are nearing the end of their projected life span. Based on the Facility Condition Index (FCI), there are 12 buildings on this campus that ha ve a good FCI score. The majority of the building on this campus are in the fair and poor FCI score ranges. FCI Categories: —Good: 0 – 0.02 —Fair: 0.02 – 0.05 —Poor: 0.06 – 0.19 —Critical: +0.20 Critical Buildings: The master plan phasing addresses the following critical issues: —SACT Building (0.42) SACCSERS SLIB SACD SMTC SACT SPAC SFOB —Phase 1 — Construct new Onboarding Building —SFOE Building (0.34) SFOC SFOA SBKS SFOD SSTU SART SMUS SFOE SREC SFOF FACILITY CONDITION ASSESSMENT DIAGRAM Existing Conditions Site Plan 0' 100' 200' 400' North 80 —Phase 2 — Renovate Enrollment Services Building —Phase 3 — Construct new Automotive Building —Phase 4 — Renovate existing Automotive Building —Phase 6 — Renovate Performing Arts Center —Phase 8 — Renovate Student Union —Phase 10 — Renovate Nursing and Health Science Buildings —Phase 13 — Renovate Science Building Facility Condition Index (FCI) is the total cost of needed building repairs and renewal divided b y the current cost of replacing the building. Each building’s FCI score reflects the current condition of the building: Good, Fair, Poor, or Critical. —SFOB Building (0.31) —SFOA Building (0.29) —SFOD Building (0.29) —SAUT Building (0.22) —SPAC Building (0.20) Poor Buildings: —SART Building (0.19) —SELE Building (0.15) —SERS Building (0.15) —SMTH Building (0.11) 81 +JOE B . R U S H I N G R O A D C . A . R O B E R S O N B O U L E V A R D CA M P U S D R I V E VOLUME I RESEARCH VOLUME I RESEARCH LEGEND Utilization >75% Utilization 50% – 75% SECH Utilization 0% – 50% SBSW Program Defined SBSA SHPE Utilization Not Assignable SBSP SNUR SELT SETC SETC SAUT SSCI SCLC SHSC SELE SACA STEC SBUS SACB SMTH SACR South Campus Space Utilization Study Based on overall building utilization, there are zero buildings on this campus that have a good overall utilization. Out of the over twenty buildings that serve students of the South Campus, the majority that are scheduled contain space scheduled for classrooms or labs that are below the utilization target. Utilization Categories: —Good: +75% —Fair: 50% – 75% —Poor: 0% – 50% —Program Specific Utilization: Utilization standards not applied Overall building utilization identifies current opportunities within existing campus class lab and classr oom inventory to determine if they are capable of supporting current and projected enrollment or if additional inventory is needed. Analysis utilizes course schedule data from the Fall 2021 semester. —Not Assignable: No Class Labs or Classrooms Poor Utilization: SACCSERS SLIB SACD SMTC SACT SPAC SFOB —SCLC Building (0%) SFOC 82 83 SPACE UTILIZATION DIAGRAM Existing Conditions Site Plan SFOA SFOD SFOF SBKS SFOE SSTU SMUS SART SREC 0' 100' 200' 400' North Primary limiters to the higher utilization of classrooms and labs can be attributed to size, configuration, lack of upgraded technology, and functionality of many of the buildings that are original to the campus. The utilization of the Automotive and any program that is part of the Center of Excellence for Energy Technology should be considered separately from other programs based on the unique programming requirements. —SPAC Building (7.3%) —SACR Building (8%) —SACC Building (11.5%) —SART Building (12%) —SHSC Building (13.2%) —SREC Building (16%) —STEC Building (20.3%) —SMUS Building (20.6%) Program Specific Utilization: —SAUT Building 84 85 +VOLUME I RESEARCH VOLUME I RESEARCH MARKET SUMMARY Campus Catchment Area MARKET SUMMARY Campus Catchment Area 86 87 +VOLUME I RESEARCH VOLUME I RESEARCH EDUCATION SUMMARY Campus Catchment Area HISTORIC AND PROJECTED POPULATION ESTIMATES Campus Catchment Area 88 89 +VOLUME I RESEARCH VOLUME I RESEARCH SHARE OF POPULATION BY AGE COHORTS, 2011 – 2031 Campus Catchment Area TOTAL FALL ENROLLMENTS PROJECTIONS Campus Cat chment Area 90 91 +VOLUME I RESEARCH VOLUME I RESEARCH 2021 POPULATION AGE 18 – 64 ZIP Code Analysis POPULATION GROWTH AGE 18 – 64, CAGR 2021 – 2031 ZIP Code Analysis 92 93 +VOLUME I RESEARCH VOLUME I RESEARCH STUDENT RESIDENCE DENSITY BY ZIP CODE TCC has no on-campus student residences STUDENT RESIDENCE DENSITY HEAT MAP TCC has no on-campus student residences 94 95 +VOLUME I RESEARCH Campus Access Vehicular and Pedestrian Circulation VEHICULAR CIRCULATION The campus is bound by four roadways, Campus Drive to the West, Joe B. Rushing Road to the North, C.A. Roberson Boulevard to the East, and Interstate Highway 20 to the South. Each of the roadways offers vehicular connectivity to the campus. None of the proposed phases would negatively impact vehicular paths and/or traffic with the exception of the construction material drop offs and the staging of construction materials. VOLUME I RESEARCH PEDESTRIAN CIRCULATION There are no sidewalks that connect to any of the main roadways, so pedestrian connectivity will originate from either the parking lots or drop off areas. There are public bus stops located on the East side off of C.A. Roberson Boulevard, on the North side off of Joe B. Rushing Road and on the South side of the campus off an internal drive. INTERST A TE 20 H W Y 2 8 7 C A M P U S D R . OA K GR O V E RD . WI C H I T A ST . F O R E S T H I L L D R . CAMPUS ACCESS FRAMEWORK Vehicular and Pedestrian Traffic 96 97 + wccm wm .. u llt)' College• ,~ Tarranl Co AEACH. CORGAN VOLUME I RESEARCH Student using models and drafting as part of the Architectural Technology program. VOLUME I RESEARCH Labor Market Analysis South Campus Occupational Programs Fastest Growing Occupations 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #5: Web Developers Occupations Adding the Most Jobs 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #5: First-Line Supervisors of Office and Administrative Support Workers — #10: First-Line Supervisors of Mechanics, Installers, and Repairers Highest Paying Occupations Dallas, North Central Texas, Tarrant WDAs — #11: Web Developers — #12: First-Line Supervisors of Mechanics, Installers, and Repairers Occupations With Greatest Annual Openings 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #4: First-Line Supervisors of Office and Administrative Support Workers — #5: First-Line Supervisors of Mechanics, Installers, and Repairers FPC provided data related to job demand, need, and growth within the College’s service area and the Greater Dallas- Fort Worth-Arlington, Texas, MSA (Metropolitan Statistic Area). This study was cross- walked with the programs that the South Campus offers and the available top 20 occupations were outlined. Student using the Library to study. Professor utilizing hands on learning with Automotive program students. 98 99 + ,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN VOLUME I RESEARCH View of a campus quad near the Library. Interior of the Theater in the Fine Arts Building. Clock tower at the Student Union, a defining campus landmark. VOLUME I RESEARCH Northeast Campus Campus Background The Northeast Campus is the second oldest campus within the college and shares the Tarrant County College joint commitment to being One College, Student Ready, Serving the Community. The campus has been serving students for over 50 years on their 186.79-acre site. The campus consists of 17 buildings housing various technical, academic, early education, and community programs ensuring there is a place for everyone at the Northeast Campus. Looking towards the future, all new construction, existing building renovations, and functional re-configurations should further the campus’ mission to support all learners in achieving their goals. The master plan team’s tour with the campus President and their faculty and staff established a background of the campuses identity and the direction that the campus leadership had in mind. Emphasis was placed on the people that make up the campus, from the students to the faculty and staff. The importance of involvement in both the campus and the community were underlined by the academic and student-centric programs that the campus engages in. The diversity of the student body and the pride that the students have in the campus was identified as a key factor in the success of the campus. Additionally, the condition of the existing facilities was identified as something that directly effects overall campus morale. The leadership believes that students deserve a high quality experience and that the spaces should enable students to achieve their dreams. The master plan programming for the future of the Northeast Campus should take into account the construction of new facilities aimed at meeting the current and future needs of technical programs, Early College High School, Student Support Services, and the development of a Learning Commons. Renovations, additions, and new construction should focus on implementing the College initiative of 3 Goals and 8 Principles. The master plan will further enhance the existing cohesiveness on campus by creating and enhancing pedestrian paths, outdoor spaces, and connections between the existing buildings and any new construction. “Our faculty and staff take pride in working here to support learners in bringing their goals to fruition. We are TCC proud and resolute in our commitment to support students in completing the goals they set for themselves. We also take pride in a long history of working lockstep with our community partners – civic, educational, economic development, and corporate – to ensure exceptional experiences for TCC students and families.” — Dr. Ayers-Palmore 100 101 + Tarran , WCCE55 wm•• AEACH. ~ I Cou11ty College· CORGAN GRAPEVINE HIGflWAY (1 ''; \,"~--_#_.,/ VOLUME I RESEARCH VOLUME I RESEARCH NORTHEAST CAMPUS SITE PLAN Master Plan Landscape Plan Northeast Campus Key Campus Statistics Year Constructed: 1968 Campus Size: 186.79 acres between North Richland Hills and Hurst Building Inventory: 23 Buildings, 665,862 SF Campus President: Dr. Ayers-Palmore Student Enrollment: 9,968 students Signature Programs: — Child Development — Dental Hygiene — Information Technology — Teacher Education — Visual Arts — World Languages 0' 100' 200' 400' North GAP ANALYSIS Gap analysis identified inequities between campuses and synthesized them into needs to be accommodated into the master plan. Work sessions with faculty and staff at each campus helped identify deficiencies and desired improvements. The work session with the campus faculty and staff provided an opportunity for an iteration of the phases to be ranked based on importance of the work completed during that phase to the state of the campus. This opportunity yielded the valuable feedback that the campus was lacking in: — A defined campus front entry. — A consolidated “One-Stop Shop” for students with Onboarding, student services, and a Welcome Center. — The science buildings were also identified as being sub-par and an urgent issue to resolve to improve campus perception and student service. + --] r -= _, L_ Li I J LIO,-,_, I~' L_l ( -,,, ¢__) \ l --J \ "'.-\ ) '- 1"L r -_l r-·-, ~ .. ,. I _., ( ') ()/ 07 ,•; ,: I . - , ,, __ ;', _/ .,,,--, ,, i i' I b l1fl ,~ -7 ,I I I ,.___,l ,, ,_ ~t) _I ' ' -:: / :-- . I~ I I -f, , c~ __ =_:"('L\/_-_ -_-]_-;_ -=----=-I ~=_Jlt ~ 1-1" .--I R~L. [ :,:,: ,-f-_, r _ ___ll__ lu ~r~rr ~,11 B :• o I _) I - -__ ___:_____::_-=-::::':::::__' ; r--_,, -/ j " ~/ \._ J-__ --~=-==- I ■ ■ ■ ■ ,~ Tarronl C wccm wm.:ullt)' C ollege• AEACH. CORGAN HAR W O O D R O A D VOLUME I RESEARCH LEGEND GRAPEVINE HIGHWAY Good Facility Condition Fair Facility NBSA NDPP Condition NMPC NDPW NBSA NDSC Poor Facility Condition Critical Facility NDPA Condition NSCW NTAB NHSC NSCE NHPE NACB NFAC NIMC NLIB NBSS NFAB NCAB NADM NSTU FACILITY CONDITION ASSESSMENT DIAGRAM Existing Conditions Site Plan 0' 100' 200' 400' North VOLUME I RESEARCH Northeast Campus Facility Condition Assessment Report Based on the facility condition assessment provided by Jacobs, the most critical buildings on this campus were originally built between 1968 and 1972 and are ending their projected life span. Based on the Facility Condition Index (FCI), there are 11 buildings on this campus that have a good FCI score. The majority of the proposed work on this campus is renovation of existing buildings to accommodate present programs and make the buildings operate more efficiently. The master plan phasing addresses the following critical issues: —Phase 1 — Construct new Science Building —Phase 2 — Renovate Science Buildings —Phase 6 — New Academic Classroom Building —Phase 8 — Addition to Health & Physical Education Building —Phase 9 — Renovate Communication Arts Building Facility Condition Index (FCI) is the total cost of needed building repairs and renewal divided by the current cost of replacing the building. Each building’s FCI score reflects the current condition of the building: Good, Fair, Poor, or Critical. FCI Categories: —Good: 0 – 0.02 —Fair: 0.02 – 0.05 —Poor: 0.06 – 0.19 —Critical: +0.20 Critical Buildings: —NFAC Building (0.38) —NHPE Building (0.29) —NBSA Building (0.24) —NSCE Building (0.23) —NCAB Building (0.21) —NACB Building (0.20) Poor Buildings: —NFAB Building (0.18) —NHSC Building (0.18) —NADM Building (0.17) —NSCW Building (0.13) —NLIB Building (0.09) 102 103 + I '- --] r -= _, L_ 1"L r -_l Li r-·-, ~ __ ;', ~/ \._ J-__ --~=-==- I ■ ■ ■ ■ ■ ,~ TarronlC wccm wm.:ullt)' College• AEACH. CORGAN HAR W O O D R O A D VOLUME I RESEARCH LEGEND GRAPEVINE HIGHWAY Utilization >75% Utilization NBSA NDPP 50% – 75% NMPC NDPW Utilization NBSA NDSC 0% – 50% Program Defined NDPA Utilization Not Assignable NSCW NTAB NHSC NSCE NHPE NACB NFAC NIMC NLIB NBSS NFAB NCAB NADM NSTU SPACE UTILIZATION DIAGRAM Existing Conditions Site Plan 0' 100' 200' 400' North VOLUME I RESEARCH Northeast Campus Space Utilization Study Based on overall building utilization, there are zero buildings on this campus that have a good overall utilization. Out of the 17 buildings that serve students of the Northeast Campus, the majority that are scheduled contain space scheduled for classrooms or labs that are below the utilization target. Overall building utilization identifies current opportunities within existing campus class lab and classroom inventory to determine if they are capable of supporting current and projected enrollment or if additional inventory is needed. Analysis utilizes course schedule data from the Fall 2021 semester. Further analysis of the existing spaces on the Northeast Campus indicate that primary limiters to the higher utilization of classrooms and labs can be attributed to the lack of upgraded classrooms and classrooms that are undersized or lack the proper technology. The utilization of the Dental Hygiene and EMS programs should be considered separately from other programs based on the unique programming requirements. Utilization Categories: —Good: +75% —Fair: 50% – 75% —Poor: 0% – 50% —Program Specific Utilization: Utilization standards not applied —Not Assignable: No Class Labs or Classrooms Poor Utilization: —NIMC Building (25.5%) —NACB Building (35.9%) —NHPE Building (43.2%) —NBSS Building (46.6%) —NSCW Building (48.4%) —NSCE Building (49.6%) —NFAB Building (48.7%) —NCAB Building (49.5%) Program Specific Utilization: —NHSC Building 104 105 106 107 +,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN □FACILITY PROGRAMM ING AND CO NSULT ING Market Summary 2021 v TCC: NE Campus Catchment Area, 2021 F V SOURCE: ESRI I Page 1 of2 □FACILITY PROGRAMMING AND CONS U LTI NG Market Summary 2021 v TCC: NE Campus Catchment Area , 2021 F V SOURCE: ESRI I Page 2 of2 Total Population Businesses and Employment 2010 934,900 Sector PCT Businesses Employmen1 PCT Occupations Age Groups 2021 Race/ Ethnicity 0 Businesses Retai l 14.9% 5,500 67,740 2031 10-YrProjected CAGR ► 1.6% 0 :51 4 Population Age 18-64 0 15-17 593,800 • 2010 18-34 0 2021 35-64 0 2031 2:65 10-Yr Projected CAGR ► 1.3% • Employment Accommodation 7.6% 2,830 49,030 Diversity 71.7 Health Care Index 8.5% 3,160 40,710 • White Collar • Manufacturing 3.3% 1,210 34,330 8.3% 0 White Educatio n Blue Collar An estimated 36,980 2.4% 890 34,130 8.2% 0 Black businesses are located within Other Serivces 11.7% 4,310 27,790 6.7% 0 Services 0 Asian the Market Area and t h ey Construction 7.3% 2,690 22,430 5.4% 0 employed approximately Professional 9.1% 3,360 22,260 5.4% Other 414,870 workers. Wholesa le 2.7% 1,000 17,940 4.3% Q Hispanic Government 1.3% 480 17, 130 4.1% Management Finance 5.8% 2,140 15,720 3.8% Educational Attainment No High School High School Degree or Equivalent Households Some College, No Degree Transportation 2.1% 770 15,620 3.8% Professional In terms of employment, the Retail Trade sector was the Administrative 3.4% 1,250 13,690 3.3% Sales NOTE: Pe!sons of Hispanic Origin may be of any race. I Th e Diveisitylndex mrosues the p1000bil iy Real Estate 5.5% 2,040 13,450 3.2% tllat ~vo people from the same M!!l will be f,omdiffeient race/ ethnic groups . A Diveisily Index largest in t h e *M arket Area Admin 1111:re;:-f)f-!i h1 J1r1 II lo 1{K> as llte Iq11lal11H1 1s evml y d1•.11ct-x:l 11llo l wc1 f)r rrKN~ ,a:P., l-!lhr11c gn11IIis with app roxi mately 67,740 Informatio n 1.8% 660 10,490 2.5% Farming 0.1% worke rs. This sector Enterta inment 1.8% 670 7,490 1.8% Income accounted for an esti mat ed Unclass ified 10.1% 3,730 2,220 0.5% Construction 4.3% 415,400 Associates Degree Total 46.4% Bachelor's Degree $266,100 Home Value Graduate Degree $78,000 5500 businesses. Headquarters 0.3% 120 1,070 0.3% Maintenance .3.1% Median HH Income Mining 0.2% 70 780 0.2% Production Utilities 0.1% 30 590 0.1% $38,400 Agricultu re 0 .2% 80 270 0.1% Transportation 8.9% Per Capita Income • Market Area: Is the same as the region refe renced in the YELLOW bar highlighted at the top of the page VOLUME I RESEARCH VOLUME I RESEARCH MARKET SUMMARY MARKET SUMMARY Campus Catchment Area Campus Catchment Area 108 109 + Education Summary □FACILITY PROGRA MMING AND CO N S U LT ING 202 1 v T C C : N E Campus C atchment A rea , 2 021 F Education Enrollment Total Enrolled in School Not Enrolled in School 304,700 736,500 Percent in/ Not in School 29.3% 70.7% School Enrollment by Grade Level 0 PRE-Preschool -KND-Grade 12 0 Higher Ed SOURCE: 2015-2019 American Com munity S urvey Percent of Enrolled 70.8% K-12 17.4% College 5.1% Grad School V SOURC E: ESRI , ACS Household Expenditures on Education Total Spending Average/ Household Index Spending Category College Tuition K-12 Tuition Other School Supplies Rental of Books/ Equipment Supplies for College Test Preparation/ Tutoring Services Supplies for K-12 Schools Vocational Tuition Tuition for Other Schools Supplies for Preschool Supplies for Vocational Schools $796,014,900 $1,916 111 Total Expenditures $472,450,500 $109,862,000 $29,907,000 $26,776,300 $22,071,200 $11,723,000 $10,781 ,800 $7,062,900 $6,409,300 $1,524,700 $450,800 I Page 1 of 1 Average/ Index Household $1,137 108 $265 111 $72 118 $64 116 $53 121 $28 108 $26 122 $17 120 $15 109 $4 117 $1 118 NOTE: A n index of 100 re flect s t he national average. An i ndex of 120 s uggests spending is 20 percent above t he average. SOURCE: ESRI and Fac ility Prog ramming and Consu lting 1,600,000 1,400,000 1,200,000 1,000,000 953,300 Historic Population Estimates ,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN 800,000 ----812,600 710,800 --------------- 604,4 A~QQ~-------------------600,QOQ : 400,000 222,900 268,800 -----------------------318,300 200,000 I I 0 42,500 46,200 ------------------------ - - - - --------- - ---- - - -50,800 2011 2013 2015 2017 2019 2021 2023 2025 202 7 2029 2031 -2011-21 Total Popu lation CNG: 184,600, 19.4 % or CAGR 1.8% 11 2021-31 CNG: 191,800, 16.9% or CAGR 1.6% -2011-21 Population Age 18-64 CNG: 106,400, 17.6% or CAGR 1.6% 11 2021-31 CNG : 101,700, 14.3% or CAGR 1.3% -2011-21 Population Age 18-34 CNG: 45,900, 20.6% or CAGR 1.9% 11 2021-31 CNG: 49 ,600, 18.4% or CAGR 1.7% -2011-21 Population Age 15-17 CNG: 3,700 , 8.8% o r CAGR 0.8% 11 2021-31 CNG: 4,600, 9.9% or CAGR 1.0% VOLUME I RESEARCH VOLUME I RESEARCH EDUCATION SUMMARY HISTORIC AND PROJECTED POPULATION ESTIMATES Campus Catchment Area Campus Catchment Area 110 111 + 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% SOURCE ES RI and Faci lity Prog ramming and Con sult ing ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. 0 ~ 0 0 0 0 8, ~ 0 0 0 ~ 0 0 ~ 0 0 0 0 0 0 00 CD 0) C"') CD ~ ~ ..... ..... 0 .,, ..... 0) ..... C"') .,, 00 c,; c,; c,; ci ci ci ..... ..... ..... N N N ('I) ('I) ('I) ('I) ('I) ~ ~ ~ ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ':§e. ':§e. ':§e. ~ ':§e. 0 0 &, ':§e. ':§e. 0 0) .. 0 ':§e. ':§e. '#. ~ ;j ~ '° .,, ~ .. ~ 0 ':§e. ':§e. ':§e. ':§e. c,; c,i c,; c,; C"') ..... 0) ~ 0 .. 0 ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ~ .,, .. 0 C"') c,; c,; co N 0) CD C"') 0 0 0 0 ~ ['I') C"') C"') co 00 00 ....: CD .,, "<:I" C"') C"') C") ....: ....: ....: C") ['I') C"') C"') C") ....: ....: ....: ....: C"') C") M M C"') C") C") 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Percentage Point Change by Cohort and 10-YearTime Frames ■ 2010-21 Age ~14 -2011-21: -1.9% II 2021-31 : -0 .9 % ■ 2010-21 Age 15-17 -2011-21: -0.4% II 2021-31: -0 .2% ■2010-21Age18-34-2011-21:0.2% 112021-31:0.3% □2010-21Age35-64-2011-21:-1.2% 112021-31:-1.7% a 2010 -21 Age ~65 -201 1-21: 3.2% II 2021 -31: 2.5% 20,000 18,000 16,00 0 14,000 12,000 10,000 8,000 6,00 0 4,000 2,000 SOURCE: Tarrant County Co ll ege and Facility Programming and Con sulting Historic Enrollment 17,458 ,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. Average of All Enrollment Scenarios Projected Growth (2021-31) ■ Enrollment Change: 2,048 ■ Total Percent Change: 21.5% ■ Annual Growth (CAGR): 1.96% CORGAN 13,185 11,591 10,909 10,678 6,252 201 0 2011 20 12 20 13 2014 2015 2016 201 7 20 18 20 19 2020 2021 2022 2023 202 4 2025 2026 2027 2028 2029 2030 203 1 -Based on 2016-21 Trend Line -2021 Capture Rate (2021 Enrollment/ 2021 College Service Area Population Age 18-64) Held Constant at 0.7% -catchment Area Population Age 18-64, CAGR 2021-31 Held Constant at 1.3% -9-12 Grade Graduate Growth in Catchment Area (Institutions with > 100 Graduates), CAGR 2015-20 Held Constant at 3.3% -Average of all Enrollment Projection Scenarios (minus Trend Line) □FACILITY PROGRAMMING AN D CONS ULT I NG VOLUME I RESEARCH VOLUME I RESEARCH SHARE OF POPULATION BY AGE COHORTS, 2011 – 2031 TOTAL FALL ENROLLMENTS PROJECTIONS Campus Catchment Area Campus Catchment Area 112 113 + @ Northwest ... Northeast @ South @ Southeast @ Trinity River Mile Radius O s Miles 0 10 Miles 0 15 Miles Population Age 18-64 LJ 510,000 -530,000 c:]520,000 -~30,001 Ellis □FACILITY PROGRAMM ING AN D CO N SU LTI NG Information shown hereon is a graphical representation only and based upon available information. Facility Programming and Consulting cannot be responsible for consequences resulting from error or omission in the information and graphical representations made hereon. 0 '-{ Wise 1 I White Slettle I a O 5 10Mi les W Source: ESRI and Facility Programming and Consulting @ Northwest @ Northeast @ South Rendon • Mans • A-isco I • I I The Colont . ' I ,~ Tarranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN Murphy Wylie • • ' I I owlett i • I oo ----------r-~-- @ Southeast @ Trinity River Mile Radius O s Miles 0 10 Miles 0 15 Miles 1 IL-.,;~-' Annual Growth Population Age 18-64 D :;;;0.0% -52.0% -54.0% D :;;;1_0% •53.o% •>4.o% Ellis □FACILITY PROGRAMMING A N D CONS UL T I NG Information shown hereon is a graphical representation only and based upon available information Facility Programming and Consulting cannot be responsible for consequences resu lting from error or omission in the in formation and graphical representations made hereon. VOLUME I RESEARCH VOLUME I RESEARCH 2021 POPULATION AGE 18 – 64 POPULATION GROWTH AGE 18 – 64, CAGR 2021 – 2031 ZIP Code Analysis ZIP Code Analysis 114 115 + □ Catchment Area Catchment Area: Top ZIP Codes comprised of 7,694 students (CUML 79.6%); Capture Rate : 1.1% Mile Radius 0 5 Miles 0 10 Miles Q 15 Miles Students by ZIP Code LJ:50 -:5200 c=J ::;;50 -::;;400 1111 ::;;100 ->400 Ellis Information shown hereon is a graphical representation only and based upon available information. Facility Programming and Consulting cannot be respon~ble for consequences resulting from error or omission in the information and graphical representations made hereon. • I ' I,, ' It ... , .. • ,. • r I I .. I . . , , .. .. , . , . . ' . ... - Piir-ke r ~ Hood I • I I. ~ . I' I White Slett I 0 0 5 10Mi les W Source: ESRI and Facility Programming an d Consu lting Johnson .... Northeast Campus • Little Elm Mile Radius 0 5 Miles 0 15 Miles 0 10 Miles ,~ Tarranl Cou11ty College· ~ WCCE55 wm•• AEACH. Sparse Dense CORGAN • • Information shown hereon is a graphical representation only and based upon available information Facility Programming and Consulting cannot be responsible for consequences resu lting from error or omission in the information and graphical representations made hereon. VOLUME I RESEARCH VOLUME I RESEARCH STUDENT RESIDENCE DENSITY BY ZIP CODE STUDENT RESIDENCE DENSITY HEAT MAP TCC has no on-campus student residences TCC has no on-campus student residences 116 117 +Tarran , WC:CE55 wm .. AEACH. ~ I Cou11ty College· CORGAN VOLUME I RESEARCH Campus Access Vehicular and Pedestrian Circulation VEHICULAR CIRCULATION The Northeast Campus connects North Richland Hills at its Western edge and Hurst on its Eastern edge. The campus is bordered by several major thoroughfares which provide access points to the campus. Primary access points are from Harwood Road and Grapevine Highway via Interstate Highway 820 and State Highway 183. Tarrant County Jr. College Road and TCC Road provide access to the college campus from Harwood Road, Grapevine Highway, and Precinct Line Road. None of the proposed phases would negatively impact vehicular paths and/or traffic with the exception of the construction material drop offs and the staging of construction materials. PEDESTRIAN CIRCULATION There are no sidewalks along any of the main roads. All pedestrian traffic will come from the parking lots and drop offs. Mass transit options include a stop for the Trinity Metro Bus Route #23 located at the South corner outside the Student Center (NSTU) and the TEXRail Smithfield station. Internally, the normal pedestrian traffic routes should not be interrupted except for master plan phases 3 and 6. Phase 3 consists of a renovation and expansion as well as an expansion to its parking lot. Phase 6 consists of a new academic classroom that will remove the sidewalk, so students that traditionally use these sidewalks will have to navigate around the proposed building or find a different route. VOLUME I RESEARCH TX HIGHWAY 121 CAMPUS ACCESS FRAMEWORK Vehicular and Pedestrian Traffic N. HARDWOOD RD. G R A P E V I N E H I G H W A Y PREC I N C T L I N E R D . DAV I S B L V D . 118 119 + ,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN VOLUME I RESEARCH Students taking notes as part of their course. Students participating in an SI discussion. Dental Hygiene program student practicing their skills in the Dental Hygiene Clinic. VOLUME I RESEARCH Labor Market Analysis Northeast Campus Occupational Programs Fastest Growing Occupations 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #1: Dental Hygienists — #5: Web Developers — #6 Substance Abuse and Mental Health Counselors — #7: Paralegals and Legal Assistants — #12: Tax Preparers Occupations Adding the Most Jobs 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #5: First-Line Supervisors of Office and Administrative Support Workers — #11: Paralegals and Legal Assistants — #15: Dental Hygienists — #16: Real Estate Sales Agents — #18: Property, Real Estate, and Community Association Managers Highest Paying Occupations Dallas, North Central Texas, Tarrant WDAs — #4: Tax Preparers — #5: Property, Real Estate, and Community Association Managers — #9: Dental Hygienists — #11: Web Developers — #19: Photographers — #20: Real Estate Sales Agents Occupations With Greatest Annual Openings 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #4: First-Line Supervisors of Office and Administrative Support Workers — #14: Real Estate Sales Agents — #20: Paralegals and Legal Assistants FPC provided data related to job demand, need, and growth within the College’s service area and the Greater Dallas- Fort Worth-Arlington, Texas, MSA (Metropolitan Statistic Area). This study was cross- referenced with the programs that the Northeast Campus offers and the available top 20 occupations were outlined. 120 121 + ,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN . ~ ~ • ~ v~l "--'! • -• . . . ,:..,. . ;-~ ... ~ VOLUME I RESEARCH Annual Horticulture program Spring plant sale. Fire Academy training using the Fire Field at the Public Safety Training Center. Ongoing construction as part of bond projects involved in the campus redevelopment. VOLUME I RESEARCH Northwest Campus Campus Background The Northwest Campus has focused on putting students first for over 40 years. As teaching methodologies, technology, and student needs continue to change, so have the space needs of the educational facilities that support those functions. As TCC looks forward to 40 more years of serving students, they are also looking at what that means in terms of their current and future facilities. The master plan team’s tour with the campus President and their faculty and staff established a background of the campuses identity and the direction that the campus leadership had in mind. Dr. Blankenbaker made it clear to the master plan team that the defining guide for the campus is to respond to community and employment needs. The tour’s focus on the Public Safety Training Center and Horticulture facilities was based on programs not addressed by ongoing projects. Further development of these programs is restricted by the existing facilities and the lack of updates. In particular, the stagnant nature of the Fire Field and Swift Water program, while unique elements, are not drivers for community members to come back and engage with. These unique facilities provide potential community involvement and revenue opportunities, but lack of attention has lessened their usage. Future program success was also established on the growth of the facilities despite constant increase in student and community member interest/enrollment. The master plan programming for the future of the Northwest Campus should take into account the construction of new facilities aimed at meeting the current and future needs of the Horticulture program, the Public Safety Training Center, and future enrollment growth. In addition, renovation, expansion, and reprogramming of the WHPE which provides resources for dance, physical education and aquatic programs should be addressed. The master plan will also focus on creating a cohesive campus and working to create paths, outdoor spaces, and connections between the existing buildings and any new construction. “TCC Northwest is committed to providing a student- centered environment and focusing our resources on student learning, development, and success. Our college has over 155 student organizations providing you an opportunity to make connections and develop leadership skills that translate to professional careers. We hope that during your time at TCC, you experience a sense of community, respect, and belonging both in and out of the classroom.” — Dr. Blankenbaker 122 123 + MARINE CREEK LAKE --------- \_____ ---- r ~ ~---------su 1L□ 1NG 4 _3) ,__ _ ---_ -------=V:----.::~-::==----~\ ,,...-----------.................. _ --------- I I I /1 I I l I , i I I l I I IU _) ~ i ~'l~ -'-'--~---\ \-~--~~--~~-~~-~~---~~~ ,~ Tarranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN VOLUME I RESEARCH VOLUME I RESEARCH NORTHWEST CAMPUS SITE PLAN Master Plan Landscape Plan Northwest Campus Key Campus Statistics Year Constructed: 1975 Campus Size: 187.50 acres in North Fort Worth Building Inventory: 38 Buildings, 523,460 SF Campus President: Dr. Blankenbaker Student Enrollment: 7,372 students (shared with Alliance West Site) Signature Programs: — Aviation — Criminal Justice — Dance — Fire Technology — Horticulture — Nondestructive Inspection, Testing, and Evaluation 0' 100' 200' 400' North GAP ANALYSIS Gap analysis identified inequities between campuses and synthesized them into needs to be accommodated into the master plan. Work sessions with faculty and staff at each campus helped identify deficiencies and desired improvements. The campus visit with the campus faculty and staff provided an opportunity for the master plan team to hear items that the campus wanted to focus future development efforts on. This opportunity yielded the valuable feedback that the campus was lacking in: — A defined identity for the Public Safety Training Center. — Many of the facilities and site infrastructure for the Public Safety Training Center are sub-par and an urgent issue to resolve to improve campus perception and student service. — The Horticulture program also was identified as needing attention. +~~ Tnrrant County Co llegec ~ sucass wn 1-1N REACH. CORGAN ■ ■ ■ ■ DRIVE COLLEGE WFSK W F S C W F S S WACB WFSE WATB VOLUME I RESEARCH VOLUME I RESEARCH LEGEND Good Facility Condition WFMP Fair Facility Condition WCJD Poor Facility Condition WCTT Critical Facility WCJC WFSJ Condition WFSIWCJR WPFR WFSF WFSH WFSG WFSB WFSD WFSA WFSV WMBD WMBC Northwest Campus Facility Condition Assessment Report Based on the facility condition assessment provided by Jacobs, the most critical buildings on this campus were originally built between 1975 and 1988 and are ending their projected life span. FCI Categories: —Good: 0 – 0.02 —Fair: 0.02 – 0.05 WMBBWMBA —Poor: 0.06 – 0.19 Based on the Facility Condition Index (FCI), there are 29 buildings on this campus that have a good FCI score. The majority of the proposed work on this campus is renovation of existing buildings to accommodate present programs and make the buildings operate more efficiently. —Critical: +0.20 WHPE BUILDING 1 WGHB Critical Buildings: WBSA WHPB —WATB Building (23.85) MARINE CREEK LAKE —WGHA Building (0.44) The master plan phasing addresses the following critical issues: —WCJR Building (0.33) BUILDING 3 —Phase 1 — New Building Services Building at Construction Hub BUILDING 2 —Phase 2 — Renovate Building Services Building Poor Buildings: BUILDING 4 —Phase 3 — New Public Safety Training Center Building —WCJC Building (0.16) —Phase 5 — Construct new Reality-based Training Center —WACB Building (0.11) —Phase 7 — Renovate Fire Service Training Center —WGHB Building (0.10) —Phase 9 — Renovate Academic Classroom Building —WFSC Building (0.07) Facility Condition Index (FCI) is the total cost of needed building repairs and renewal divided by the current cost of replacing the building. Each building’s FCI score reflects the current condition of the building: Good, Fair, Poor, or Critical. FACILITY CONDITION ASSESSMENT DIAGRAM Existing Conditions Site Plan 0' 100' 200' 400' North 124 125 +~~ Tnrrant County Co llegec ~ sucass wn 1-1N REACH. CORGAN ■ ■ ■ ■ DRIVE COLLEGE WFSK W F S C W F S S WACB VOLUME I RESEARCH VOLUME I RESEARCH LEGEND Utilization >75% WFMP Utilization 50% – 75% WCJD Utilization 0% – 50% WCTT Program Defined WCJC WFSJ Utilization WFSIWCJR WPFR WFSF Not Assignable WFSH WFSG WFSB WFSD WFSA WFSE WATB Northwest Campus Space Utilization Study WFSV Based on overall building utilization, there are four buildings on this campus that have a good overall utilization. Out of the over 35 buildings on the Northwest Campus, the majority that are scheduled contain space scheduled for classrooms or labs that should be considered separately from other programs based on the unique programming requirements. Utilization Categories: WMBD WMBC —Good: +75% —Fair: 50% – 75% WMBBWMBA —Poor: 0% – 50% —Program Specific Utilization: Utilization standards not applied WHPE —Not Assignable: No Class Labs or Classrooms BUILDING 1 WGHB Overall building utilization identifies current opportunities within existing campus class lab and classroom inventory to determine if they are capable of supporting current and projected enrollment or if additional inventory is needed. Analysis utilizes course schedule data from the Fall 2021 semester. WBSA WHPB Poor Utilization: MARINE CREEK LAKE —WATB Building (0%) —WHPE Building (48.5%)BUILDING 3 BUILDING 2 Separating these certain programs from the defined standards is appropriate at the Northwest Campus because of the requirement of many of these programs. In particular, the Horticulture and Public Safety Training Center programs require unique instructional spaces. Many of these spaces are also utilized as part of Continuing Education, which is not included in utilization. Program Specific Utilization: BUILDING 4 —All Fire Training Field Buildings/Facilities —WCJC Building —WCJR Building —WFSC Building —WFSS Building —WPFR Building SPACE UTILIZATION DIAGRAM Existing Conditions Site Plan 0' 100' 200' 400' North 126 127 128 129 + FACILITY PROGRAMM ING AND C ONSULT IN G Market Summary 2021 v TCC: NW Campus Catchment Area, 2021 F V SOURCE: ESRI I Page 1 of2 Total Population 2010 733,700 Age Groups 2021 Race/ Ethnicity 2031 Diversity 71.5 10-YrProjected CAGR ► 1.8% 0 :51 4 Population Age 18-64 0 15-17 455,600 • 2010 18-34 0 2021 35-64 0 2031 2:65 10-Yr Projected CAGR ► 1.6% Index • White 0 Black 0 Asian 0 Other Q Hispanic Educational Attainment No High School NOTE: Pe!sons of Hispanic Origin may be of any race. I Th e Diveisitylndex mrosues the p1000bil iy tllat ~vo people from the same M!!l will be f,omdiffeient race/ ethnic groups . A Diveisily Index 1111:re;:-f)f-!i h1 J1r1 II lo 1{K> as llte Iq11lal11H1 1s evml y d1•.11ct-x:l 11llo l wc1 f)r rrKN~ ,a:P., l-!lhr11c gn11IIis High School Degree or Equivalent Households Some College, No Degree Income 319,500 Associates Degree $77,200 Total Median HH Income 40.9% Bachelor's Degree $240,100 $34,600 Home Value Graduate Degree Per Capita Income □FACILITY PROGRAMMING A ND C O N S U LTI NG Market Summary 2021 v TCC: NW Campus Catchment Area, 2021 F Businesses and Employment Sector PCT Businesses Employmen1 PCT 0 Businesses Retai l 15.9% 3,690 44,400 • Employment Accommodation 8.4% 1,950 30,480 Education 2.5% 590 23,280 Professional 7.8% 1,800 23,030 8.9% An estimated 23, 160 Health Care 6.8% 1,580 19,950 7.7% busi nesses are locat ed within Manufacturing 3.5% 820 18,420 7.1% the Market Area and t h ey Other Seriv ces 13.0% 3,010 17,910 6.9% employed approximately Construction 8.5% 1,960 15,910 6.1% 260, 160 workers. Wholesa le 3.0% 700 13,840 5.3% Transportation 2.1% 490 12,880 5.0% Government 1.2% 270 9,390 3.6% Finance 5.2% 1,210 7,950 3.1% In t erms of employment, the Retail Trade sector was the Real Estate 5.3% 1,220 6,110 2.3% largest in t h e *Market Area Administrative 3.4% 780 5,680 2.2% with app r oxi mately 44,400 Entertainment 1.8% 410 4,070 1.6% worke rs. This se ctor Information 1.7% 400 3,560 1.4% accounted for an esti mat ed Unclassified 9.0% 2,080 1,470 0.6% 3690 businesses. Mining 0.2% 60 650 0.3% Headquarters 0.3% 70 500 0.2% Utilities 0.1% 20 360 0.1% Agricultu re 0 .3% 60 310 0.1% • Market Area: Is the same as the region refe renced in t he YE LLOW bar highlig hted at the top of t he page ,~ T arranl Cou11t y College· ~ WCCE55 wm•• AEACH. CORGAN V SOURCE: ESRI I Page 2 of2 Occupations Management Professional Sales Admin Farming Construction Maintenance Production Transportation • White Collar Q Blue Collar Q Services 0.1% 9.1% VOLUME I RESEARCH VOLUME I RESEARCH MARKET SUMMARY MARKET SUMMARY Campus Catchment Area Campus Catchment Area 130 131 + Education Summary □FACILITY PROGRA MMING AND CO N S U LT ING 202 1 v T CC: NW C ampus Catchme nt Area , 202 1 F Education Enrollment Total Enrolled in School Not Enrolled in School 236,500 585,700 Percent in/ Not in School 28.8% 71.2% School Enrollment by Grade Level GRAD 11K 0 PRE-Preschool -K ND-Grade 12 0 Higher Ed SOURCE: 2015-2019 A mer ican Commu nity Survey Percent of Enrolled 72.9% K-12 15.9% College 4.6% Grad School V SOURC E: ESRI , ACS Household Expenditures on Education Total Spending Average/ Household Index Spending Category College Tuition K-12 Tuition Other School Supplies Rental of Books/ Equipment Supplies for College Test Preparation/ Tutoring Services Supplies for K-12 Schools Vocational Tuition Tuition for Other Schools Supplies for Presc hool Supplies for Vocational Schools $552,243,000 $1,728 100 Total Expenditures $324,625,300 $80,009,500 $21,650,900 $19,076,800 $15,284,200 $8,377,100 $8,120,100 $5,087,300 $4,654,600 $1,060,700 $318,000 I Page 1 of 1 Average/ Index Household $1,016 96 $250 105 $68 111 $60 107 $48 109 $26 100 $25 120 $16 113 $15 103 $3 106 $1 108 NOTE: A n index of 100 reflect s t he national average. An i ndex of 120 s uggests spending is 20 percent above t he average. ,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN SOURCE ESR I and Facil ity Programm ing and Consu lting 1,200,000 I Historic Population Estimates 1,000 ,000 800 ,000 750,400 600 ,000 -----659,400 562,200 --------------- 465i:,3~00~--------------------- 400 ,000 212,700 ---------------255,600 -------------------------------200,000 174,200 33,800 37,700 ------------------------ - - - - ---- - - - ---- -------43,300 0 2011 2013 2015 2017 2019 2021 2023 2025 2027 2029 2031 -2011-21 Total Population CNG: 166,900 , 22.2% or CAGR 2.0% 11 2021-31 CNG: 181 ,300 , 19.8% or CAGR 1.8% -2011-21 Population Age 18-64 CNG: 96,900, 20 .8% or CAGR 1.9% 11 2021-31 CNG: 97 ,200 , 17 .3% or CAGR 1.6% -2011-21 Population Age 18-34 CNG: 38 ,600, 22.1% orCAGR 2.0% 11 2021-31 CNG: 42 ,900 , 20.1% orCAGR 1.9% -2011-21 Population Age 15-17 CNG: 3,900, 11.5% orCAGR 1.1% 11 2021-31 CNG: 5,600, 14.8% or CAGR 1.4% VOLUME I RESEARCH VOLUME I RESEARCH EDUCATION SUMMARY HISTORIC AND PROJECTED POPULATION ESTIMATES Campus Catchment Area Campus Catchment Area 132 133 + 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% SOURCE ES RI and Faci lity Prog ramming and Con sult ing ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. 0 0 0 ~ 0 0 0 ~ 0 0 0 ~ 0 0 0 0 0 0 8, 0 0 ..... ..,, CIO ..,, CIO "'": ~ CJ? ..... ..... en ..... C") ..,, ..... ..... C") CJ) CJ) CJ) 0 0 0 .... .... .... .... N N N N ('I) ('I) ('I) ('I) ('I) ~ ~ .... .... .... .... .... .... .... ..... ..... ..... .... ..... .... .... ..... ..... ..... ..... ':§e. '#. ':§e. ~ ':§e. ':§e. &, ..... 0 0 0 '#. ':§e. ':§e. ':§e. ~ ':§e. co co ..,, 0 0 ':§e. ':§e. ':§e. co co co -.:I" C") C") ~ 0 0 0 '#. ~ ':§e. ':§e. ':§e. ':§e. a:i ~ co N ..... CIO 0 0 0 C") co co ~ N 0 0 0 0 0 C") C") C") co co ~ ....: ..... .... 0 en CIO CIO C") C") C") C") C") ..... ....: ....: CD ....: ....: CD CD ~ C") C") C") C") C") C") C") C") C") ~ "#-~ ..... ~ ~ r.l 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Percentage Point Change by Cohort and 10-YearTime Frames ■ 2010-21 Age ~14 -2011-21: -1.9% II 2021-31 : -0 .7% ■ 2010-21 Age 15-17 -2011-21: -0.4% II 2021-31: -0 .2% ■2010-21Age18-34-2011-21:0.0% 112021-31:0.1% □2010-21Age35-64-2011-21:-0.7% 112021-31:-1.3% a 2010 -21Age~65 -201 1-21:3.0% 112021-31:2 .1% ,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN SO UR CE : Tarran t Cou nty Coll ege and Faci lity Program mi ng and Cons ulti ng 16,000 Historic Enrollment 14,000 13,,..:!,43~---,_, 12 ,000 10,000 8,000 6,000 4,000 2,000 10,054 8,614 8,080 7,708 Average of All Enrollment Scenarios 4,397 Projected Growth (2021-31) ■ Enrollment Change: 1,725 ■ Total Percent Change: 25.0% ■ Annual Growth (CAGR): 2.26% 2010 20 11 20 12 201 3 201 4 201 5 20 16 20 17 20 18 20 19 2020 202 1 2022 2023 202 4 2025 2026 2027 2028 2029 2030 203 1 -Based on 2016-21 Trend Line -2021 Capture Rate (2021 En rollmenU 2021 College Service Area Population Age 18-64) Held Constant at 0.5% -catchment Area Population Age 18-64, CAGR 2021 -31 Held Constant at 1.6% -9-12 Grade Graduate Growth in Catchment Area (Institutions with >100 Graduates), CAGR 2015-20 Held Constant at 3.9% -Average of all Enrollment Projection Scenarios (minus Trend Line) □FACILITY PROGRAMM I NG AN D CO NSU LT I N G VOLUME I RESEARCH VOLUME I RESEARCH SHARE OF POPULATION BY AGE COHORTS, 2011 – 2031 TOTAL FALL ENROLLMENTS PROJECTIONS Campus Catchment Area Campus Catchment Area 134 135 + I ' ...., @ Northwest ... Northeast @ South @ Southeast @ Trinity River Mile Radius O s Miles 0 10 Miles 0 15 Miles Population Age 18-64 LJ 510,000 -530,000 c:]520,000 -~30,001 □FACILITY PROGRAMM ING AN D CO N SU LTI NG Information shown hereon is a graphical representation only and based upon available information. Facility Programming and Consu lting cannot be responsible for consequences res ulting from error or omission in the information and graphical representations made hereon. a O 5 10Mi les W Source: ESRI and Facility Programming and Consulting @ I eB i --·--r·-----1 ~ - --- - - --eu @ Northwest @ Northeast @ South Johnson @ Southeast @ Trinity River Mile Radius O s Miles 0 10 Miles 0 15 Miles ,~ Tarranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN Annual Growth Population Age 18-64 LJ 50.0% -52.0% -54.0% □~1.0% -53 .0% ->4.0% d.,;• rr ■SCO ' he Colony • • I Heig • Oak □FACILITY PROGRAMMING A N D CONS UL T I NG Information shown hereon is a graph ica l representation only and based upon available information Foc:il ity Programm ing and Consu lting cannot be responsib le for consequences resu lting from error or omission in th e in formation and graph ica l representat ions made hereon. VOLUME I RESEARCH VOLUME I RESEARCH 2021 POPULATION AGE 18 – 64 POPULATION GROWTH AGE 18 – 64, CAGR 2021 – 2031 ZIP Code Analysis ZIP Code Analysis 136 137 + . . • • .t'\. Northwest Campus c:J Catchment Area Catchment Area: Top ZIP Codes comprised of 5,527 students (CUML 79.8%); Capture Rate: 1.0% Mile Radius 0 5 Miles 0 10 Miles Q 15 Miles Students by ZIP Code 0 :::;o -:::;250 0 :::;2s -:::;soo -:::;75 ->500 Information shown hereon is a graphical representation only and based upon available information. Facility Programming and Consulting cannot be respon~ble for consequences resulting from error or omission in the information and graphical representations made hereon. /' • ... t I I .. , .. ..... ' I . • • .. . ( ... 1' • I . • I , 0 0 5 10Mi les W Source: ESRI and Facility Programming an d Consu lting I • • 4 liif Northwest Campus Highland • Denton • Mile Radius 0 5 Miles 0 15 Miles 0 10 Miles ,~ T arranl C ou11ty College· ~ WCCE55 wm•• AEACH. I ·• Fpsc I The Colon • Spa rse Dense CORGAN Information shown hereon is a graphical representation only and based upon available information Facility Programming and Consulting cannot be responsible for consequences resu lting from error or omission in the information and graphical representations made hereon. VOLUME I RESEARCH VOLUME I RESEARCH STUDENT RESIDENCE DENSITY BY ZIP CODE STUDENT RESIDENCE DENSITY HEAT MAP TCC has no on-campus student residences TCC has no on-campus student residences 138 139 +I~ Tarranl Cou11ty College· ~ """"w"-""'" CORGAN VOLUME I RESEARCH VOLUME I RESEARCH Campus Access Vehicular and Pedestrian Circulation VEHICULAR CIRCULATION The main vehicular access points will be from Marine Creek Parkway which lies to the East of the campus, where it connects to Interstate Highway 820 to the south. There is also a small drive that connects to the Interstate Highway 820 Westbound frontage road, West of the Marine Creek/I.H. 820 interchange. Some additional vehicular traffic may originate from the Chisholm Trail High School located directly to the North of the campus. In the Southeast corner of the site there is currently a temporary gravel parking lot. That location could be used for permanent parking. A permanent pavement would be needed, and the grades as well as drainage will need to be analyzed. Providing utilities to the new Construction Hub may be challenging, especially sanitary sewer. PEDESTRIAN CIRCULATION With no sidewalks leading off campus, the majority of the pedestrian traffic will originate from the parking lots. Some of the pedestrian traffic, however, will come from the Chisholm Trail High School located directly to the North of the campus. There is also a public bus stop located at the Southeast corner of the campus at the intersection of Northwest College Drive and Marine Creek Parkway. CAMPUS ACCESS FRAMEWORK Vehicular and Pedestrian Traffic M A R I N E C R E E K P K W Y O L D D E C A T U R R D . L O N G H O R N R D . HUF F I N E S BLVD INTER S T A TE 820 140 141 + ,~ TarronlC wccEss wn_ouHt)' College· AEACH. CORGAN VOLUME I RESEARCH Student participating in event to promote women in firefighting. VOLUME I RESEARCH Labor Market Analysis Northwest Campus Occupational Programs Fastest Growing Occupations 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — Occupations Adding the Most Jobs 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #5: First-Line Supervisors of Office and Administrative Support Workers — #13: Police and Sheriff's Patrol Officers Highest Paying Occupations Dallas, North Central Texas, Tarrant WDAs — #13: Police and Sheriff's Patrol Officers Occupations With Greatest Annual Openings 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #13: Police and Sheriff's Patrol Officers FPC provided data related to job demand, need, and growth within the College’s service area and the Greater Dallas- Fort Worth-Arlington, Texas, MSA (Metropolitan Statistic Area). This study was cross- walked with the programs that the Northwest Campus offers and the available top 20 occupations were outlined. Father and son graduating from the Law Enforcement Academy. The Fire Field in use by students at the Public Safety Training Center at the Northwest Campus. 142 143 + ,},-Tarran! Counl)' College· C O R G A N ~ WCCE55 wm•• AEACH. VOLUME I RESEARCH Classroom and lab space. Flight Simulators used in the Pilot program. Aviation Maintenance Technology Lab. VOLUME I RESEARCH Alliance West Site Site Background The Alliance West Site, also known as the Erma C. Johnson Hadley Northwest Center of Excellence for Aviation, Transportation, and Logistics, provides students with expanded credit and non-credit training opportunities. The site provides specialty training while core curriculum classes are completed online or on the main campus. Students participating in programs at the Alliance West Site are enrolled through the Northwest Campus. The master plan team’s tour with the Real Estate and Facility staff and conversations with site faculty established a background of the site’s identity and the potential direction that the site had in mind. The College’s investment has been very fruitful and yielded a great asset, but there have been difficulties transitioning the property from a corporate building to a community college site. The usage of the third floor for Corporate Services has been beneficial for the College, but the remainder of the building still lacks student-centric functions and spaces. The all-day nature of some of the programs and site location substantiates a need for a food service option for students. Additionally, the former corporate identity leaves little space for students to use as study or gathering. The design of the hangar spaces were based on workforce needs, which now do not provide optimal conditions for instructional environments. The future of the site has determined to lie in being more student-centric with its resources. Master plan programming for the Alliance West Site should be a multi-phase plan, allowing the facility to remain operational while renovations provide necessary updates and expansions. Reorganization and initial renovations should focus on the aviation shop lab and its supporting facilities. Creating improved flow, additional support spaces, and functional adjacencies are a priority for this renovation. Additional building projects should continue the focus on student, staff, and faculty needs, implementing the College initiative of 3 Goals and 8 Principles. Upgrading classrooms to align with IILE standards, providing student success spaces, and creating staff and faculty neighborhoods should be a priority as additional renovations occur. Creating a visible, welcoming, easily accessible main entry and an expanded pilot ramp are also proposed future campus projects. “It was important for us to establish a center for aviation, transportation and logistics excellence in the Tarrant County College because the need for transportation workers is continuing to grow. … As the only public institution that offers these critical programs, we needed to be prepared to meet that growing need that undergirds the economic development in this region.” — Erma Johnson Hadley 144 145 + ~ Tar rant County College~ ~ SUCCESS WITHIH IIUCH. CORGAN I I I ,. VOLUME I RESEARCH VOLUME I RESEARCH ALLIANCE WEST SITE PLAN Master Plan Landscape Plan Alliance West Site Key Campus Statistics Year Constructed: 1991 Campus Size: 40.41 acres in North Fort Worth Building Inventory: 2 buildings, 164,060 SF Campus President: Dr. Blankenbaker Student Enrollment: 7,372 students (shared with Northwest Campus) Signature Programs: — Aviation — Avionics — Logistics and Supply Chain Management — Nondestructive Inspection, Testing, and Evaluation — Welding Technology 0' 100' 200' 400' North GAP ANALYSIS Gap analysis identified inequities between campuses and synthesized them into needs to be accommodated into the master plan. Work sessions with faculty and staff at each campus helped identify deficiencies and desired improvements. The site visit by the master plan team and discussion with faculty and staff familiar with the facility provided a background for site resources that need improvement. This opportunity yielded the valuable feedback that the site was lacking: — Providing student-centric spaces, such as study spaces and a food service option. — Additionally, the former corporate identity of the site was readily evident. While this is a benefit to students as it prepares them for the workforce, the site does not present itself as being focused on student service. +,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN ■ \ I ■ ■ ■ VOLUME I RESEARCH LEGEND Good Facility Condition Fair Facility Condition Poor Facility Condition Critical Facility Condition VOLUME I RESEARCH Alliance West Site Facility Condition Assessment Report Based on the facility condition assessment provided by Jacobs, this site is not that old and most of the issues are that of deferred maintenance or functional improvements. Based on the Facility Condition Index (FCI), there are two buildings on this site that have a good FCI score. The majority of the building on this site are in the good range based on the FCI. The proposed work on this site focuses on renovation of existing buildings to accommodate present programs and make the buildings operate more efficiently. The master plan phasing addresses the following critical issues: —Phase 1 — Renovate Aviation Maintenance Technology (AMT) —Phase 2 — Renovate classrooms to align with IILE standards —Phase 4 — Construct Pilot Ramp Extension FCI Categories: —Good: 0 – 0.02 —Fair: 0.02 – 0.05 —Poor: 0.06 – 0.19 —Critical: +0.20 FACILITY CONDITION ASSESSMENT DIAGRAM Existing Conditions Site Plan 0' 100' 200' 400' North 146 147 +,~ T arranl CouHt)' College· ~ WCCE55 wm•• AEACH. CORGAN ■ \ I ■ ■ ■ -- ,(<? __:~:¢' ■ ,,{r:::::-::>/ 1/ • -{ VOLUME I RESEARCH LEGEND Utilization >75% Utilization 50% – 75% Utilization 0% – 50% Program Defined Utilization Not Assignable VOLUME I RESEARCH Alliance West Site Space Utilization Study Based on overall building utilization, there are two buildings on this site that have a good overall utilization. Of the rooms on the Alliance West Site, several major spaces that are scheduled should be considered separately from other programs based on the unique programming requirements. While there are typical classroom and lab space at the site, the specialized hangar and other workforce training spaces require unique programming and layout standards. Overall building utilization identifies current opportunities within existing site class lab and classroom inventory to determine if they are capable of supporting current and projected enrollment or if additional inventory is needed. Analysis utilizes course schedule data from the Fall 2021 semester. Separating these specialty programs from the defined standards is appropriate because of the requirements of many of these programs. In particular, the Aviation Maintenance Technology and Welding Technology programs require unique instructional spaces. Further, the size of the equipment used for the programs present further constraints. SPACE UTILIZATION DIAGRAM Existing Conditions Site Plan 0' 100' 200' 400' North Utilization Categories: —Good: +75% —Fair: 50% – 75% —Poor: 0% – 50% —Program Specific Utilization: Utilization standards not applied —Not Assignable: No Class Labs or Classrooms Poor Utilization: —Third Floor Classrooms (0%) —Classroom 2305 (0%) —Lab 2303 (6.3%) —Classroom 2319 (20.1%) —Classroom 2321 (39.2%) —Classroom 2212 (42.5%) —Classroom 2317 (48.6%) Program Specific Utilization: —Aviation Maintenance Technology Lab/Shop —Welding Lab 148 149 150 151 +,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN Market Summary 2021 v TCC: NW Campus Catchment Area, 2021F □ rn~!1i~Pil Market Summary V SOURCE: ESRI I Page 1 of2 2021 V TCC: NW Campus Catchment Area, 2021 F V SOURCE: ESRI I Page 2 of2 Total Population Businesses and Employment 2010 733,700 Sector PCT Businesses Employmen1 PCT Occupations Age Groups 2021 Race/ Ethnicity Q Businesses Retail 15.9% 3,690 44,400 2031 10-Yr Projected CAGR ► 1.8% 0 S14 Population Age 18-64 0 15-17 455,600 • 2010 18-34 0 2021 35-64 0 2031 ~65 10-Yr Projected CAGR ► 1.6% • Employment Accommodation 8.4% 1,950 30,480 Diversity 71.5 Education Index 2.5% 590 23,280 • White Collar Professional 7.8% 1,800 23,030 8.9% 0 • White Health Care Blue Collar An estimated 23, 160 6.8% 1,580 19,950 7.7% 0 Black businesses are located within Manufactu ring 3.5% 820 18,420 7.1% 0 Services 0 Asian the Market Area and they Othe r Serivces 13.0% 3,010 17,910 6.9% 0 employed approximately Construct ion 8.5% 1,960 15,910 6.1% Other 260, 160 workers. Vl/holesale 3.0% 700 13,840 5.3% Q Hispanic Transportation 2.1% 490 12,880 5.0% Management Governme nt 1.2% 270 9,390 3.6% Educational Attainment No High School High School Degree or Equivalent Households Some College, No Degree Finance 5.2% 1,210 7,950 3.1% Professional In terms of employment, the Retail Trade sector was the Real Estate 5.3% 1,220 6,110 2.3% Sales NOTE. f'e 1S()(1' of Hispa1Hc Ongi11 may be of any race. I n,e Diveisity Index ""'"""" u-., p1cwboliy Administrative 3.4% 780 5,680 2 .2% tllm two peopl e from the same area will be from d fferent raoe I ethnic QllX.l)S. A Clversity Index largest in the *Market Area Admin 1ncicascs from Oto 100 as the popuallon 1s evenly Mdcd mto lWO or moic rocc I ethnic groups w i th approximately 44,400 Entertainment 1.8% 410 4,070 1.6% workers. This sec tor Information 1.7% 400 3,560 ~ 1.4% Farming I 0.1% Income accounted for an estimated Unclassified 9.0% 2,080 1,470 0.6% Construction 319,500 Associates Degree Total 40.9% Bachelor's Degree $240,100 Home Value Graduate Degree $77,200 3690 businesses. Mining 0.2% 60 6S0 0.3% Maintenance Median HH Income Headquarters 0.3% 70 500 0.2% Production Utilities 0.1% 20 360 0.1% $34,600 Agriculture 0.3% 60 310 0.1% Transportation 9.1% Per Capita Income • Market Area: Is t h e same as the region referenced in the YELLOW bar highlig hted at the l op of the page VOLUME I RESEARCH VOLUME I RESEARCH MARKET SUMMARY MARKET SUMMARY Campus Catchment Area Campus Catchment Area 152 153 + Education Summary □FACILITY PROGRA MMING AND CO N S U LT ING 202 1 v T CC: NW C ampus Catchme nt Area , 202 1 F Education Enrollment Total Enrolled in School Not Enrolled in School 236,500 585,700 Percent in/ Not in School 28.8% 71.2% School Enrollment by Grade Level GRAD 11K 0 PRE-Preschool -K ND-Grade 12 0 Higher Ed SOURCE: 2015-2019 A mer ican Commu nity Survey Percent of Enrolled 72.9% K-12 15.9% College 4.6% Grad School V SOURC E: ESRI , ACS Household Expenditures on Education Total Spending Average/ Household Index Spending Category College Tuition K-12 Tuition Other School Supplies Rental of Books/ Equipment Supplies for College Test Preparation/ Tutoring Services Supplies for K-12 Schools Vocational Tuition Tuition for Other Schools Supplies for Presc hool Supplies for Vocational Schools $552,243,000 $1,728 100 Total Expenditures $324,625,300 $80,009,500 $21,650,900 $19,076,800 $15,284,200 $8,377,100 $8,120,100 $5,087,300 $4,654,600 $1,060,700 $318,000 I Page 1 of 1 Average/ Index Household $1,016 96 $250 105 $68 111 $60 107 $48 109 $26 100 $25 120 $16 113 $15 103 $3 106 $1 108 NOTE: A n index of 100 reflect s t he national average. An i ndex of 120 s uggests spending is 20 percent above t he average. ,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN SOURCE ESR I and Facil ity Programm ing and Consu lting 1,200,000 I Historic Population Estimates 1,000 ,000 800 ,000 750,400 600 ,000 -----659,400 562,200 --------------- 465i:,3~00~--------------------- 400 ,000 212,700 ---------------255,600 -------------------------------200,000 174,200 33,800 37,700 ------------------------ - - - - ---- - - - ---- -------43,300 0 2011 2013 2015 2017 2019 2021 2023 2025 2027 2029 2031 -2011-21 Total Population CNG: 166,900 , 22.2% or CAGR 2.0% 11 2021-31 CNG: 181 ,300 , 19.8% or CAGR 1.8% -2011-21 Population Age 18-64 CNG: 96,900, 20 .8% or CAGR 1.9% 11 2021-31 CNG: 97 ,200 , 17 .3% or CAGR 1.6% -2011-21 Population Age 18-34 CNG: 38 ,600, 22.1% orCAGR 2.0% 11 2021-31 CNG: 42 ,900 , 20.1% orCAGR 1.9% -2011-21 Population Age 15-17 CNG: 3,900, 11.5% orCAGR 1.1% 11 2021-31 CNG: 5,600, 14.8% or CAGR 1.4% VOLUME I RESEARCH VOLUME I RESEARCH EDUCATION SUMMARY HISTORIC AND PROJECTED POPULATION ESTIMATES Campus Catchment Area Campus Catchment Area 154 155 + 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% SOURCE ES RI and Faci lity Prog ramming and Con sult ing ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. 0 0 0 ~ 0 0 0 ~ 0 0 0 ~ 0 0 0 0 0 0 8, 0 0 ..... ..,, CIO ..,, CIO "'": ~ CJ? ..... ..... en ..... C") ..,, ..... ..... C") CJ) CJ) CJ) 0 0 0 .... .... .... .... N N N N ('I) ('I) ('I) ('I) ('I) ~ ~ .... .... .... .... .... .... .... ..... ..... ..... .... ..... .... .... ..... ..... ..... ..... ':§e. '#. ':§e. ~ ':§e. ':§e. &, ..... 0 0 0 '#. ':§e. ':§e. ':§e. ~ ':§e. co co ..,, 0 0 ':§e. ':§e. ':§e. co co co -.:I" C") C") ~ 0 0 0 '#. ~ ':§e. ':§e. ':§e. ':§e. a:i ~ co N ..... CIO 0 0 0 C") co co ~ N 0 0 0 0 0 C") C") C") co co ~ ....: ..... .... 0 en CIO CIO C") C") C") C") C") ..... ....: ....: CD ....: ....: CD CD ~ C") C") C") C") C") C") C") C") C") ~ "#-~ ..... ~ ~ r.l 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Percentage Point Change by Cohort and 10-YearTime Frames ■ 2010-21 Age ~14 -2011-21: -1.9% II 2021-31 : -0 .7% ■ 2010-21 Age 15-17 -2011-21: -0.4% II 2021-31: -0 .2% ■2010-21Age18-34-2011-21:0.0% 112021-31:0.1% □2010-21Age35-64-2011-21:-0.7% 112021-31:-1.3% a 2010 -21Age~65 -201 1-21:3.0% 112021-31:2 .1% ,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN SOURCE: Tarrant County Co ll ege and Facility Programming and Con sulting 16,000 Historic Enrollment 14 ,000 13,,~4t.J3 i-------~ 12,000 10,000 8,00 0 6,00 0 4,000 2,000 Average of All Enrollment Scenarios Projected Growth (2021-31) ■ Enrollment Change: 1,725 ■ Total Percent Change: 25.0% ■ Annual Growth (CAGR): 2.26% 201 0 20 11 20 12 2013 2014 2015 2016 20 17 201 8 20 19 2020 202 1 2022 2023 2024 2025 2026 2027 2028 2029 2030 203 1 -Based on 2016-21 Trend Line -2021 Capture Rate (2021 Enrollment/ 2021 College Service Area Population Age 18-64) Held Constant at 0.5% 10,054 8,614 8,080 7,708 4,397 -catchment Area Population Age 18-64, CAGR 2021-31 Held Constant at 1.6% -9-12 Grade Graduate Growth in Catchment Area (Institutions with >100 Graduates), CAGR 2015-20 He ld Constant at 3.9% -Average of all Enrol lment Projection Scena rios (minus Trend Line) □FACILITY PROG RAMM ING AN D CON SU LT I NG VOLUME I RESEARCH VOLUME I RESEARCH SHARE OF POPULATION BY AGE COHORTS, 2011 – 2031 TOTAL FALL ENROLLMENTS PROJECTIONS Campus Catchment Area Campus Catchment Area 156 157 + I ' ...., @ Northwest ... Northeast @ South @ Southeast @ Trinity River Mile Radius O s Miles 0 10 Miles 0 15 Miles Population Age 18-64 LJ 510,000 -530,000 c:]520,000 -~30,001 □FACILITY PROGRAMM ING AN D CO N SU LTI NG Information shown hereon is a graphical representation only and based upon available information. Facility Programming and Consu lting cannot be responsible for consequences res ulting from error or omission in the information and graphical representations made hereon. a O 5 10Mi les W Source: ESRI and Facility Programming and Consulting @ I eB i --·--r·-----1 ~ - --- - - --eu @ Northwest @ Northeast @ South Johnson @ Southeast @ Trinity River Mile Radius O s Miles 0 10 Miles 0 15 Miles ,~ Tarranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN Annual Growth Population Age 18-64 LJ 50.0% -52.0% -54.0% □~1.0% -53 .0% ->4.0% d.,;• rr ■SCO ' he Colony • • I Heig • Oak □FACILITY PROGRAMMING A N D CONS UL T I NG Information shown hereon is a graph ica l representation only and based upon available information Foc:il ity Programm ing and Consu lting cannot be responsib le for consequences resu lting from error or omission in th e in formation and graph ica l representat ions made hereon. VOLUME I RESEARCH VOLUME I RESEARCH 2021 POPULATION AGE 18 – 64 POPULATION GROWTH AGE 18 – 64, CAGR 2021 – 2031 ZIP Code Analysis ZIP Code Analysis 158 159 + . . • • .t'\. Northwest Campus c:J Catchment Area Catchment Area: Top ZIP Codes comprised of 5,527 students (CUML 79.8%); Capture Rate: 1.0% Mile Radius 0 5 Miles 0 10 Miles Q 15 Miles Students by ZIP Code 0 :::;o -:::;250 0 :::;2s -:::;soo -:::;75 ->500 Information shown hereon is a graphical representation only and based upon available information. Facility Prog ramm ing and Consulting cannot be respon~ble for consequences resulting from error or omission in the information and graphical representations made hereon. /' . . I • I • • -------'----~-----~~-- ~ .. ' , .. , -..... ' ' I . • I .. s. . ' ~ ... 1' • :, • , • .. \ Johnson "' ~ :l liilll Northwest Campus • Mile Radius Highland • Denton Flower Mound • 0 5 Miles O 15 Miles Q 10Miles ,~ Tarranl Cou11ty College· ~ WCCE55 wm•• AEACH. Little Elm ,. Frisc I The Colon • Glenn Ellis Height ..,_._ "R Sparse Dense --~ CORGAN Information shown hereon is a graphical representation only and based upon available information. Facility Programming and Consulting cannot be respon~ble for consequences resulting from error or omission in the information and graphical representations made hereon. VOLUME I RESEARCH VOLUME I RESEARCH STUDENT RESIDENCE DENSITY BY ZIP CODE STUDENT RESIDENCE DENSITY HEAT MAP TCC has no on-campus student residences TCC has no on-campus student residences 160 161 +-,i~ T arranl Cou11ty College· ~ WC:CE55 wm .. AEACH. CORGAN VOLUME I RESEARCH VOLUME I RESEARCH Site Access Vehicular and Pedestrian Circulation VEHICULAR CIRCULATION The main vehicular access points will be from Legacy Crossing, where it connects to Interstate Highway 35 West. None of the proposed phases would negatively impact vehicular paths and/or traffic with the exception of the construction material drop offs and the staging of construction materials. However, coordinating with the AHJ and the airport will likely need to occur as construction projects may need to access the restricted air-side of the site. PEDESTRIAN CIRCULATION There are no sidewalks that connect to any of the main roadways, so pedestrian connectivity will originate from either the parking lots or drop off areas. O L D D E N T O N R D . WESTPORT PKWY IN T E R M O D A L P K W Y IN T E R S T A T E 35 CAMPUS ACCESS FRAMEWORK Vehicular and Pedestrian Traffic 162 163 + ,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN VOLUME I RESEARCH Student engaged in the Welding program. VOLUME I RESEARCH Labor Market Analysis Alliance West Site Occupational Programs Fastest Growing Occupations 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #8: Commercial Pilots — #17: Transportation, Storage, and Distribution Managers Occupations Adding the Most Jobs 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #5: First-Line Supervisors of Office and Administrative Support Workers — #19: Transportation, Storage, and Distribution Managers — #20: First-Line Supervisors of Transportation and Material Moving Workers, Except Aircraft Cargo Handling Supervisors Highest Paying Occupations Dallas, North Central Texas, Tarrant WDAs — #2: Commercial Pilots — #3: Transportation, Storage, and Distribution Managers — #8: Transportation Inspectors — #17: Aircraft Mechanics and Service Technicians Occupations With Greatest Annual Openings 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #4: First-Line Supervisors of Office and Administrative Support Workers — #10: Transportation, Storage, and Distribution Managers — #18: First-Line Supervisors of Transportation and Material Moving Workers, Except Aircraft Cargo Handling Supervisors FPC provided data related to job demand, need, and growth within the College’s service area and the Greater Dallas- Fort Worth-Arlington, Texas, MSA (Metropolitan Statistic Area). This study was cross- referenced with the programs that the Alliance West Campus offers and the available top 20 occupations were outlined. Student pilot learning as part of the Aviation programs. Students investigating a mechanical component as part of the Non-Destructive Inspection, Testing, and Evaluation program. 164 165 + CORGAN VOLUME I RESEARCH Ongoing construction as part of bond projects involved in the campus redevelopment. Fine Arts classroom. Aerial view of Southeast Campus prior to redevelopment construction. VOLUME I RESEARCH Southeast Campus Campus Background As a higher institution of learning, the Southeast Campuses most capital-intensive aspect of its institution is its buildings. Space is an asset and a tool for delivering the educational mission, vision, values, and pedagogy for students on the Southeast Campus. The need for additional, functional, and updated space on the campus is the guiding strategy in the master plan for the Southeast Campus. Space is an asset and TCC’s facilities are a tool for delivering the educational mission, vision, values, and pedagogy for students on the Southeast Campus. Understanding what assets the Southeast Campus currently has is imperative to establishing a baseline upon which to build future space and renovation needs. Existing space was examined to determine its current ability to serve departmental needs both in quantity and functional adequacy. The results of this analysis were utilized by the master plan team to develop a detailed program of new and renovated spaces as the campus moves forward with a mix of new construction and renovation. The analysis was used to compare current Southeast Campus facilities with the 3G8P guidelines to make sure current and future spaces are functionally appropriate and have enough flexibility to adapt to changes in instruction and technology. The information will be used to bring transformative spaces to the current and future buildings on the Southeast Campus. The master plan programming for the future of the Southeast Campus should include the construction of additional academic facilities and student spaces. The construction of the Student Experience Building and the Academic Building, scheduled for completion in 2024, provided the campus with additional space, but was unable to bridge the enrollment cap in terms of the overall campus space needs. Future expansion at the campus should focus on creating a college campus atmosphere with outdoor spaces, study spaces, student support areas, outdoor recreational areas, and provide a place for students to be. The overall plan should create a cohesive campus which includes the existing and future early college high school communities. “For the past 18 years, TCC Southeast has focused on helping thousands of students achieve their personal and professional goals though our myriad academic and workforce development programs. Like all of the campuses in the TCC family, we commit daily to bringing quality education to our communities in an open, friendly and affordable manner.” — Dr. Coppola 166 167 + Cou11ty C ollcg Tarranl ACH. , WCCE55 wm•• AE ~ ,· CORGAN r-·-·-·-·-·-·7 I . i ! i 1 i ! , I r r j ' ; I I - j I ! i L:,_, ________ .J CD \,"~--_#..,/ VOLUME I RESEARCH VOLUME I RESEARCH SOUTHEAST CAMPUS SITE PLAN Master Plan Landscape Plan Southeast Campus Key Campus Statistics Year Constructed: 1996 Campus Size: 162.15 acres in Southeastern Arlington Building Inventory: 14 Buildings, 635,965 SF Campus President: Dr. Coppola Student Enrollment: 8,537 students Signature Programs: — Culinary Arts — Dietetics — Drama/Theater — Engineering — Hospitality Management 0' 100' 200' 400' North GAP ANALYSIS Gap analysis identified inequities between campuses and synthesized them into needs to be accommodated into the master plan. Work sessions with faculty and staff at each campus helped identify deficiencies and desired improvements. The work session with the campus faculty and staff provided an opportunity for an iteration of the phases to be reviewed and the campus priorities to be stated. This opportunity yielded the valuable feedback that the campus was lacking in: — Providing student-centric spaces, such as study spaces. — The Music and Theater spaces need additional support space. — The additional student support that the ongoing bond projects would provide was considered as well, as it had been identified that it would have to work within the existing building massing. + I I ! r ffi I \__ ■ ■ ■ ■ ~~ Tarrant County Coll .. ~ wcms wm.,, '""" egc CORGAN ■ SOUT H E A S T P A R K W A Y EMOD VOLUME I RESEARCH VOLUME I RESEARCH LEGEND Good Facility Condition Fair Facility ECHS Condition Poor Facility Condition Critical Facility Condition Southeast Campus Facility Condition Assessment Report Based on the facility condition assessment provided by Jacobs, the most critical buildings on this campus is the Building Services Power Plant (EBSP) and Classroom Buildings. FCI Categories: —Good: 0 – 0.02 ESSE ESEE ESEB ESEC ESED ESCT EBSP ESAC EART EBSE EBSA EBSB Based on the Facility Condition Index (FCI), there are five buildings on this campus that have a good FCI score. The majority of the building on this campus are in the fair and poor FCI score ranges. The master plan phasing addresses the following critical issues: —Phase 2 — Construct Physical Education Addition and Performing Arts Addition, renovate Physical Education Wing —Phase 4 — Renovate Fine Arts Building —Phase 7 — Renovate Science and Technology Building —Fair: 0.02 – 0.05 —Poor: 0.06 – 0.19 —Critical: +0.20 Critical Buildings: —EBSP Wing (0.88) —EMOD Buildings (0.47) Poor Buildings: —EART Building (0.17) —EBSA Building (0.16) —ESED Wing (0.09) NE W YO R K AV E N U E Facility Condition Index (FCI) is the total cost of needed building repairs and renewal divided by the current cost of replacing the building. Each building’s FCI score reflects the current condition of the building: Good, Fair, Poor, or Critical —ESEE Wing (0.09) EBSC —ESEB Wing (0.08) —ESEC Wing (0.08) FACILITY CONDITION ASSESSMENT DIAGRAM Existing Conditions Site Plan 0' 100' 200' 400' North 168 169 + EB I , 1f ~ _ -•. ~- 11 [ _ _ _ -- ~l , - ' \ \: : - _ .-- - - ; ; ; ; ; - ~ ~ - \" ' " " _ _ _ , , ,.. , : - - - - - - - - \ G - - - ~ ' , \ II ;J ; / \ . n ' I ·/ ; _ , - - v U - \ ,,; '• I I I ~ . \ I i', ' i J" ;"/ i l O g ' I\ ' i ll I~ d , [ ] ~ [1 I I _ r , 0 r· 1, 1 111 1 1 ,, ; ,; / I ' ] ' , , ) '1 ,1 I 1'', ,/ J t ' 1,' I\~ ' / ~- , " ~ ~ -- - 11 0 0 D I I I \ / ,- .J ~ - --- --- ~- : ,. . . . . . . , . _ _ O I I I, t I, \ I' ,' I - - -- l I -· \ i __ \ \ '"' - . '. . a ~ ' I ' " ' I 1 , ' 1 - - - ~ ~ - - - - - - ) I '\ \ \ 1\ 1111 /1 / _.; _i; ; ( 11· '-- - - - - = ~ - - - ,._ _ , -_\ \ . \j ) \ ~ \ I /f t ~ n r - i - = ' \ J "' }I I I : d -- - , ~ ~ - -- = - - - r " '- - ' Y \ I _f : ' \~ ... ... ,' ( ,,. , . ,, . - - - \ \, c - : , . \ \ ·: ' , ::/ rl C C ' : L _ _ _ ,_ ,..✓~--- - I "- - ✓ / ) , ., (: ' / I -, , } ~ - 7 . , ; ~ ~,., 1 'c;, , . , ; - ; _ . : : > - \;\ /1 · (/ /I IY C O D ; g - ~ " , . . , , ~ \ _ _, , \. , / ,✓, - ' \ ' : \ . ( ,1 ' -l . : : : : : : = : : : : : 11 B'= " = ; = i . . ,, ( , \~ . \~ \_ '- .. __ _ _ __ . , . _ ---i c~1 . f \I _,, _ . _ . . \ / \ , \ \ ·c-: :-- - ) . // ,, , ~ ~ ~~sv :f ' ~cb t /. I t ; ( \ \ \ \ \ '¾ , , ~ ' - - - / , \' I , " · / ' .. . . . . \ \ ~ ~- '\ I { / '7 ~ (/ { ;, ~sJ i ; ,6 "'; .. - 1 ' . : \ : :i J < ; ~ , < \\ \ _ \ , , \I Ii es / , / ' ,\) \-~s~ , ~ -~~ \ i\~ \ 11! \ I I I ,= = i _ J \\ \\ ~,, \ i, ,. I \ , , § ~ - \\ ,, t i ~ -- - - ·- , \ ~, \ (' \ ~-.,\ : : : ·-:\ + · I I] l1 I \ ( ' , \ \ ' ; \ ,, ' \ \ \ ' ' '· I L I \ \ \ \ \ \ ', 1 ( ' \ V \ \ - : , '- . . j ~ . \ \ \ \c \ \ \ I ' . c , ,_ . ,, - ~ 0 ] ] r- \ , \ , \ V V , 11 ., , . . . , ' ) \ \ \ , ; · , ) \. . . . . . . . . . . . . I L) \ ._ 1 \ \ \ ' , \ \ \ . \ ' \ 1~ ~ '\ . \ "t t :r> · J· ; ~ ( \ <:,j \ \~ ~ n O D ) \ \ \ \ \ ~ \ \ , " ' ~ 11 0 ) > \ -- < ~ - , _,,"('. _ } ,\ ; . ' \ ~ J O ,I \ \, ' \ , , ,, I ,. " \ ' - ., \ \ \ \ . '~ \ , -- ' " \ ., , ., , I , , , , , d ; , \; , / \ l. , , ,, _,_ , , . • ..- - - ,, ... . ' ,, ' \ \ \ \ \ I ' . , . / -:: < : \ ' , '\ ~" ,, ' ,, . - ,,. / .,. ,. . , \ . , ~ '. u~ _. . , , . - " ,; ; , ; o ' . ,c ; , , , :; , - \ 'J O -; : D < /: , , , , . - : ; ; ,.,, '. \ : \\ ' ! Y ., , -; _ , , , / C\ \ , • ~~-. ~ _.,.1 / .. . / ., ,, \;_ : , / _, , / 0/ . p " \ , ' \ \ \ \< { : : ? ; , ~ \ \ i \ ??~~ c,, , , / '\ ~ ;, . - ~ > ; ; ; ~ ~ \; \) \ \~ < ~ ' \ \ \~ .\ '< " ' < , ~' ' / / - ~ \ \ \ \" + , / ~ < I ' ' ! , c, ~ , • . :, , \ I - /' , . , . , X ; , , '•> ('- , n , \ , <- ; - : \ \ : : \ l \ ' \ \ ) ; , ~ ; __ . , . . / { : / ) \ ~ \ ) \ \ \ \ \ _ . , / ' , ' \ ;" " \ I, <... ' . s - - - - - - " " ~~ \ \ ,, " \ ": \ ' \ / V7 ,, , > 1 / , - ~ - \ \; , , ,., ·\ ,. . / / -:: : ,i : ~- - - ~tr , \ ~ ,: , '\ . \ ~ n \ \ ~ \ ~\ ~' - " I \ , ' } , ,, _ . . \ - - /_ _ . , . ' V \' ; , ' ' ' ( ' " \ ' 1 ' ' ' I v . , . / ,, , ,, ' \ \ "\ ' \ - ),, ) : ', _, . - - - - -- = -=-~ ___ _. . . / . . , . <-... \ (' V \: . \ ) \ \ \ \ \ \ ~ <!J / ,, ,/ ,,.- , ,- - - \l l ) \ ) \. , \ . , ' ' \ ' , , , · · \ (~/\<\ . , ~~✓-- ' \ ' , , A \ __ ,,, . - , : , _ , ; : : - ~ c: , - 0 , . 7 ' ,, 7 ~ \ \ \ , \ ~ 's \) \0 \ ) \ \ \ \ ' ( \ , \ \ \ ~ '. . \ \ , , ,,. . . . . . . / ( , ? ~ \ \ ' \ \' - '. J ' \ \ ~ \ ~ \ \ \ , ( "\ \ \ \ \ ' \ \ / ' \ - ' ( \ .. - - - - : : : : - : : __ _ ,, , - _, , , , , , , . . - - - \ "\ \ ~ ) , , 'V \ \ \ , \ ) \ \ ) ' \ ~ ' \ ~C \ ~ ,., . , , , , , . •' \ , \ ~, \ \ '\ , \ , ,, ._ \ \ \ , \ ' ( / . , , / / ' '- , ) \ , ~ ', ~ • ~ , - / \ ,, \ , ' u Y \ , \ \) 'C . . - · -:: : : c - .. . . : : _ _ _> - . \ '' \ _\ ___ \ _ \ _ - /,. . , , . . _ \ c· \ t " \\ ,. \\ \ ~ ,,, . . , , , \ , ,..,✓- ' - ' " - - - - , ' \ \ > ) I ~ - , O \' , ~ / 0- - ' \ ' / / "'- - . . _ \ \ \ / ·· \ --- - - - ... . .. _ ~ ' \ . , / ~ \ / / {: \ , 1 ' . , _ \ ci v. : < _ , . / r , . ) : · \ \ \. . \ ,, '; \ / \ · , \ \ ,. . , , / " _,, , \ \ ,- ; ! . , / \ )\ , ,, , ; :.; - / / / -- - - - \ _, \\ ' - - '. . \: ;, ,/ ~ ,, . ·- , ; : ; : "' / " ' ~ \ . ) ';, ~ r ' ' \ , • - -__ , \ ; 1· __ l \ , \ ~ / '\ . , ' ; / V ,, , , - - - - - . \ 1 ) \' . _ _ , 0) \ \ \ \ , , ~ - f ,. . ,S , , / ,, \ , --- - - - ,. , , ) I I \ \ V , , . - . ~ ' \ \ _ . , . / ,, I ' \ ) \ , \ ( \ ' · · I .1 , / ( - , \ , / / / ~ - \ i' ~ , \ \ _ ) / r ,, / / ; \ \ ( /. , . _,,, . . . , V \ I\ _,,, , , / ' / ~ ~: j . \ ' . \ \ ' I . ,' _, - , _ ' \_ ; , , , , ) ·- . , , . - < , ~ • ~ ' I I I ' , \ \ <" " / . . ; y ✓ \ \ 1 / I \ / \ \ - \ ,: ; ; ? ~ --- - : :; _ , v . ' , \ I / , \ \ \ '. ) ' . ) \ , • • , , , (I ' \ \ C C , '~ \ . . ~ -- , I c: ? " ) - ,, / I / \I \ ? ./' <, ; y ·< " \ <.:\ --, . , . , . , . , ,., . . , , , , . ... --✓,., ' / , . I < , , \ ( _ ,, , , / •. -- ~ - -- - I \ ~ ~! \ ; ,_ ., . / / I ., , . . . , . -- - I I \~ ; ? 1 / ~\ \, . ,, . , ., , ~ · f l ,; : _ ; : : : > ~ ·- , . ( / / / I \ ,,,._ _ _ ~V\ = > \ \ I \ · , , , _ _ , , / · . . _ -- I . - - , I ,_ I I I \_ _J I I I I r·- - , : r ~ -- - - -- - - . - ,' ■ ■ ■ ■ ~ §~ •• ~ , ;Q •= ~· ; : : ~ ~ i •. (" " ) 0 : c en l > 2 ■ PARK W A Y SOUT H E A S T EMOD VOLUME I RESEARCH VOLUME I RESEARCH ECHS LEGEND Utilization >75% Utilization 50% – 75% Utilization 0% – 50% Program Defined Utilization Not Assignable ESSE ESEE ESEC ESED ESEB ESCT EBSP ESAC EART EBSE EBSA EBSB Southeast Campus Space Utilization Study Based on overall building utilization, there are two buildings on this campus that have a good overall utilization. Of the buildings and wings on the Southeast Campus, several major spaces that are scheduled should be considered separately from other programs based on the unique programming requirements. These spaces have been identified as those that contain programs involving the ECHS, Community and Continuing Education, Fine and Performing Arts, and Physical Education. Overall building utilization identifies current opportunities within existing campus class lab and classroom inventory to determine if they are capable of supporting current and projected enrollment or if additional inventory is needed. Analysis utilizes course schedule data from the Fall 2021 semester. The growth in campus and program enrollment has outpaced the available space and caused issues with poor utilization. Primary conclusions from the space utilization analysis found that many of the classrooms are not right-sized or setup for active teaching modalities, a need for additional faculty support spaces, a lack of student support space for studying and gathering, and a need for additional wellness and storage spaces. Utilization Categories: —Good: +75% —Fair: 50% – 75% —Poor: 0% – 50% —Program Specific Utilization: Utilization standards not applied —Not Assignable: No Class Labs or Classrooms Poor Utilization: —ESED Wing (25.9%) —ESEE Wing (44.8%) —ESEC Wing (45.7%) Program Specific Utilization: NE W YO R K AV E N U E EBSC —EMOD Modular Buildings —ESEB Wing SPACE UTILIZATION DIAGRAM Existing Conditions Site Plan 0' 100' 200' 400' North 170 171 —EART Building —ECHS Building 172 173 +,~ T arranl Cou11t y College· ~ WCCE55 wm•• AEACH. CORGAN □FACILITY PROGRAMM ING AND C ONSULT IN G Market Summary 2021 v TCC: SE Campus Catchment Area, 2021F V SOURCE: ESRI I Page 1 of2 □FACILITY PROGRAMMING A ND C O N S U LTI NG Market Summary 2021 v TCC: SE Campus Catchment Area , 2021F V SOURCE: ESRI I Page 2 of2 Total Population Businesses and Employment 2010 478,900 Sector PCT Businesses Employmen1 PCT Occupations Age Groups 2021 Race/ Ethnicity 0 Businesses Retail 15.8% 2,510 31,720 2031 10-YrProjected CAGR ► 1.1% 0 :51 4 Population Age 18-64 0 15-17 302,700 • 2010 18-34 0 2021 35-64 0 2031 2:65 10-Yr Projected CAGR ► 0.9% Educational Attainment No High School High School Degree or Equivalent Households Some College, No Degree • Employment Accommodation 8.6% 1,360 24,370 Diversity 81.4 Education Index 2.8% 440 19,270 • White Collar • Manufacturing 3.1% 490 18,890 10.1% 0 White Health Care Blue Collar An estimated 15,850 8.5% 1,360 18,320 9.8% 0 Black busi nesses are locat ed within Other Serivces 13.0% 2,060 12,510 6.7% 0 Services 0 Asian the Market Area and t h ey Professional 8.5% 1,340 10,300 5.5% 0 employed approximately Government 1.1% 170 9,110 4.9% Other 186,800 workers. Wholesa le Q Hispanic 2.6% 410 7,560 r: 4.0% Entertainment 1.8% 290 7,140 3.8% Construction 8 Management 5.7% 910 7,020 3.8% Fi nance 5.8% 920 5,480 2.9% Professional In t erms of employment, the Retail Trade sector was the Real Estate 5.4% 850 4,890 2.6% Sales NOTE: Pe!sons of Hispanic Origin may be of any race. I Th e Diveisitylndex mrosues the p1000bil iy A dministrative 3.3% 520 3,710 ! 2.0% tllat ~vo people from the same M!!l will be f,omdiffeient race/ ethnic groups . A Diveisily Index largest in t he *Market Area i Admin 1111:re;:-f)f-!i h1 J1r1 II lo 1{K> as llte Iq11lal11H1 1s evml y d1•.11ct-x:l 11llo l wc1 f)r rrKN~ ,a:P., l-!lhr11c gn11IIis with app r oxi mately 31,720 Transportation 2.1% 340 3,190 ! 1.7% ! 1 0.1% worke rs. This se ctor Informati on 1.6% 250 2,010 i 1.1% Farming Income ; accounted for an esti mat ed Unclassified 9.8% 1,550 770 I 0.4% Construction 182,300 Associates Degree Total 41.2% Bachelor's Degree $229,800 Home Value Graduate Degree $72,200 2510 businesses. Headquarters 0.2% 30 260 0.1% Maintenance Median HH Income Agri c ultu re 0.2% 30 110 0.1% Production 5.2% Mining 0.1% 20 110 0.1% $30,900 Utilities 0.0% 10 80 0.0% Transportation 10.1% Per Capita Income • Market Area: Is the same as the region refe renced in t he YE LLOW bar highlig hted at the top of t he page VOLUME I RESEARCH VOLUME I RESEARCH MARKET SUMMARY MARKET SUMMARY Campus Catchment Area Campus Catchment Area 174 175 + Education Summary □F ACIL IT Y PROGRAMM ING AND CO NSULT ING 2021 v TCC: SE Campus Catchment Area, 2021F Education Enrollment Total Enrolled in School 161, 700 Not Enrolled in School 349,400 Percent in/ Not in School 31.6% 68.4% School Enrollment by Grade Level 0 PRE-Preschool -KND-Grade 12 0 Higher Ed SOURCE: 2015-2019 American Community Survey Percent of Enrolled 67.0% K-12 23.1% College 5.4% Grad School V SOURC E: ESRI , ACS Household Expenditures on Education Total Spending Average/ Household Index Spending Category College Tuition K-12 Tuition Other School Supplies Rental of Books/ Equipment Supplies for College Test Preparation/ Tutoring Services Supplies for K-12 Schools Vocational Tuition Tuition for Other Schools Supplies for Preschool Supplies for Vocational Schools $301,594,800 $1,655 96 Total Expenditures $177,418,100 $41,526,400 $11,531,200 $10,154,700 $8,561,200 $4,518,800 $4,149,900 $2,773,800 $2,513,400 $610,400 $176,500 I Page 1 of 1 Average/ Index Household $973 92 $228 96 $63 103 $56 100 $47 107 $25 95 $23 107 $15 108 $14 98 $3 107 $1 105 NOTE: An index of 100 reflects the national average. An index of 120 s uggests s pending is 20 percent above the average. ,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN SOURC E ESRI and Faci lity Progra mming and Con sulting 700,000 Historic Population Estimates 600,000 -----600,000 ---------539,500 - - - ----------500,000 484,400 400,000 341700 ----------375,100 ' -------------306i~,20~0--------------- 300,000 200,000 141,100 -------------162,000 119,!40~0~----------------------- - - ---- - 100,000 23, 700 22, 700 ---------------------------------------------0 22,100 2011 2013 2015 2017 2019 2021 2023 2025 2027 2029 2031 -2011-21 Total Populat ion CNG: 55,100, 11.4% orCAGR 1.1% 11 2021-31 CNG: 60,500, 11 .2% orCAGR 1.1% -2011-21 Population Age 18-64 CNG: 35,400, 11 .6% or CAGR 1.1 % 11 2021-31 CNG: 33 ,400 , 9.8% or CAGR 0.9% -2011-21 Population Age 18-34 CNG: 21 ,700, 18.1% orCAGR 1.7% 11 2021-31 CNG: 21 ,000, 14.9% orCAGR 1.4% -2011-21 Population Age 15-17 CNG: -900, -3.9% or CAGR-0.4% 11 2021-31 CNG: -600, -2.8% or CAGR-0.3% VOLUME I RESEARCH VOLUME I RESEARCH EDUCATION SUMMARY HISTORIC AND PROJECTED POPULATION ESTIMATES Campus Catchment Area Campus Catchment Area 176 177 + 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% SOURCE ES RI and Faci lity Prog ramming and Con sult ing ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. 0 0 0 0 0 0 0 0 0 ~ ~ 0 0 ~ 0 0 ~ 0 0 ~ CD ('? .... .... .... .... .... C! ~ ~ «? .... C") CD en GO GO oi oi oi 0 0 0 .... .... .... .... N N N N (") (") (") .... .... .... .... .... .... .... .... .... .... .... .... .... .... ':§e. ':§e. ~ ~ ':§e. 0 ~ ':§e. '#. ~ CD C") 0 0 0 ':§e. ':§e. ~ ... ':§e. ':§e. ~ ~ ~ ~ 0 co .... CD ~ 0 0 ~ ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. GO .,..; C") N 0 • 0 0 ~ ':§e. .,..; .,..; CD ~ 0 .,..; .,..; ~ .... en 0 0 0 ~ C") C") C") co co co co en co CD C") C") C") iri co ~ iri C") C") (") (") (") (") iri iri (") (") C") 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Percentage Point Change by Cohort and 10-YearTime Frames ■ 2010-21 Age ~14 -2011-21: -2.8% II 2021-31 : -1.3% ■ 2010-21 Age 15-17 -2011-21: -0.7% II 2021-31: -0 .5% ■2010-21 Age 18-34 -2011-21: 1.5% II 2021-31: 0.9% □2010-21 Age 35-64 -2011-21: -1.4% II 2021-31: -1.7% a 2010 -21 Age ~65 -201 1-21: 3.4% II 2021 -31: 2.7 % ,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN SO UR CE : Tarran t Cou nty Coll ege and Fac ility Program mi ng and Cons ulti ng 16,000 Historic Enrollment 14,000 12 ,000 10,000 10,313 R:3i ~ 8,890 8,000 6,000 4,000 Average of All Enrollment"-'~~- Projected Growth (2021-31) ■ Enrollment Change: 1,324 2,687 2,000 ■ Total Percent Change: 16.4% ■ Annual Growth (CAGR): 1.53% 2010 20 11 20 12 20 13 201 4 201 5 20 16 20 17 20 18 20 19 2020 202 1 2022 2023 202 4 2025 2026 2027 2028 2029 2030 203 1 -Based on 2016-21 Trend Line -2021 Capture Rate (2021 Enro llmenU 2021 Col lege Service Area Population Age 18-64) Held Constant at 0.6% -catchment Area Population Age 18-64 , CAGR 2021-31 Held Constant at 0.9% -9-12 Grade Graduate Growth in Catchment Area (Institutions with >100 Graduates), CAGR 2015-20 Held Constant at 2.4% -Ave rage of all Enrollment Projection Scenarios (minus Trend Line) □FACILITY PR OGRAMMING AND C O N S UL T IN G VOLUME I RESEARCH VOLUME I RESEARCH SHARE OF POPULATION BY AGE COHORTS, 2011 – 2031 TOTAL FALL ENROLLMENTS PROJECTIONS Campus Catchment Area Campus Catchment Area 178 179 + Hood Johnson ' Cleburne • c~ @ Northwest ... Northeast @ South @ Southeast @ Trinity River Mile Radius 0 5 Miles 0 10 Miles 0 15 Miles Population Age 18-64 LJ 510,000 -530,000 c:]520,000 -~30,001 □FACILITY PROGRAMM IN G A N D CO N SU LTI NG Information shown hereon is a graphical representation only and based upon available information. Facility Programming and Consu lting cannot be responsible for consequences res ulting from error or omission in the information and graphical representations made hereon. ,~ Tarranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN :::::::~~========~=::;:---...-r--------..----r----....... --------..... ---_----,,_-... _.....,,=--=-----.7"'1'""...,,.~b!--;..-;:_-;,""L---_-'"'1.,..,..-.....-~-------"T---_-.::-_-_-_-_-_-...,-..:::___,,--........ .....,. a O 5 10Mi les W Source: ESRI and Facility Programming and Consu lting @ Northwest @ Northeast @ South Southl • @ Southeast @ Trinity River Mile Radius O s Miles 0 10 Miles 0 15 Miles Annual Growth Population Age 18-64 LJ 50.0% -52.0% -54.0% □~1.0% -53 .0% ->4.0% □FACILITY PROGRAMMING A N D CONSULT I NG Information shown hereon is a graph ica l representation only and based upon available information Foc:il ity Programm ing and Consu lting cannot be responsib le for consequences resu lting from error or omission in th e in formation and graph ica l representat ions made hereon. VOLUME I RESEARCH VOLUME I RESEARCH 2021 POPULATION AGE 18 – 64 POPULATION GROWTH AGE 18 – 64, CAGR 2021 – 2031 ZIP Code Analysis ZIP Code Analysis 180 181 + I I I I A.tie • I . Hood Cleburne • @ Southeast Campus c:J Catchment Area Catchment Area : Top ZIP Codes comprised of 6,499 students (CUML 79.6%); Capture Rate: 1 .9% Mile Radius O s Miles 0 10 Miles Q 15 Miles Students by ZIP Code o ~o -~200 □~25 -~300 -~75 ->300 .. , all --- Information shown hereon is a graphical representation only and based upon available information. Facility Programming and Consulting cannot be respon~ble for consequences resulting from error or omission in the information and graphical representations made hereon. f-1' I I I I • •4 / • , I I C L .. I' ..... .. I Whi . . --------- 0 0 5 10Mi les W Source: ESRI and Facility Programming and Consulting ... :; . j~ I • • • I • I ~ I @ Southeast Campus Mile Radius 0 5 Mi les 0 15 Miles 0 10 Miles ,~ Tarranl Cou11ty College· ~ WCCE55 wm•• AEACH. Sparse Dense CORGAN I - Information shown hereon is a graphical representation only and based upon available information Facility Programming and Consulting cannot be responsible for consequences resu lting from error or omission in the information and graphical representations made hereon. VOLUME I RESEARCH VOLUME I RESEARCH STUDENT RESIDENCE DENSITY BY ZIP CODE STUDENT RESIDENCE DENSITY HEAT MAP TCC has no on-campus student residences TCC has no on-campus student residences 182 183 +-,~ T arranl Cou11ty College· ~ WC:CE55 wm .. AEACH. CORGAN VOLUME I RESEARCH VOLUME I RESEARCH Campus Access Vehicular and Pedestrian Circulation VEHICULAR CIRCULATION The Southeast College campus is located in Arlington, West of State Highway 360, South of Southeast Parkway, and East of New York Avenue. The main drives connect the campus to Southeast Parkway and New York Avenue. There are also internal drives that provide access between drop-offs and parking lots. None of the proposed phases would negatively impact vehicular paths and/or traffic with the exception of the construction material drop offs and the staging of construction materials. PEDESTRIAN CIRCULATION There are sidewalks along all three roadways, but only Southeast Parkway provides pedestrian connectivity to the campus. There is also a public bus drop off/pick up point located on the North side of the main building. TEX A S 3 6 0 T O L L R D . SOUTHEAST PKWY. S C O L L I N S S T . NE W YO R K AV E . WEBB L Y N N R D . CAMPUS ACCESS FRAMEWORK Vehicular and Pedestrian Traffic 184 185 + ,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN .r VOLUME I RESEARCH Student using software to explore digital modeling. VOLUME I RESEARCH Labor Market Analysis Southeast Campus Occupational Programs Fastest Growing Occupations 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #5: Web Developers — #10: Chefs and Lead Cooks — #11: Computer User Support Specialist — #16: Food Service Managers Occupations Adding the Most Jobs 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #5: First-Line Supervisors of Office and Administrative Support Workers Highest Paying Occupations Dallas, North Central Texas, Tarrant WDAs — #10: Computer Network & Support Specialists — #11: Web Developers Occupations With Greatest Annual Openings 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #4: First-Line Supervisors of Office and Administrative Support Workers FPC provided data related to job demand, need, and growth within the College’s service area and the Greater Dallas- Fort Worth-Arlington, Texas, MSA (Metropolitan Statistic Area). This study was cross- walked with the programs that the Southeast Campus offers and the available top 20 occupations were outlined. Students taking notes during classes. Culinary Arts students learning in the extensive teaching kitchen. 186 187 + I TRINIIY LEVEL 2. MAIN ST. I'-Bookstore 1' Porking Goroge Student life Center ,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN VOLUME I RESEARCH Trinity River "Main Street" near Rotunda and parking garage. Recently renovated Learning Commons. The Idea Store is an important connection between the campus and downtown Fort Worth. VOLUME I RESEARCH Trinity River Campus Campus Background The Trinity River Campus is comprised of two physical locations; Trinity River Campus and Trinity River Campus East. The campuses, separated by only a half mile, are easily accessible by road or a beautiful walk along the adjacent West Fork Trinity River path. The Trinity River Campus offers a number of general education programs supporting careers in the STEM disciplines while also provided signature educational path in areas such as sign language. The Trinity River Campus was purchased from RadioShack in 2008 and opened its doors to its first students in the fall of 2009. The master plan team’s tour with the campus President and their faculty and staff established a background of the campuses identity and the direction that the campus leadership had in mind. The former corporate identity of the building had caused the campus to develop in a staggered manner, and a comprehensive review of program placement was welcomed. The spatial limitations of the building constrains the placement of program. The inadequacies of the existing space and layout was most prevalent for the Onboarding and Health Professions programming. Access for potential and current students is hampered by the poor visibility of the current Onboarding location and layout. The Health Professions programs lack space that is properly sized or outfitted for optimal utilization. The exterior conditions of the campus were also identified as an asset that can further engage students and other community members. Master plan programming for the Trinity River Campus requires multiple building and campus wide improvements. While the building is beautiful, it is over 15 years old and has some deferred maintenance and functional improvements which need addressed. Trinity River currently has a multi-level “Main Street” in the TRTR Building which provides a number of student services. A major project of the master plan on the campus is the further development of a main, welcoming, accessible entry point which provides easy and direct access to the “Main Street". The construction of a new fourth wing is recommended to house the Health Care Professions. Development of the new tower and all interior renovations should include the implementation of the College initiative 3 Goals and 8 Principles. “From the moment you set foot on TCC Trinity River Campus, you will notice something truly special about its environment. The College has not only invested in a positive learning space that accommodates a community of learners, but it maintains an equitable culture of care to support our students and each other. By doing so, we ensure a consistent and successful academic experience for all. Together, our diversity creates a rich campus community.” — Dr. Madison 188 189 + PEACH STREET BLUFF STREET (]) O> I >-3: I 1-w w a:: 1-(/) z 0 (/) a:: w 0 z w I TRPG PARKING TRTR ELBOW ,~ T arranl CouHt)' College· ~ WCCE55 wm•• AEACH. CORGAN TRIN ITY RIVER Ch \,"~--_#..,/ VOLUME I RESEARCH TRINITY RIVER CAMPUS SITE PLAN Master Plan Landscape Plan VOLUME I RESEARCH Trinity River Campus Key Campus Statistics Year Constructed: 2003 Campus Size: 39.9 acres in downtown Fort Worth Building Inventory: 1 Building Complex, 965,360 SF Campus President: Dr. Madison Student Enrollment: 5,908 students (shared with Trinity River Campus East) Signature Programs: — GIS Technology — Healthcare Professions — Sign Language Interpreting GAP ANALYSIS Gap analysis identified inequities between campuses and synthesized them into needs to be accommodated into the master plan. Work sessions with faculty and staff at each campus helped identify deficiencies and desired improvements. The work session with the campus faculty and staff provided an opportunity for an iteration of the phases to be reviewed and the campus priorities to be stated. This opportunity yielded the valuable feedback that the campus was lacking in: — A defined front entry. — A consolidated “One-Stop Shop” for students with Onboarding, student services, and a Welcome Center. — The Health Professions facilities were also identified as being sub-par and an urgent issue to resolve to improve campus perception and student service. 0' 100' 200' 400' North +,~ T arranl C ou11ty College· ~ WCCE55 wm•• AEACH. CORGAN ■ ■ ■ ■ L. I / D I ~ ~ (k_-__ ,,r'--\ / ._, ,-(+:--..... _\ ,', t \ I ' \ ' -_J -· -\___J 'l 7 I I J _J ,-'\. (<<::: __ '~ _J ~----. FO R K (T R W F ) WE S T FOR K ) F CLE A R CRT ( TRPGPARKING TRIN I T Y ) RTR T ( EAST F O R K (TRE F ) TRTRELBOW VOLUME I RESEARCH VOLUME I RESEARCH LEGEND Good Facility Condition Fair Facility Condition Poor Facility Condition Critical Facility Condition TRINITY RIVER Trinity River Campus Facility Condition Assessment Report STREET Based on the facility condition assessment provided by Jacobs, this campus is not that old and most of the issues are that of deferred maintenance or functional improvements. Based on the Facility Condition Index (FCI), there are 10 buildings on this campus that have a good FCI score. The majority of the building on this campus are in the good range based on the FCI. FCI Categories: —Good: 0 – 0.02 —Fair: 0.02 – 0.05 —Poor: 0.06 – 0.19 —Critical: +0.20 MI L L S ST R E E T PEACH STREET BLUFF STREET HE N D E R S O N ST R E E T (H W Y 19 9 ) Poor Buildings: The master plan phasing addresses the following critical issues: —TRPG Tower (0.07) —Phase 1 — New Onboarding Center Addition —Phase 2 — New Health Professions Innovation Center Tower —Phase 3A — Renovate Rotunda and Community Ed. space —Phase 3B — Renovate Science Labs into Synergy Labs TA Y L O R ST R E E T IDEA STORE —Phase 3C — Renovate Healthcare Workforce Annex (TRIS) BELKNAP STREET FACILITY CONDITION ASSESSMENT DIAGRAM Existing Conditions Site Plan BELKNAP STREET 0' 100' 200' 400' North —Phase 4E — Renovate Learning Commons Facility Condition Index (FCI) is the total cost of needed building repairs and renewal divided by the current cost of replacing the building. Each building’s FCI score reflects the current condition of the building: Good, Fair, Poor, or Critical 190 191 +,~ T arranl CouHt)' College· ~ WCCE55 wm•• AEACH. CORGAN -------- -----------■ ■ ■ ■ ■ L/-j □ _J ,.._7 _J _J FO R K (T R W F ) WE S T FOR K ) F CLE A R CRT ( TRPGPARKING TRIN I T Y ) RTR T ( EAST F O R K (TRE F ) TRTRELBOW VOLUME I RESEARCH VOLUME I RESEARCH LEGEND Utilization >75% Utilization 50% – 75% Utilization 0% – 50% Program Defined Utilization TRINITY RIVER Not Assignable Trinity River Campus Space Utilization Study STREET Based on overall building utilization, there are zero buildings on this campus that have a good overall utilization. Out of the six towers that serve students of the Trinity River Campus, the majority that are scheduled contain space scheduled for classrooms or labs that are below the utilization target. Utilization Categories: —Good: +75% —Fair: 50% – 75% —Poor: 0% – 50% —Program Specific Utilization: Utilization standards not applied MI L L S ST R E E T PEACH STREET BLUFF STREET HE N D E R S O N ST R E E T (H W Y 19 9 ) Overall building utilization identifies current opportunities within existing campus class lab and classroom inventory to determine if they are capable of supporting current and projected enrollment or if additional inventory is needed. Analysis utilizes course schedule data from the Fall 2021 semester. —Not Assignable: No Class Labs or Classrooms Poor Utilization: —East Fork Tower (TREF) (30.6%) —Trinity River Tower (TRTR) (44.9%) The renovation of a former corporate campus to work within a community college model has caused issues as programs and section sizes have grown. Primary limiters to higher utilization were identified as under-sized classrooms or labs and that most spaces lack technology upgrades for active teaching. Additionally, the infill of programming into available space as need is identified has caused the majority of spaces to not be used for the best possible function. Program Specific Utilization: TA Y L O R ST R E E T IDEA STORE —N/A (TRIS) BELKNAP STREET BELKNAP STREET SPACE UTILIZATION DIAGRAM Existing Conditions Site Plan 0' 100' 200' 400' North 192 193 194 195 + Market Summary □FACILITY PROGRAMM ING AND C O N SULTING 2021 v TCC: TR Campus Catchment Area, 2021F Age Groups 0 :514 0 15-17 0 18-34 0 35-64 0 2:65 Households 533.300 Total $223.900 Home Value 2010 2021 2031 2010 2021 2031 No High School High School Degree or Equivalent Some College, No Degree Associates Degree 37.7% Bachelor's Degree Graduate Degree Total Population 1,282,900 1,530,100 1.775.800 10-YrProjected CAGR ► 1.5% Population Age 18-64 798,500 940,700 1,071,400 10-YrProjectedCAGR ► 1.3% Educational Attainment V SOURCE: ESRI I Page 1 of2 Race/ Ethnicity Diversity 78. 7 Index 0 White 0 Black 0 Asian 0 Other Q Hispanic NOTE: Per.ions of Hspanic Origin may be of any race. I Th e Civersitylndcx mcast1es the piooabil iy tllat ~vo people from the same M!0 will be from different race/ ethnic groups . A Dversily Index 1111:re,~f-!i l11J1r1 II lo 1{X> as lt1e Iq11lal11x1 1s evmly d1•.11ci-xi 11i!o lwc1 f)r rrK •~ ,~:,~, f-!lhrnc grrnIIis Income $66,500 Median HH Income $30,800 Per Capita Income □FACILITY Market Summary PROGRAMMING AND CONS ULT I NG 2021 v TCC: TR Campus Catchment Area, 2021F 0 Businesses Q Employment An estimated 44,430 busin esses are lo cated within the Market Area and they employed approximately 537,250 workers. Businesses and Employment Sector PCT Businesses Employmen1 Retail Health Care Accommodation Professional Manufacturing Educatio n Other Serivces Construction Fin ance Wholesale Government Transportation Real Estate Ad ministrative Entertainment Informatio n Mining Utilities Unclassified Headquarters A gricultu re 15.3% 8.1% 8.0% 8.9% 3.4% 2.5% 12.5% 7.2% 5.9% 2.7% 1.2% 1.9% 5.5% 3.1% 1.7% 1.7% 0.4% 0.1% 9.2% 0.3% 0 .3% 6,800 3,620 3,560 3,940 1,520 1,090 5,580 3,180 2,620 1,210 530 850 2,450 1,390 760 760 170 40 4,100 140 130 76,550 70,570 54,580 47,500 45,720 45,290 35,460 26,980 23,980 22,100 19,630 16,380 14,240 12,320 8,640 7,480 2,720 2,620 2,440 1,430 640 c:--=;;;;;;;- PCT 14.21' 13.1% 10.2% 8.8% 8.5% 8.4% 6.6% 5.0% 4.5% 4.1% 3.7% 3.0% 2.7% 2.3% 1.6% 1.4% 0.5% 0.5% 0.5% 0.3% 0.1% • Ma rket Area: Is the same as the region refe renced in the YELLOW ba r highlighted at the top of the page ,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN V SOURCE: ESRI I Page 2 of2 Occupations Management Professional Sales Admin Farming Construction Maintenance Production Transportation 0 White Collar Q Blue Collar &O.K Q Services 17.1'6 21.7" 0.1% 10.4% VOLUME I RESEARCH VOLUME I RESEARCH MARKET SUMMARY MARKET SUMMARY Campus Catchment Area Campus Catchment Area 197 + Education Summary PROGRAMM ING AND CO NSULT ING 2021 v TCC: TR Campus Catchment Area, 2021F Education Enrollment Total Enrolled in School Not Enrolled in School 409,900 982,500 Percent in/ Not in School 29.4% 70.6% School Enrollment by Grade Level GRAD 20K 0 PRE-Preschool -KND-Grade 12 0 Higher Ed SOURCE: 2015-2019 American Community Survey Percent of Enrolled 70.4% K-12 18.9% College 4.9% Grad School V SOURC E: ESRI , ACS Household Expenditures on Education Total Spending Average/ Household Index Spending Category College Tuition K-12 Tuition Other School Supplies Rental of Books/ Equipment Supplies for College Test Preparation/ Tutoring Services Supplies for K-12 Schools Vocational Tuition Tuition for Other Schools Supplies for Preschool Supplies for Vocational Schools $831,318,600 $1,559 90 Total Expenditures $489,262,000 $114,304,000 $32,315,700 $28,766,500 $23,693,800 $12,507,100 $11,877,300 $7,554,900 $6,908,200 $1,613,900 $488,200 I Page 1 of 1 Average/ Index Household $917 87 $214 90 $61 99 $54 97 $44 101 $23 90 $22 105 $14 100 $13 92 $3 96 $1 99 NOTE: An index of 100 reflects the national average. An index of 120 s uggests s pending is 20 percent above the average. ,~ T arranl Cou11ty College· WCCE55 wm•• AEACH. CORGAN SOURC E ESRI and Faci lity Progra mming and Con sulting 2,000,000 Historic Population Estimates I 1,800,000 1,600,000 1,400,000 1 200 000 1,305,300 ' ' 1,000,000 --------1,071,400 940,700 --------------------- 811~,4~00!_..----------------'----+----+---+-----+---+--+----+---+------l----l 800 ,000 c- 600 ,000 381,200 ---------------441,100 400,000 325,!7~00~----------------------- ----- 200 ,000 58,000 62,400 ----------------------- - - - ----- - - - ---- - ------69,000 0 2011 2013 2015 2017 2019 2021 2023 2025 2027 2029 2031 -2011-21 Total Population CNG: 224,700, 17.2% or CAGR 1.6% 11 2021-31 CNG: 245,700, 16.1% or CAGR 1.5% -2011-21 Population Age 18-64 CNG: 129,200, 15.9% or CAGR 1.5% 11 2021-31 CNG: 130,700 , 13.9% or CAGR 1.3% -2011-21 Population Age 18-34 CNG: 55,500, 17.1% or CAGR 1.6% 11 2021-31 CNG: 59,900, 15.7% or CAGR 1.5% -2011-21 Population Age 15-17 CNG: 4,400, 7.6% or CAGR 0.7% 11 2021-31 CNG: 6,500 , 10.5% or CAGR 1.0% VOLUME I RESEARCH VOLUME I RESEARCH EDUCATION SUMMARY HISTORIC AND PROJECTED POPULATION ESTIMATES Campus Catchment Area 196 Campus Catchment Area 198 199 + 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% SOURCE ES RI and Faci lity Prog ramming and Con sult ing ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 u, OC) C) ..... ..,, OC) ..... ,.._ C! ..... M ..,, OC) C) CJ) CJ) CJ) 0 0 0 .... .... .... .... N N N N ('I) ('I) ('I) ('I) ('I) .... .... .... .... .... .... .... ..... ..... ..... .... ..... .... .... ..... ..... ..... ..... ':§e. '#. ':§e. -;fl. ':§e. ':§e. 0 ':§e. ':§e. ':§e. '#. .... .... 0 0 0 0 -;1e. ':§e. ':§e. ':§e. ....; a, en OC) 0 0 ';;!!. ':§e. '#. ':§e. ':§e. ....; ....; ,.._ ,.._ u, :1, 0 0 0 ':§e. ';;!!. ....: co co M ..... a, 0 0 0 M co co I'-; ..,, OC) 0 M M M co u;; co ,.._ u, u, ..,, M M M in ..,, in in in in M M M M M M in in M M M M M M '#, 0 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Percentage Point Change by Cohort and 10-YearTime Frames 2010-21 Age ~14 -2011-21: -1.9% II 2021-31 : -0 .8% 2010-21 Age 15-17 -2011-21: -0.4% II 2021-31: -0 .2% 112021-31:-0.1% 112021-31:-1.1% a 2010 -21Age~65 -201 1-21:2.9% 112021-31:2 .1 % 20,000 18,000 16,000 14,000 12,000 10,000 8,000 6,000 4,000 2,000 SO UR CE : Tarran t Cou nty Coll ege and Fac ility Program mi ng and Cons ulti ng Historic Enrollment ,~ T arranl Cou11ty College· WCCE55 wm•• AEACH. Average of All Enrollment Scenarios Projected Growth (2021-31) Enrollment Change: 1,232 Total Percent Change: 23.3% Annual Growth (CAGR): 2.12% CORGAN 7,613 6,510 6,011 5,906 2,452 2010 2011 20 12 20 13 201 4 20 15 20 16 201 7 201 8 2019 20 20 2021 2022 202 3 202 4 2025 2026 20 27 202 8 20 29 20 30 -Based on 2016-21 Trend Line -2021 Capture Rate (2021 Enro llmenU 2021 Col lege Service Area Population Age 18-64) Held Constant at 0.4% -catchment Area Population Age 18-64 , CAGR 2021-31 Held Constant at 1.3% -9-12 Grade Graduate Growth in Catchment Area (Institutions with >100 Graduates), CAGR 2015-20 Held Constant at 3.7% -Ave rage of all Enrollment Projection Scenarios (minus Trend Line) PR OGRAMMING AND CO N S UL T IN G VOLUME I RESEARCH VOLUME I RESEARCH SHARE OF POPULATION BY AGE COHORTS, 2011 – 2031 TOTAL FALL ENROLLMENTS PROJECTIONS Campus Catchment Area Campus Catchment Area 200 201 + Hood @ Northwest ... Northeast @ South @ Southeast @ Trinity River Mile Radius O s Miles 0 10 Miles 0 15 Miles Population Age 18-64 LJ 510,000 -530,000 c:]520,000 -~30,001 PROGRAMM IN G A N D CO N SU LTI NG Information shown hereon is a graphical representation only and based upon available information. Facility Programming and Consulting cannot be responsible for consequences resulting from error or omission in the information and graphical representations made hereon. Wise _____ (.....,.___..,,_ a O 5 10Mi les W Source: ESRI and Facility Programming and Consu lting I ----r ___ ..,l _ @ Northwest @ Northeast @ South @ Joljnson @ Southeast @ Trinity River Mile Radius O s Miles 0 10 Miles 0 15 Miles Denton r Mound• -r- 1 I I I I I Annual Growth Population Age 18-64 ,~ Tarranl Cou11ty College· WCCE55 wm•• AEACH. CORGAN LJ 50.0% -52.0% -54.0% -53 .0% ->4.0% PROGRAMMING A N D CONSULT I NG Information shown hereon is a graphical representation only and based upon available information Facility Programming and Consulting cannot be responsible for consequences resulting from error or omission in the in formation and graphical representations made hereon. VOLUME I RESEARCH VOLUME I RESEARCH 2021 POPULATION AGE 18 – 64 POPULATION GROWTH AGE 18 – 64, CAGR 2021 – 2031 ZIP Code Analysis ZIP Code Analysis 202 203 + @ Trinity River Campus D Catchment Area Catchment Area: Top ZIP Codes comprised of 4 ,302 students (CUML 79.4%); Capture Rate: 0 .5% Mile Radius O s Miles 0 10 Miles 0 15 Mil es Students by ZIP Code O :;;o -:;;100 0:;;25 -~00 -:;;50 ->200 PROGRAMM ING A N D CO N SU LTI NG Information shown hereon is a graphical representation only and based upon available information. Facility Programming and Consulting cannot be responsible for consequences resulting from error or omission in the information and graphical representations made hereon. , I "' . , .. .. ' .:-\ ,. .. • I .. ' I . .. ' • C ' •• ) 0 0 5 10Miles W Source: ESRI and Facility Programming and Consulting • @ Trin it y River Campus • •• Mile Radius Q s Miles O 15 Mi les Q 10 Miles ,~ Tarranl Cou11ty College· WCCE55 wm•• AEACH. Spa rse Dense CORGAN Information shown hereon is a graphical representation only and based upon available information Facility Programming and Consulting cannot be responsible for consequences resulting from error or omission in the information and graphical representations made hereon. VOLUME I RESEARCH VOLUME I RESEARCH STUDENT RESIDENCE DENSITY BY ZIP CODE STUDENT RESIDENCE DENSITY HEAT MAP TCC has no on-campus student residences TCC has no on-campus student residences 204 205 +-,i~ T arranl Cou11ty College· WC:CE55 wm .. AEACH. CORGAN VOLUME I RESEARCH VOLUME I RESEARCH Campus Access Vehicular and Pedestrian Circulation VEHICULAR CIRCULATION The vehicular traffic will access the campus either from Henderson Street or by Belknap Street. The parking garage in TRPG is the primary entry for students while the circle drive off of Belknap Street provides a visible access point for visitors. School buses also use the gravel drive along the North edge of the site. With some of the parking spaces at the Rotunda entry being removed due to the proposed construction, the parking garage will be more utilized. None of the proposed phases would negatively impact vehicular paths and/or traffic with the exception of the construction material drop offs and the staging of construction materials. PEDESTRIAN CIRCULATION This campus has the highest potential for the pedestrian traffic due to its close proximity to housing and downtown Fort Worth. The location of the Idea Store on the corner of Belknap Street and Taylor Street provides a visible entry for pedestrians. I N T E R S T A T E 3 5 TX HWY 280 W 7TH ST . E BELKN A P ST. H O U S T O N S T T X H W Y 1 9 9 N M A I N S T . CAMPUS ACCESS FRAMEWORK Vehicular and Pedestrian Traffic 206 207 + ,~ TarronlC wccEss wn_ouHt)' College· AEACH. CORGAN VOLUME I RESEARCH Respiratory Therapy students practicing on a dummy. VOLUME I RESEARCH Labor Market Analysis Trinity River Campus Occupational Programs Fastest Growing Occupations 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #3: Respiratory Therapists — #4: Physical Therapy Assistants — #5: Web Developers — #9: Cardiovascular Technologists and Technicians — #14: Radiologic Technicians — #18: Licensed Practical and Licensed Vocational Nurses Occupations Adding the Most Jobs 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #4: Computer User Support Specialists — #5: First-Line Supervisors of Office and Administrative Support Workers — #7: Licensed Practical and Licensed Vocational Nurses Highest Paying Occupations Dallas, North Central Texas, Tarrant WDAs — #11: Web Developers Occupations With Greatest Annual Openings 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #4: First-Line Supervisors of Office and Administrative Support Workers — #9: Licensed Practical and Licensed Vocational Nurses FPC provided data related to job demand, need, and growth within the College’s service area and the Greater Dallas- Fort Worth-Arlington, Texas, MSA (Metropolitan Statistic Area). This study was cross- walked with the programs the Trinity River Campus offers and the available top 20 occupations were outlined. Student participating in the Sign Language program. Students utilizing the computers at the Learning Commons. 208 209 + Cou11ty Collcg Tarranl ACH. , WCCE55 wm•• AE ,· CORGAN ~- F 1\ ~..,. ~;;:. VOLUME I RESEARCH THRA lobby and classrooms. Health Professions Auditorium. Exterior shaded area with outdoor circulation, water features, and seating. VOLUME I RESEARCH Trinity River Campus East Campus Background The Trinity River Campus is comprised of two physical locations; Trinity River Campus and Trinity River Campus East. The campuses, separated by only a half mile, are easily accessible by road or a beautiful walk along the adjacent West Fork Trinity River path. Trinity River Campus East focuses on providing quality accredited healthcare programs as its main educational focus. Trinity River Campus East, a newer campus, became operational in 2011. The master plan team’s tour with the Real Estate and Facility staff established a background of the campuses identity and the direction that the campus leadership had in mind. The initial identity of the campus was altered during construction from administrative functions to Health Professions programming. This has caused the campus to infill within spaces that were not originally designed for the current programming, and a comprehensive review of program placement was welcomed. The spatial limitations of the building constrains the placement of program. The Health Professions programs lack space that is properly sized or outfitted for optimal utilization. The master plan team was invited to explore the different potential futures of the campus through the lens of best possible use. This included thinking about the possibilities of the campus not just as performing college level functions, but also as working with community members. The urban location of the campus in downtown Fort Worth provides the College an invaluable asset. Trinity River Campus East is the newest Tarrant County College physical campus and as a result does not have a significant amount of deferred maintenance. However, while in physically good condition, the facilities are not suited for health care education. Multiple levels, exterior access classrooms, long linear buildings, and minimal room for future expansion suggest this location is not the best fit for the TCC health care professions. Master planning looks slightly different from the other campuses, as it is the recommendation of the team to repurpose the building for a higher and better use. The Health Care Professions should be located in a newly constructed tower on the Trinity River Campus. Development of the new tower should include the implementation of the College initiative 3 Goals and 8 Principles. "“Our mission is to graduate highly qualified Health Care Professionals that exhibit a desire to serve and advocate for patient safety with a spirit of excellence and an aspiration for lifelong learning.”" — Trinity River Campus East Mission + f-- 1 ' --', ·:_-_-- --....:::....-' ---------- -, ',',I ' :ii~--'"'l I ,--~F-'r1 ,-'---if) I ,,d ''10! I.--, ~n -~ ... J~ ,, I ··I ,, 11 ,, I I I ','1, I ,:,:~------' -.J•--··1 11 11 11 11 11 ,~ T arran l Cou11ty College· WCCE55 wm•• AEACH. CORGAN b1·· 1 . l J I I J I I VOLUME I RESEARCH VOLUME I RESEARCH TRHA TRHN Trinity River Campus East Key Campus Statistics Year Constructed: 2011 GAP ANALYSIS TRHN TRHP Campus Size: 8.75 acres in downtown Fort Worth Gap analysis identified inequities between campuses and synthesized them into needs to be accommodated into the master plan. Work sessions with faculty and staff at each campus helped identify deficiencies and desired improvements. Building Inventory: 5 Buildings, 134,364 SF BELKNAP STREET Campus President: Dr. Madison Student Enrollment: 5,908 students (shared with Trinity River Campus) TRHT CO M M E R C E ST R E E T TRHW CA L H O U N ST R E E T Signature Programs: The campus visit by the master plan team and discussion with faculty and staff familiar with the facility provided a background for campus resources that need improvement. This opportunity yielded the valuable feedback that: — Healthcare Professions — Nursing — Health Professions facilities are sub-par and an urgent issue to resolve to improve campus perception and student service. — The campus was lacking in having a defined front entry. — The architecture of the campus lacked the ability for significant changes to be possible. TRINITY RIVER CAMPUS EAST SITE PLAN Master Plan Site Plan 0' 50' 100' 200' North 210 211 + f-- 1 ._'....::.._J l J I I J I I ,~ T arranl Cou11ty College· WCCE55 wm•• AEACH. CORGAN VOLUME I RESEARCH TRHA TRHN TRHN TRHP BELKNAP STREET TRHT LEGEND Good Facility Condition Fair Facility Condition Poor Facility Condition Critical Facility Condition VOLUME I RESEARCH Trinity River Campus East Facility Condition Assessment Report Based on the facility condition assessment provided by Jacobs, this campus is not that old and most of the issues are that of deferred maintenance or functional improvements. Based on the Facility Condition Index (FCI), there is one building on this campus that has a good score. The majority of the buildings on this campus are in the poor range based on the FCI. The master plan phasing addresses the following critical issues: — Phase 1 — Trinity River Campus East Renovation Facility Condition Index (FCI) is the total cost of needed building repairs and renewal divided by the current cost of replacing the building. Each building’s FCI score reflects the current condition of the building: Good, Fair, Poor, or Critical FCI Categories: — Good: 0 – 0.02 Fair: 0.02 – 0.05 Poor: 0.06 – 0.19 Critical: +0.20 — — — CO M M E R C E ST R E E T TRHW CA L H O U N ST R E E T Poor Buildings: — TRHT Building (0.11) — TRHW Building (0.08) — TRHN Building (0.07) FACILITY CONDITION ASSESSMENT DIAGRAM Existing Conditions Site Plan 0' 50' 100' 200' North 212 213 + f-- 1 ._'....::.._J l J I I J I I ,~ T arranl Cou11ty College· WCCE55 wm•• AEACH. CORGAN VOLUME I RESEARCH VOLUME I RESEARCH LEGEND Utilization >75% Utilization 50% – 75% Utilization 0% – 50% Program Defined Utilization Not Assignable TRHA TRHN TRHN TRHP BELKNAP STREET TRHT SPACE UTILIZATION DIAGRAM Existing Conditions Site Plan Trinity River Campus East Space Utilization Study Based on overall building utilization, there are zero buildings on this campus that have a good overall utilization. Of the buildings at Trinity River Campus East, the majority that are scheduled contain space scheduled for classrooms or labs that should be considered separately from other programs based on the unique programming requirements. Overall building utilization identifies current opportunities within existing campus class lab and classroom inventory to determine if they are capable of supporting current and projected enrollment or if additional inventory is needed. Analysis utilizes course schedule data from the Fall 2021 semester. Separating these certain programs from the defined standards is appropriate at Trinity River Campus East because of the requirements of many of these programs. The history of the buildings is critical as originally the campus was intended for administrative functions. Many classrooms and labs lack the appropriate layout for Health Professions programs and architecture is unable to be altered to provide adequate spatial conditions for Health Professions programming or future growth. Utilization Categories: — Good: +75% — Fair: 50% – 75% — Poor: 0% – 50% — Program Specific Utilization: Utilization standards not applied — Not Assignable: No Class Labs or Classrooms Poor Utilization: — N/A Program Specific Utilization: — TRHA Building — TRHN Building — TRHT Building — TRHW Building CO M M E R C E ST R E E T TRHW CA L H O U N ST R E E T 0' 50' 100' 200' North 214 215 216 217 + Market Summary PROGRAMM ING AND C O N SULTING 2021 v TCC: TR Campus Catchment Area, 2021F Age Groups 0 :514 0 15-17 0 18-34 0 35-64 0 2:65 Households 533.300 Total $223.900 Home Value 2010 2021 2031 2010 2021 2031 No High School High School Degree or Equivalent Some College, No Degree Associates Degree 37.7% Bachelor's Degree Graduate Degree Total Population 1,282,900 1,530,100 1.775.800 10-YrProjected CAGR 1.5% Population Age 18-64 798,500 940,700 1,071,400 10-YrProjectedCAGR 1.3% Educational Attainment V SOURCE: ESRI I Page 1 of2 Race/ Ethnicity Diversity 78. 7 Index 0 White 0 Black 0 Asian 0 Other Q Hispanic NOTE: Per.ions of Hspanic Origin may be of any race. I Th e Civersitylndcx mcast1es the piooabil iy tllat ~vo people from the same M!0 will be from different race/ ethnic groups . A Dversily Index 1111:re,~f-!i l11J1r1 II lo 1{X> as lt1e Iq11lal11x1 1s evmly d1•.11ci-xi 11i!o lwc1 f)r rrK •~ ,~:,~, f-!lhrnc grrnIIis Income $66,500 Median HH Income $30,800 Per Capita Income Market Summary PROGRAMMING AND CONS ULT I NG 2021 v TCC: TR Campus Catchment Area, 2021F 0 Businesses Q Employment An estimated 44,430 busin esses are lo cated within the Market Area and they employed approximately 537,250 workers. Businesses and Employment Sector PCT Businesses Employmen1 Retail Health Care Accommodation Professional Manufacturing Educatio n Other Serivces Construction Fin ance Wholesale Government Transportation Real Estate Ad ministrative Entertainment Informatio n Mining Utilities Unclassified Headquarters A gricultu re 15.3% 8.1% 8.0% 8.9% 3.4% 2.5% 12.5% 7.2% 5.9% 2.7% 1.2% 1.9% 5.5% 3.1% 1.7% 1.7% 0.4% 0.1% 9.2% 0.3% 0 .3% 6,800 3,620 3,560 3,940 1,520 1,090 5,580 3,180 2,620 1,210 530 850 2,450 1,390 760 760 170 40 4,100 140 130 76,550 70,570 54,580 47,500 45,720 45,290 35,460 26,980 23,980 22,100 19,630 16,380 14,240 12,320 8,640 7,480 2,720 2,620 2,440 1,430 640 c:--=;;;;;;;- PCT 14.21' 13.1% 10.2% 8.8% 8.5% 8.4% 6.6% 5.0% 4.5% 4.1% 3.7% 3.0% 2.7% 2.3% 1.6% 1.4% 0.5% 0.5% 0.5% 0.3% 0.1% • Ma rket Area: Is the same as the region refe renced in the YELLOW ba r highlighted at the top of the page ,~ T arranl Cou11ty College· WCCE55 wm•• AEACH. CORGAN V SOURCE: ESRI I Page 2 of2 Occupations Management Professional Sales Admin Farming Construction Maintenance Production Transportation 0 White Collar Q Blue Collar &O.K Q Services 17.1'6 21.7" 0.1% 10.4% VOLUME I RESEARCH VOLUME I RESEARCH MARKET SUMMARY MARKET SUMMARY Campus Catchment Area Campus Catchment Area 218 219 + Education Summary PROGRAMM ING AND CO NSULT ING 2021 v TCC: TR Campus Catchment Area, 2021F Education Enrollment Total Enrolled in School Not Enrolled in School 409,900 982,500 Percent in/ Not in School 29.4% 70.6% School Enrollment by Grade Level GRAD 20K 0 PRE-Preschool -KND-Grade 12 0 Higher Ed SOURCE: 2015-2019 American Community Survey Percent of Enrolled 70.4% K-12 18.9% College 4.9% Grad School V SOURC E: ESRI , ACS Household Expenditures on Education Total Spending Average/ Household Index Spending Category College Tuition K-12 Tuition Other School Supplies Rental of Books/ Equipment Supplies for College Test Preparation/ Tutoring Services Supplies for K-12 Schools Vocational Tuition Tuition for Other Schools Supplies for Preschool Supplies for Vocational Schools $831,318,600 $1,559 90 Total Expenditures $489,262,000 $114,304,000 $32,315,700 $28,766,500 $23,693,800 $12,507,100 $11,877,300 $7,554,900 $6,908,200 $1,613,900 $488,200 I Page 1 of 1 Average/ Index Household $917 87 $214 90 $61 99 $54 97 $44 101 $23 90 $22 105 $14 100 $13 92 $3 96 $1 99 NOTE: An index of 100 reflects the national average. An index of 120 s uggests s pending is 20 percent above the average. ,~ T arranl Cou11ty College· WCCE55 wm•• AEACH. CORGAN SOURCE: ESRI and Facility Prog ramm ing and Consultin g 2,000,000 Historic Population Estimates 1,800,000 1,600,000 1,400,000 1 200 000 1,305,300 ' ' 1,000,000 940,70 811:!;,40~0~----------------- 800,000 ------1,071,400 0 ---------------- 600,000 0 400 000 381,20 ___ _ , 325,~70~0~---------------------- - - ---------------4 41,100 200,000 58,000 62,400 ------------------------ - - - - --------- - - - - ----69,000 0 2011 2013 2015 2017 2019 2021 2023 2025 2027 2029 2031 -2011-21 Total Popu lation CNG: 224,700, 17.2% or CAGR 1.6% 11 2021-31 CNG: 245,700, 16.1% or CAGR 1.5% -2011-21 Population Age 18-64 CNG: 129,200, 15.9% or CAGR 1.5% 11 2021-31 CNG : 130,700, 13.9% or CAGR 1.3% -2011-21 Population Age 18-34 CNG: 55,500, 17.1% or CAGR 1.6% 11 2021-31 CNG: 59 ,900, 15.7% or CAGR 1.5% -2011-21 Population Age 15-17 CNG: 4,400 , 7.6%o r CAGR 0.7% 11 2021-31 CNG: 6,500, 10.5% orCAGR 1.0% VOLUME I RESEARCH VOLUME I RESEARCH EDUCATION SUMMARY Campus Catchment Area HISTORIC AND PROJECTED POPULATION ESTIMATES Campus Catchment Area 220 221 + 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% SOURCE ES RI and Faci lity Prog ramming and Con sult ing ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. ':§e. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 u, OC) C) ..... ..,, OC) ..... ,.._ C! ..... M ..,, OC) C) CJ) CJ) CJ) 0 0 0 .... .... .... .... N N N N ('I) ('I) ('I) ('I) ('I) .... .... .... .... .... .... .... ..... ..... ..... .... ..... .... .... ..... ..... ..... ..... ':§e. '#. ':§e. -;fl. ':§e. ':§e. 0 ':§e. ':§e. ':§e. '#. .... .... 0 0 0 0 -;1e. ':§e. ':§e. ':§e. ....; a, en OC) 0 0 ';;!!. ':§e. '#. ':§e. ':§e. ....; ....; ,.._ ,.._ u, :1, 0 0 0 ':§e. ';;!!. ....: co co M ..... a, 0 0 0 M co co I'-; ..,, OC) 0 M M M co u;; co ,.._ u, u, ..,, M M M in ..,, in in in in M M M M M M in in M M M M M M '#, 0 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Percentage Point Change by Cohort and 10-YearTime Frames 2010-21 Age ~14 -2011-21: -1.9% II 2021-31 : -0 .8% 2010-21 Age 15-17 -2011-21: -0.4% II 2021-31: -0 .2% 112021-31:-0.1% 112021-31:-1.1% a 2010 -21Age~65 -201 1-21:2.9% 112021-31:2 .1 % 20,000 18,000 16,000 14,000 12,000 10,000 8,000 6,000 4,000 2,000 SO UR CE : Tarran t Cou nty Coll ege and Fac ility Program mi ng and Cons ulti ng Historic Enrollment ,~ T arranl Cou11ty College· WCCE55 wm•• AEACH. Average of All Enrollment Scenarios Projected Growth (2021-31) Enrollment Change: 1,232 Total Percent Change: 23.3% Annual Growth (CAGR): 2.12% CORGAN 7,613 6,510 6,011 5,906 2,452 2010 2011 20 12 20 13 201 4 20 15 20 16 201 7 201 8 2019 20 20 2021 2022 202 3 202 4 2025 2026 20 27 202 8 20 29 20 30 -Based on 2016-21 Trend Line -2021 Capture Rate (2021 Enro llmenU 2021 Col lege Service Area Population Age 18-64) Held Constant at 0.4% -catchment Area Population Age 18-64 , CAGR 2021-31 Held Constant at 1.3% -9-12 Grade Graduate Growth in Catchment Area (Institutions with >100 Graduates), CAGR 2015-20 Held Constant at 3.7% -Ave rage of all Enrollment Projection Scenarios (minus Trend Line) PR OGRAMMING AND CO N S UL T IN G VOLUME I RESEARCH VOLUME I RESEARCH SHARE OF POPULATION BY AGE COHORTS, 2011 – 2031 TOTAL FALL ENROLLMENTS PROJECTIONS Campus Catchment Area Campus Catchment Area 222 223 + Hood @ Northwest ... Northeast @ South @ Southeast @ Trinity River Mile Radius O s Miles 0 10 Miles 0 15 Miles Population Age 18-64 LJ 510,000 -530,000 c:]520,000 -~30,001 PROGRAMM ING A N D CO N SU LTI NG Information shown hereon is a graphical representation only and based upon available information. Facility Programming and Consulting cannot be responsible for consequences resulting from error or omission in the information and graphical representations made hereon. _____ (........__ Wise I ----, ___ ...J. - ... Northwest @ Northeast @ South @ Johnson @ Southeast @ Trinity River Mile Radius O s Miles 0 10Miles Q 15Miles ,~ T arranl C ou11ty College· WCCE55 wm•• AEACH. CORGAN Dento er Mound• .......,.__, __ _ Annual Growth Population Age 18-64 LJ50.0% -$2.0% _::,AO% LJ51.0% -$3.0% ->4.0% Lancaster • PROGRAMMI NG AND CONSU LT I NG Information shown hereon is a graphical representation only and based upon available information. Facility Programming and Consulting cannot be responsible for consequences resulting from error or omission in the information and graphical representations made hereon. VOLUME I RESEARCH VOLUME I RESEARCH 2021 POPULATION AGE 18 – 64 POPULATION GROWTH AGE 18 – 64, CAGR 2021 – 2031 ZIP Code Analysis ZIP Code Analysis 224 225 + @ Trinity River Campus D Catchment Area Catchment Area: Top ZIP Codes comprised of 4,302 students (CUML 79.4%); Capture Rate: 0 .5% Mile Radius O s Miles 0 10 Miles 0 15 Miles Students by ZIP Code O :;;o -:;;100 0 :;;25 -~00 -:;;50 ->200 PROGRAMM ING A N D CO N SU LTI NG Information shown hereon is a graphical representation only and based upon available information. Facility Programming and Consulting cannot be responsible for consequences resulting from error or omission in the information and graphical representations made hereon. ... ' I 4 .. ' - -• . ., , •' r. .. •• • . 1 • ' .. , • • • Wise r •• ' Jj - @ Trinity River Campus Mile Radius Q 5 Miles Q 15 Miles Q 10 Miles ,~ Tarranl Cou11ty College· WCCE55 wm•• AEACH. Sparse Dense CORGAN Information shown hereon is a graphical representation only and based upon available information. Facility Programming and Consulting cannot be responsible for consequences resulting from error or omission in the information and graphical representations made hereon. VOLUME I RESEARCH VOLUME I RESEARCH STUDENT RESIDENCE DENSITY BY ZIP CODE STUDENT RESIDENCE DENSITY HEAT MAP TCC has no on-campus student residences TCC has no on-campus student residences 226 227 +-,i~ T arranl Cou11ty College· WC:CE55 wm .. AEACH. CORGAN VOLUME I RESEARCH VOLUME I RESEARCH Campus Access Vehicular and Pedestrian Circulation VEHICULAR CIRCULATION The vehicular traffic will access the campus either from Belknap Street or Grove Street. The parking lots to the East of the campus is the primary student access point. None of the proposed phases would negatively impact vehicular paths and/or traffic with the exception of the construction material drop offs and the staging of construction materials. PEDESTRIAN CIRCULATION This campus has a high potential for pedestrian traffic due to its close proximity to housing and downtown Fort Worth. The below-ground plaza along Weatherford Street links the campus and downtown Fort Worth. The entry plaza and occupiable spaces between buildings provide accessible urban space for pedestrians. I N T E R S T A T E 3 5 TX HWY 280 W 7TH ST . E BELKN A P ST. H O U S T O N S T T X H W Y 1 9 9 N M A I N S T . CAMPUS ACCESS FRAMEWORK Vehicular and Pedestrian Traffic 228 229 + CORGAN VOLUME I RESEARCH Nursing students graduating. Sonography student using an ultrasound machine. Nursing students practicing on a dummy. VOLUME I RESEARCH Labor Market Analysis Trinity River Campus East Occupational Programs Fastest Growing Occupations 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #3: Respiratory Therapists — #4: Physical Therapy Assistants — #5: Web Developers — #9: Cardiovascular Technologists and Technicians — #14: Radiologic Technicians — #18: Licensed Practical and Licensed Vocational Nurses Occupations Adding the Most Jobs 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #4: Computer User Support Specialists — #5: First-Line Supervisors of Office and Administrative Support Workers — #7: Licensed Practical and Licensed Vocational Nurses Highest Paying Occupations Dallas, North Central Texas, Tarrant WDAs — #11: Web Developers Occupations With Greatest Annual Openings 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #4: First-Line Supervisors of Office and Administrative Support Workers — #9: Licensed Practical and Licensed Vocational Nurses FPC provided data related to job demand, need, and growth within the College’s service area and the Greater Dallas- Fort Worth-Arlington, Texas, MSA (Metropolitan Statistic Area). This study was cross- walked with programs Trinity River Campus East offers and the available top 20 occupations were outlined. 230 231 + ,~ T arranl CouHt)' College· WCCE55 wm•• AEACH. CORGAN VOLUME I RESEARCH Faculty breakout space. Focus rooms. Presentation and event space. VOLUME I RESEARCH TCC Connect Campus Background TCC Connect provides students with an alternative educational experience through eLearning and Weekend College. The campus is designed to provide online and accelerated learning options through a variety of course offerings to include eight- week courses, monthly-starts, May-mester and Winter-mester. All student services, such as advising, online tutoring, library services, writing center, and test proctoring, can be accessed online. The TCC Connect Campus was named a Top 60 Best Online Community Colleges and Trades Schools of 2022 — Intelligent.com. As TCC looks to the future, the College is exploring the possibilities for eLearning in terms of current infrastructure and future growth for students, faculty, and staff. The master plan team’s tour with the Campus President and their faculty and staff established a background of the campuses identity and the direction that the campus leadership, had in mind. While many of the campuses students engage in a distance- learning capacity, the physical futures of the campus were identified as being tied to future needs for additional on-location staff. The need for additional instructional spaces for Weekend College was also outlined, but potential facility sharing with Trinity River was a potential solution. The usage of technology impacts the ability for the campus to function to its desired degree. Technology for lecture capture and recording would improve the abilities of the campus. Maintaining the position of the campus on the cutting edge with its active teaching functionality is central to its success and ability to provide service for students. The master plan programming for TCC Connect should account for the faculty and staff needed to support current and future student growth. Although most student services are virtual, there is and will continue to be a need for additional space for the staff which support these functions. Student growth also requires additional faculty and faculty resources. Spaces to support the development of online course work, faculty collaboration, tech support, and administrative development are needed to support this unique college. The master plan should be mindful of the College initiative of 3 Goals and 8 Principles, applying them as possible to any renovations or expansions to the staff and faculty spaces of TCC Connect. “My commitment is to lead our faculty and staff to continue to provide students the best learning experience. Whether you are a first year student in one of our fully-online programs, or part of our Weekend College, we are here to assist you in your journey. I look forward to facilitating your success and wish you the best of luck in your college experience.” — Dr. Morales + L__ I I r j I ' ' L__ E6 0 0 / ···,\ f-------,,,..< \ . '-~--_#" ,~ T arranl Cou11ty College· WCCE55 wm•• AEACH. CORGAN 2060B-X MECH VOLUME I RESEARCH VOLUME I RESEARCH 24 0 0 A - X CO R R I D O R 2907A OPEN OFFICE 2801A OPEN OFFICE 2703-C 2903A CONFERENCE OFFICE 2905A 2906A 2802A 2803A 2804A 2805A STORAGE 2902A-S 2904A FOCUS FOCUS FOCUS FOCUS FOCUS FOCUS FOCUS 2900A-X 2800A-X CORRIDOR CORRIDOR 2503-R MEN'S 2561A-X 2801-C CONFERENCE 2460A-X 2860A-X 2702A 2901A IDF IDF ELECTRICAL 2602A-S STORAGE 2700A-X OFFICE OFFICE 2800B-X LOUNGE MECHANICAL 2360A-X CORRIDOR 2207 2500A-X 2206-C TRAININGCORRIDOR 2600A-X CORRIDOR CONFERENCE 2601-C 2210A 2701A 2560A-X CONFERENCE VIDEO PRODUCTION OFFICE ELECTRICAL 2300A-X 2502-R CORRIDOR WOMEN'S 2200A-X 2504B-X 1174-X 2301A-X CORRIDOR ELEV. 4 ELEV. LOBBY 2501A-S JANITORIAL 2103-C STORAGE 2101-K BREAK RM. CONFERENCE 2204A 2208A 2209A FOCUS FOCUS FOCUS 2211A 2212A 1171-X 1172-X 1173-X FOCUS FOCUS ELEV. 1 ELEV. 2 ELEV. 3 2202A 2203A FOCUS2100C-X FOCUS CORRIDOR 2102-C 2100B-X CONFERENCE LOBBY 2201A OPEN OFFICE 2100A-X STAIR B RECEPTION1181-X TCC Connect Key Campus Statistics Year Constructed: 2015 Campus Size: Single floor of Trinity River Campus West Fork Building Inventory: TRWF floor 2 — 30,290 SF Campus President: Dr. Morales Student Enrollment: 14,763 students across the college Signature Programs: — eLearning — Weekend College GAP ANALYSIS Gap analysis identified inequities between campuses and synthesized them into needs to be accommodated into the master plan. Work sessions with faculty and staff at each campus helped identify deficiencies and desired improvements. The work session with the campus faculty and staff provided an opportunity for an iteration of the phases to be reviewed and the campus priorities to be stated. This opportunity yielded the valuable feedback that: — Despite being a largely online campus, as student enrollment grows then there will be additional need for both instructional space and faculty workspaces. — Additionally, the lack of state-of-the-art technology directly impacts the ability for the campus to function to its desired degree. This technology for lecture capture and distance teaching was a unique requirement. TCC CONNECT FLOOR PLAN Master Plan Floor Plan 0' 10' 20' 40' North 232 233 + El ~ I I I =E rC7 ,------i __J I ~ ,------i ,------i ii '~,,' -t ~LA L_J EB D I I I __J ----, L__ E6 ,---- B I I B 0 :J '' I /-----,\ \'~--_#_.,/ 2060B-X MECH VOLUME I RESEARCH VOLUME I RESEARCH LEGEND Good Facility Condition Fair Facility Condition Poor Facility Condition Critical Facility Condition 2907A OPEN OFFICE 2801A OPEN OFFICE 2703-C 2903A CONFERENCE OFFICE 2905A 2906A 2802A 2803A 2804A 2805A STORAGE 2902A-S 2904A FOCUS FOCUS FOCUS FOCUS FOCUS FOCUSFOCUS 2900A-X 2800A-X CORRIDOR CORRIDOR 2503-R MEN'S 2561A-X 2801-C CONFERENCE 2460A-X 2860A-X 2702A 2901A IDF IDF ELECTRICAL 2602A-S STORAGE 2700A-X OFFICE OFFICE 2800B-X LOUNGE MECHANICAL 2360A-X CORRIDOR 2207 CORRIDOR 2500A-X 2206-C TRAINING 2600A-X CORRIDOR CONFERENCE 2601-C 2210A 2701A 2560A-X CONFERENCE OFFICE VIDEO PRODUCTION 2300A-X 2502-R CORRIDOR WOMEN'S ELECTRICAL 2200A-X 2504B-X 1174-X 2301A-X CORRIDOR ELEV. 4 ELEV. LOBBY 2501A-S JANITORIAL2103-C STORAGE 2101-K BREAK RM. CONFERENCE 2204A 2208A 2209A FOCUS FOCUS FOCUS 2211A 2212A 1171-X 1172-X 1173-X FOCUS FOCUS ELEV. 1 ELEV. 2 ELEV. 3 2202A 2203A FOCUS2100C-X FOCUS CORRIDOR 2102-C 2100B-X CONFERENCE LOBBY 2201A OPEN OFFICE 2100A-X STAIR B RECEPTION1181-X 24 0 0 A - X CO R R I D O R 0' 10' 20' 40' North TCC Connect Facility Condition Assessment Report While this campus is largely based online, it is embedded within the larger Trinity River Campus in the West Fork Tower (TRWF). The Facility Assessment Report for this campus analyzes the portions of the Trinity River Campus that are deemed relevant as they house physical portions of the TCC Connect campus. Based on the facility condition assessment provided by Jacobs, this campus is not that old and most of the issues are that of deferred maintenance or functional improvements. FCI Categories: — Good: 0 – 0.02 — Fair: 0.02 – 0.05 — Poor: 0.06 – 0.19 — Critical: +0.20 Fair Buildings: Based on the Facility Condition Index (FCI), there is one floor on this campus that has a good FCI score. The majority of the floors on this campus are in the good range based on the FCI. — TRWF Tower (0.02) The master plan phasing addresses the following critical issues: — Phase 1 — Upgrade Touch-Down Space and Technology — Phase 4 — Re-locate College IT and Support Services — Phase 5 — Expand TCC Connect FACILITY CONDITION ASSESSMENT DIAGRAM Existing Conditions Floor Plan Facility Condition Index (FCI) is the total cost of needed building repairs and renewal divided by the current cost of replacing the building. Each building’s FCI score reflects the current condition of the building: Good, Fair, Poor, or Critical 234 235 237 + ,I __J EE I I ,---, ,---, __J L.....J ----, EE __J ffi I I 0 0 /-----,\ \'~--_#_.,/ 2060B-X MECH VOLUME I RESEARCH LEGEND Utilization >75% Utilization 50% – 75% Utilization 0% – 50% Program Defined Utilization Not Assignable 2907A OPEN OFFICE 2801A OPEN OFFICE 2703-C 2903A CONFERENCE OFFICE 2905A 2906A 2802A 2803A 2804A 2805A STORAGE 2902A-S 2904A FOCUS FOCUS FOCUS FOCUS FOCUS FOCUSFOCUS 2900A-X 2800A-X CORRIDOR CORRIDOR 2503-R MEN'S 2561A-X 2801-C CONFERENCE 2460A-X 2860A-X 2702A 2901A IDF IDF ELECTRICAL 2602A-S OFFICE OFFICE STORAGE 2700A-X 2800B-X LOUNGE MECHANICAL 2360A-X CORRIDOR 2207 CORRIDOR 2500A-X 2206-C TRAINING 2600A-X CORRIDOR CONFERENCE 2601-C 2210A 2701A 2560A-X CONFERENCE OFFICE VIDEO PRODUCTION 2300A-X 2502-R CORRIDOR WOMEN'S ELECTRICAL 2200A-X 2504B-X 1174-X 2301A-X CORRIDOR ELEV. 4 ELEV. LOBBY 2501A-S JANITORIAL2103-C STORAGE 2101-K BREAK RM. CONFERENCE 2204A 2208A 2209A FOCUS FOCUS FOCUS 2211A 2212A 1171-X 1172-X 1173-X FOCUS FOCUS ELEV. 1 ELEV. 2 ELEV. 3 2202A 2203A FOCUS2100C-X FOCUS CORRIDOR 2102-C 2100B-X CONFERENCE LOBBY 2201A OPEN OFFICE 2100A-X STAIR B RECEPTION1181-X 24 0 0 A - X CO R R I D O R SPACE UTILIZATION DIAGRAM Existing Conditions Site Plan 0' 10' 20' 40' North VOLUME I RESEARCH TCC Connect Space Utilization Study The TCC Connect Campus, though it provides distance learning options, also must retain a physical location for Weekend College and for staff and faculty. Though there are classrooms that are part of the campus, the specialty usage of those spaces should make them exempt from the utilization targets. Overall building utilization identifies current opportunities within existing campus class lab and classroom inventory to determine if they are capable of supporting current and projected enrollment or if additional inventory is needed. Analysis utilizes course schedule data from the Fall 2021 semester. However, the ability for the spaces to be utilized to the utmost ability should not be ignored. Central to this goal, the lack of state-of-the-art technology directly impacts the ability for the campus to function to its desired degree. This technology for lecture capture and distance teaching is a defining requirement to maximize utilization, not just for students but also for faculty and staff. Future growth of the Weekend College also will incur need for additional instructional and faculty space. Utilization Categories: — Good: +75% Fair: 50% – 75% Poor: 0% – 50% — — — Program Specific Utilization: Utilization standards not applied — Not Assignable: No Class Labs or Classrooms Poor Utilization: — N/A Program Specific Utilization: — West Fork Tower (TRWF) floor 2 236 238 239 + 0 S14 0 15-17 0 18-34 0 35-64 0 c:!65 Market Summary 2 0 2 2 v T C C: CN Connect Catchment Area , 2021 F Age Groups 18-64 Households 693,300 Total $252,000 Median Home Value 2010 2022 2032 2010 2022 2032 No High School Total Population 1,600,000 1,946,000 2,187,000 10-YrProjectedCAGR 1 .2% Population Age 18-64 1,006,100 1,205,000 1,326,900 10-YrProjectedCAGR 1.0% Educational Attainment H igh School Degree or Equivalent Some College, No Degree Associates Degree 9.0% 43.5% Bachelor's Degree 23.9% Graduate Degree 10.6% V SO URCE : ESRI Race/ Ethnicity Diversity 81 .6 Index I Page 1 of 2 0 White 0 Black Q Asian Q Other Q Hispanic NOTE: Peisons of Hispa,,ic Ongin may be of any race. I The Divetsity Index measures the probal>lly that IWo people from the same area will be from different race/ ethnic groups. A llver.;ity lncex increases from Oto 100 as the population is evenly d1..;ded into IWoormore race I ethnic groups. Income $78,500 Median HH Income $37,800 Per Capita Income Market Summary 2022 v TCC : CN C onnect Catc hment A rea , 2021 F Q Businesses 0 Employment An estimated 55,640 business es are located w ithin the Market A rea an d t hey employed approximately 604,100 wo rk ers. In terms of e mployment, the Retail Trade secto r was t he larges t in t h e *Mar ket Area with approximat e ly 98,400 w orkers. Thi s se ctor accounted for an estimated 8,350 b u si nesses. Businesses and Employment Sector PCT Businesses Employme nt R etail Accom modati on He alth Care Educat ion M anufacturin g Profession al Other Se rivces Constru ction W holesale Govern ment Fi nance T ra nsportation Rea l Estate Adm inistrative Informati on Ent erta inment U ncl assi fie d H eadquarters Mining Utilities Agri c ulture 15.0% 8.1% 7.8% 2.4% 3.3% 8.7% 12.5% 7.5% 2.7% 1.2% 5.5% 2.3% 5.4% 3.3% 1.6% 1.8% 10.1% 0.3% 0.2% 0.1% 0.3% 8,350 4,530 4,350 1,360 1,820 4,820 6,950 4,150 1,500 650 3,070 1,280 3,010 1,810 910 980 5,640 160 120 50 140 98,400 73,070 60,010 53,300 48,550 44,710 42,000 33,190 27,550 22,720 21,870 19,370 16,160 13,020 11,760 11,190 3,200 1,660 1,230 620 530 PCT 16.3% 12.1% 9.9% 8.8% 8.0% 7.4% 7.0% 5.5% 4.6% 3.8% 3.6% 3.2% 2.7% 2.2% 1.9% 1.9% 0 .5% 0.3% 0.2% 0.1% 0.1% • Market Area: Is the same as the reg ion referenced in t h e YELLOW bar high lighted at the top of the page ,~ Tarranl Cou11ty College· WCCE55 wm•• AEACH. CORGAN V SOURCE: ESRI I Page 2 of 2 Occupations 11.9" Manag em ent Professional Sa les Ad mi n Farming Construction Maintenance Prod uction Transportation 0 W hite C ollar Q Bl ue Collar Q Services 18.3" 21.3" 1.9" 12A" 0.1% 5.6% 3 .2% 5.2% 10.1% VOLUME I RESEARCH VOLUME I RESEARCH MARKET SUMMARY MARKET SUMMARY Campus Catchment Area Campus Catchment Area 240 241 + Education Summary 20 2 2 v TCC: CN Connect Catchment Area , 2021 F Education Enrollment Total Enrolled in School Not Enrolled in School 504,900 1,266,900 Percent in/ Not in Schoo l 28.5% 71.5% School Enrollment by Grade Level Grade 5-8 Grad e 1-4 CLG 113K Grade 9-1 2 106K 92K PRE KND GRAD 112K 30K 26K 26K 0 PRE-Presc hool O KND-Gra de 12 0 Higher Ed SOURCE: 2016-2020 American Community Survey Percent of Enrolled 70.8% K-12 18.3% College 5.1% Grad School V SOU RCE : ESRI, ACS Household Expenditures on Education Total Spending Average/ Household Index Spending Category $1,308,134,400 $1,887 96 To tal Ex penditures I Page 1 of 1 Average/ Index H ousehold College Tuition $771,768,400 $1,113 93 K-12 Tuition $181,302,700 $262 97 Other School Su pplies $50,382,500 $73 105 Rental of Books/ Equipment $44,804,300 $65 102 Supplies for College $36,684,400 $53 106 Test Preparation/ Tutoring Services $19,441,800 $28 94 Supplies for K-12 Schools $18,424,700 $27 110 Vocational Tuition $11,801,800 $17 106 Tuition for Other Schools $10,722,000 $15 96 Supplies for Preschool $2,530,300 $4 102 Supplies for Vocational Schools $761,600 $1 105 NOTE: An index of 100 reflects the national average. An i ndex of 120 suggests spending is 20 percent above the average. SOURCE: ESRI and Facility Programming and Co nsulting 2,500,000 Historic Population Estimates 2,250,000 2,000,000 ,~ T arranl Cou11t y College· WCCE55 wm•• AEACH. l 1---1----J---f--l---+--t--t--~-2,188,200 --· ---------1,946,000 ---------------------1,750,000 1,65i!7,~60~0!------------- 1,500,000 1,326 ,900 1,250,00 0 1,039 , 1,000,000 1205 000 --1-~~l-~---'..~-'L__ ----------~~~------------------·--· ------------- 750,000 500,000 533 ,900 472 ,200 ----------------------------------------------396 ,000 250,000 74 ,200 79 ,300 83 ,200 ----------------------------------------------0 20 12 20 14 20 16 2018 2020 2022 2024 2026 2028 2030 2032 -2012-22 Total Popu lation CNG: 288,400, 17.4%or CAGR 1.6% II 2022-32 CNG: 242,200 , 12.4%or CAGR 1.2% -2012-22 Age 18-64 CNG: 165,700 , 15.9% or CAGR 1.5% 11 2022-32 CNG: 122 ,000, 10.1% or CAGR 1.0% -2012-22 Age 18-34 CNG: 76 ,200, 19.2% or CAGR 1.8% 11 2022-32 CNG: 61,700 , 13.1%or CAGR 1.2% -2012-22 Age 15-17 CNG: 5,100, 6.9%or CAGR 0.7% 11 2022-32 CNG: 3,900, 4.9%or CAGR 0.5% CORGAN VOLUME I RESEARCH VOLUME I RESEARCH EDUCATION SUMMARY HISTORIC AND PROJECTED POPULATION ESTIMATES Campus Catchment Area Campus Catchment Area 242 243 + 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% SOURCE: ESRI and Facil ity Programming and Consulting "$. "$. .... .... c .... .... .... .... &i .... c-.i .... "$. .... ...: M .. .... ...: M 0 M co M 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 Percentage Point Change by Cohort and 10-YearTime Frames Age $;14: -1 .9% 11 2022-32: -0.8% Age 15-17: -0.4% 11 2022-32: -0 .3% Age 18-34: 0.4% II 2022-32: 0.1% B 2012-22 Age ~65: 3.1 % II 2022-32: 2.4% II 2022-32:-1.4% 20,000 18,000 16,000 14,000 12,000 10,000 8,000 6,000 4,000 2,000 SOURCE : Tarrant County College and Facility Programming and Consulting Historic Enrollment 14,047 12,776 ,~ T arranl Cou11ty College· WCCE55 wm•• AEACH. CORGAN 18,415 17,771 15 ,290 14,123 13 ,975 Average of All Enrollment Scenarios Projected Growth (2021-31) Enrollment Change: 2,514 Total Percent Change: 19.7% Annual Growth (CAGR): 1.81 % 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 -Based on 2016-21 Trend Line -2021 Capture Rate (2021 Enrollment/ 202 1 Cdlege Service Area lnterpdated Popul ation Age 18-64) Held Constant al 1.()% -catchment Area Population Age 18-64, CAGR 2022-32 Held Constant at 1.0% -9-12 Grade Graduate Growth in Catchment Area (Institutions with > 100 Graduates), CAGR 2015-20 Held Cons tant at 3.4% -Average of all Enrollment Proj ection Scenarios (minus Trend Line) PROGRAMMING AND C ON SUl T I N G VOLUME I RESEARCH VOLUME I RESEARCH SHARE OF POPULATION BY AGE COHORTS, 2011 – 2031 TOTAL FALL ENROLLMENTS PROJECTIONS Campus Catchment Area Campus Catchment Area 244 245 + Tarrant Campus Locations ... Northwest @ South @ Trinity River @ Northeast @ Southeast Population Age 18-64 0 S10,000 -S40,000 D s20 ,ooo •sso,ooo -S30,000 ->50,000 PROGRAMMING AN D CONSULTING Information shown hereon is a graphical representation only and based upon available information. Facility Programming and Consulting cannot be responsible for consequences resulting from error or omission in the information and graphical representations made hereon Tarrant Campus Locations 6 0 5 10Mi les W Source: ESRI and Facility Programming and Cons ulting @ Northwest @ South @ Trinity River @ Northeast @ Southeast Annual Growth Population Age 18-64 D so .0% D :s:2 .0% -:s:4 .0% D :s:1 .0% -s3.o% ->4.o% ,~ T arranl Cou11ty College· WCCE55 wm•• AEACH. CORGAN Information shown hereon is a graphical representation only and based upon available information. Facility Programming and Consulting cannot be responsible for consequences resu lting from error or omission in the information and graphical representations made hereon. VOLUME I RESEARCH VOLUME I RESEARCH 2021 POPULATION AGE 18 – 64 POPULATION GROWTH AGE 18 – 64, CAGR 2021 – 2031 ZIP Code Analysis ZIP Code Analysis 246 247 + c:::::] Catchment Area Catchment Area: Top ZIP Codes comprised of 10,434 students (CUML 79 .4%); Capture Rate: 0.9% Students by ZIP Code 0 $0 -$200 0 $50 -$400 -$100 ->400 PROGRAMMING AN D CONSULTING Information shown hereon is a graphical representation only and based upon available information. Facility Programming and Consulting cannot be responsible for consequences resulting from error or omission in the information and graphical representations made hereon ,~ Tarranl Cou11ty College· WCCE55 wm•• AEACH. CORGAN ' ... ' I, \ • • . . .. . .. :•. • 4 • ' • , . , Parker • \ • . 1 6 0 5 10Mi les W Source: ESRI and Facility Programming and Cons ulting Tarrant Campus Locations @ Northwest @ South @ Trinity River ... Northeast @ Southeast Sparse Dense Information shown hereon is a graphical representation only and based upon available information. Facility Programming and Consulting cannot be responsible for consequences resu lting from error or omission in the information and graphical representations made hereon. VOLUME I RESEARCH VOLUME I RESEARCH STUDENT RESIDENCE DENSITY BY ZIP CODE STUDENT RESIDENCE DENSITY HEAT MAP TCC has no on-campus student residences TCC has no on-campus student residences 248 249 +-,i~ T arranl Cou11ty College· WC:CE55 wm .. AEACH. CORGAN VOLUME I RESEARCH VOLUME I RESEARCH Campus Access Vehicular and Pedestrian Circulation VEHICULAR CIRCULATION The location of the TCC Connect Campus within the West Fork Tower of the Trinity River Campus means that the same traffic and access patterns that apply to the Trinity River Campus are applicable. None of the proposed phases would negatively impact vehicular paths and/or traffic with the exception of the construction material drop offs and the staging of construction materials. PEDESTRIAN CIRCULATION The location of the TCC Connect Campus within the West Fork Tower of the Trinity River Campus means that the same traffic and access patterns that apply to the Trinity River Campus are applicable. However, the location of the campus within a single floor of a tower means that the pedestrian experience is the primary campus access. Current and potential students access the campus by navigating through the Trinity River Tower and then make their way down and across the Clear Fork Tower. I N T E R S T A T E 3 5 TX HWY 280 W 7TH ST . E BELKN A P ST. H O U S T O N S T T X H W Y 1 9 9 N M A I N S T . CAMPUS ACCESS FRAMEWORK Vehicular and Pedestrian Traffic 250 251 + ,~ T arranl Cou11ty College· WCCE55 wm•• AEACH. CORGAN VOLUME I RESEARCH VOLUME I RESEARCH Students utilizing collaboration for distance assignments. Student using a computer in a Library to complete assignments. Students in the cybersecurity program participating in an event sponsored by Cisco. Labor Market Analysis TCC Connect Occupational Programs Fastest Growing Occupations 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — Occupations Adding the Most Jobs 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #5: First-Line Supervisors of Office and Administrative Support Workers Highest Paying Occupations Dallas, North Central Texas, Tarrant WDAs — Occupations With Greatest Annual Openings 2018 – 2028 Dallas, North Central Texas, Tarrant WDAs — #4: First-Line Supervisors of Office and Administrative Support Workers FPC provided data related to job demand, need, and growth within the College’s service area and the Greater Dallas- Fort Worth-Arlington, Texas, MSA (Metropolitan Statistic Area). This study was cross- walked with programs the TCC Connect Campus offers and the available top 20 occupations were outlined. VOLUME I PLANNING VOLUME I PLANNING + Planning c 255 + • • • • • • ,_Q T orru111 Coull!)' C oll<'g e• ""' wccmwn_n....._ CORGAN VOLUME I PLANNING MASTER PLAN WORK SESSION Master plan work session at the Northwest Campus discussing impact of demographics on the campus. College Level Planning The college level Planning sub-section focuses on the impact of college level evaluative standards, primarily the 3G8P. The application of these goals and principles to all campuses helped establish priorities for each campus related to deficiencies with meeting these standards. The vision for the future of the College and the available resources to enact this vision guided project priorities as well. This established overall college level priorities and began the process to develop a schedule for when these deficiencies would need to be addressed. The master plan team considered a variety of different planning scenarios at both the campus and college level. The master plan team approached each potential planning scenario with the following understanding: — The master plan framework is flexible to change over time. — The master plan framework considers that there is not just one correct answer but recommends employing the best correct answer. During this process of evaluating planning scenarios, the master plan team engaged in multiple working review sessions with the College’s principle advisory panels. These work sessions were highly participatory and provided valuable feedback. The feedback included in-depth explanations of the principles that the college had set and feedback regarding critical principle deficiencies that the master plan would need to address. 256 257 + VOLUME I PLANNING VOLUME I PLANNING THREE GOALS, EIGHT PRINCIPLES Master Plan Planning Standards 3G8P Planning Concepts Master Plan Guidance The master plan team used the standards that the 3G8P set for evaluation of existing facilities and the minimum that proposed projects should achieve. The following describes the correlation between spaces that are utilized by the College on each campus and the 3G8P. The team uncovered that multiple principles can be applied to a single space, elevating the potential of a space. 8 Principles LEARNING COMMONS Learning commons are an integrated component with the college level active learning experience and foster greater student engagement by meeting student needs in a dynamic and flexible environment. Libraries are undergoing physical and programmatic changes and are less about books and more about supporting learning activities. Learning Commons Spaces: — Reduced Stacks: Substantial reduction in stacks but includes laptop check-out and collections accessibility. — Tutoring and Supplemental Instruction: General areas for collaboration between two or more people. — Learning Labs: Writing Center, Math Center, Science Center. — Student Engagement Spaces: Small glass rooms for study, conference rooms for group meetings, lounge areas for rejuvenation. — One Button Labs: Technology rich environment for video, video review and editing. — Maker Spaces: Equipped with small appliances, 3D printers, and layout space. — AI/VR Lab: Area to stand and work with AI/VR goggles and appliances. — Gaming Lab: Area to work with gaming software with space to gather and discuss and record interviews. INTEGRATED INSTRUCTIONAL LEARNING ENVIRONMENTS The college embraces a culture of teaching and learning as the foundation of its mission. Innovation in space, technology, and teaching practices serve as the core for student learning and success. As a result, the transformation of learning spaces beyond the traditional format accommodates experiential and active learning environments and better support the learning needs of students. Integrated Instructional Learning Environments Spaces: — Formal Learning Space Tech+ Classroom: The IILE educational specifications with new formal learning environments called Formal Learning Spaces Tech Classroom with addition of the Technology Plus components including cameras and additional Cleartouch screens. ˜°˛˝˙ˆˆ˛ˇ˘ˆˆˆˆˆˇ˝˙3 8 ˜°˛˛°˝˙ˆˇ˘˝˙ˆˇ˘ˆ˙˛˙ 8 ˜°˛˝˙˛˜ˆˇ˘ ˜°˛˝˙ˆ˜˜ˇ˘˙°˘˙ˇ˘˜˜°˛˜˝˙ˆˇ˘˘˝ˆ˙˝˘˙˙˛ ˜°˛˝˙˜ˆ°ˇ ˜°˛˝˙ˆˇ˛˝˘˛˘˝°˛ ˝˘˝ ˛˘˝°˛ ˝˝ˆ˜˝°˝ ˝˘˜°˙ˇ°˘ ˇ˛ ˛˜˜ ˇ˛˜° ˜˙  ˜°˛˝˙ˆˇ˛˝˘˜°˛ˆ˛˜°ˇ ˝ˇˆ°˜°˙˝° ˜ˆ°˝°˛ ˝ˇˆ°˜°˙ ° ˆˇ˝ ˝° ˜ˆ°˝°˛ ˇˇˆˇ˛˝ˆ ˇ°˘ˇ˜˛ 258 259 + ,~ T arranl Cou11ty College· WCCE55 wm•• AEACH. CORGAN VOLUME I PLANNING — Formal Learning Space: Highly used classroom that is accessible primarily to faculty trained in active and engaged learning pedagogy and technology. New architecture or renovation of existing classrooms. INTEGRATED STUDENT SUCCESS MODEL The college dedicates significant resources focused on student success including faculty and staff, spaces, equipment, and technology. Successful integration of resources is fundamental to the learning experience, so that the college is a welcoming environment for students that promotes learning. Integrated Student Success Model Spaces: — Wellness Centers: To include Health Services, the Campus Nurse, and Health Staff, as well as Counseling. Spaces include an open reception to each, counseling, and health services, focus rooms for privacy, exam rooms and meditation space. — Food Pantries: Spaces for storage of dry food, fresh produce, refrigerated items and frozen items. Location for checkout with separate discreet entry. — Orientation and First Year Experience: Large meeting space with technology to provide streaming video. — TRIO Space: Federal grant to provide special assistance to students. Environments include a meeting area, focus rooms as well as tutoring spaces. — Childcare Assistance Spaces: Meeting areas with access to lockers and kitchenette, small child play space within site and family centered restrooms nearby. — Co-Curricular Clubs and Organizations: A dedicated gathering space to socialize, meeting spaces of various sizes are both important to this concept. Meeting spaces could be classrooms not in use. — Student Employment: Spaces throughout the work environments for students to work, could be touch-down spaces or smaller temporary workstation areas. STUDENT EXPERIENCE A Student-Ready College provides an experience for students that is welcoming, simple to understand, provides a clear pathway, and breaks down barriers. Streamlined processes which are more student-centric ensure that students get through the door on their desired pathway more quickly. Student Experience Spaces: — Onboarding: Guided Pathways, meeting students elsewhere on campus such as a Welcome Center. Concierge Desk and entry welcome station. — Welcome Center: Includes a Concierge Desk, large open inviting space to house a learning stair for student rejuvenation, meetings with students and lyceum type meetings. — Advising: Large area for workstations, Focus rooms for private conversations, larger meeting/conference rooms. — First Time in College Students: Special needs include meeting spaces for families, campus touring noting spaces for interaction with other students to develop college quality of life experience. — Enrollment Services: Transaction areas to be more inviting, easily located, and consistent among campuses. Includes Registrar, Business Services and Financial Aid. — New Student Orientation: Individual space for large groups of students, smaller spaces for gathering and presenting. Includes presentation technology. Learning Stair to be used for New Student Orientations. “By committing to the institution’s 3 Goals and 8 Principles, TCC will function as One College, be Student Ready, and Serve the Community.” VOLUME I PLANNING HIGH SCHOOLS Building and maintaining strong P-20 partnerships is essential for the student pathways to success. The dual enrollment (Early College High Schools) and dual credit partnerships with local school districts support student transition to college. High School Spaces: — Free Standing Buildings: 10-14 classrooms for 25 students following the IILE Classroom Standards including two science labs, Cafetorium, learning commons space, and administrative spaces. Also, on campus, touch down spaces for High School students to meet, have meals and congregate throughout the day. SCHEDULING AND FACILITY UTILIZATION A student-centered schedule of classes is offered and supports student access and success. Scheduling and Facility Utilization Spaces: — Common Schedule: A common schedule was established to have standard start times and end times for student classes. — Schedule Design: Continual work to design a full pathway schedule for students in both credit degrees and certificates. — Facility Utilization: Utilization is an ongoing research approach to how we function in classrooms and meeting spaces. Ad Astra is the scheduling software tool used. We strive for 75% classroom capacity and a 38 hour utilization week per classroom. CAMPUS CHARACTER AND QUALITY A student-ready college provides a welcoming and easily navigated experience for students and uses spaces effectively to maximize the student experience. Campus Character and Quality Spaces: — Outdoor Learning Spaces: Classrooms following the IILE standards outside environments. Includes the standard technology. — Wayfinding and Signage: A college level project to redesign TCC wayfinding approach with new signage. — Fountains and Exterior Features: A college level approach to fountains, maintenance, and operations. — Green Spaces: Inviting outdoor areas for students to lounge, study or meet. — Amphitheaters: Outdoor assembly spaces for attracting various venues of entertainment and education. — Prairie Restoration Projects: Natural features of the land to use for teaching. — Monarch Butterfly Stations: To house plants appropriate for monarch butterflies. — Community Gardens: To be used as a teaching tool for students to learn about sustainable food creation. Includes composting and water collection systems. WORKSPACE ENVIRONMENTS Redesigned workspace environments will promote more collegiality, enhance spatial quality, provide flexibility and increased efficiency, and support a culture of collaboration. Workspace Environment Spaces: — Open concept Neighborhoods contain the following spaces: — Workstations — Focus Rooms — Conference Rooms — Social Zones and Rejuvenation Spaces — Resource Rooms — Ancillary Spaces 260 261 + VOLUME I PLANNING MASTER PLAN WORK SESSION Master plan work session at the Northeast Campus discussing impact of phasing on the campus. Campus Level Planning The campus level Planning sub-section focuses on the holistic consideration of planning alternatives. These alternatives are reviewed for the effect that each may have on campus development in the near-term and over the 20-year horizon of the master plan. The master plan team approached each potential planning scenario with the following understanding: — The master plan framework is flexible to change over time. — The master plan framework considers that there is not just one correct answer but recommends employing the best correct answer. During this process of evaluating planning scenarios, the master plan team engaged in multiple working review sessions with both the College’s Real Estate and Facilities team as well as stakeholders at each of the campuses. These work sessions were highly participatory and provided valuable feedback regarding goals of each campus. + (' c:-::> ' -, \ '\ \ \ \ CORGAN / '-~-- JOE B . R U S H I N G R O A D C . A . R O B E R S O N B O U L E V A R D CA M P U S D R I V E VOLUME I PLANNING VOLUME I PLANNING SECH SBSW SBSA SHPE SBSP SNUR SELT SAUT STEC SACR SHSC SELE SETC SMTH SETC SSCI SBUS SCLC SACA SACB SACCSERS SLIB SACD SMTC SACT SPAC SFOB SFOC SFOA SBKS SSTU SMUS SART SFOD SFOE SFOF 0' 100' 200' 400' North 262 263 South Campus Planning Background GOALS — Define the campuses front entry and where to start — for potential students, community members, and visitors. ISSUES — Onboarding process is decentralized and can be confusing. — Entry, circulation, and parking do not reinforce campus entry. OPPORTUNITIES — Space to develop new facilities while existing buildings are utilized by current programs. — Campus has a strong existing framework to guide potential future expansion and growth. — Establish a consolidated “One-Stop Shop” for students — Onboarding, student services, Welcome Center. — Many buildings are older, have poor performing systems, and are undersized. — Visible presence available for high profile and engaging programs. — Plan future development to collaborate with workforce partners. — Faculty office building complex limits direct access of faculty to students. — Ample parking to support re-distributed programming. — Preserve the small, liberal arts feel of the campus framework. — Outdated campus and building infrastructure limit usage and community engagement opportunities. — Plan for growth in enrollment in successful and trending workforce programs. SREC CAMPUS SITE PLAN Existing Conditions +,~ Tarronl C wccm wm.:ullt)' College• AEACH. CORGAN -;• ' -' (-' ,--J ' I ,-, (-, ,-,I I~ I HAR W O O D R O A D VOLUME I PLANNING GRAPEVINE HIGHWAY NBSA NDPP NMPC NDPW NBSA NDSC NDPA NSCW NTAB NHSC NSCE NHPE NACB NFAC NIMC NLIB NBSS NFAB NCAB NADM NSTU CAMPUS SITE PLAN Existing Conditions 0' 100' 200' 400' North VOLUME I PLANNING Northeast Campus Planning Background GOALS — Define the campuses front entry and where to start — for potential students, community members, and visitors. — Establish a consolidated “One-Stop Shop” for students — Onboarding, student services, Welcome Center. — Provide state-of-the-art space for growing and successful programs. — Think ahead about opportunities with local school districts. — Strengthen the existing beautiful campus core and quads. — Create new athletic spaces and improve existing to prepare for future growth. ISSUES — Older science buildings are nearing end of services life and do not meet the standards that the College has set. — Centralized faculty office building limits direct access of faculty to students. — Onboarding process is decentralized and can be confusing. — Fine arts spaces are undersized and is due for upgrades in both technology and in space provided for performing arts. — Entry, circulation, and parking are challenging to access the Student Union for potential students. OPPORTUNITIES — Improve campus framework and views by demolishing buildings in poor conditions. — Opportunity to create a grand front entry at the Student Union and increase visibility and access. — Space to construct new science building to the North of existing science buildings. — Construction of new science building provides possible swing space or additional classroom space. — Increase parking access for potential students. — Existing community partnerships present opportunities to leverage. 264 265 + Tnrrant County Co llegec sucass wn 1-1N REACH. CORGAN DRIVE COLLEGE WFSK W F S C W F S S WACB VOLUME I PLANNING VOLUME I PLANNING WFMP WCJD WCTT WCJC WFSJ WFSIWCJR WPFR WFSF WFSH WFSG WFSB WFSD WFSA WFSE WATB Northwest Campus Planning Background WFSV GOALS ISSUES OPPORTUNITIES WMBD WMBC — Plan development to respond to community and employment needs. Public Safety Training Center facilities and infrastructure need updates to match current standards of the professions that they seek to serve. — Removal of facilities nearing end-of-life provides space for landmark Public Safety Training Center program expansion. — WMBB WMBA — Provide state-of-the-art space for growing and successful programs. WHPE Horticulture program left without proper home after the ongoing bond projects. — Re-organization and expansion of Public Safety Training Center programs can established a more unified identity on the campus and for the community. — BUILDING 1 WGHB — Capitalize on access to Marine Creek Lake and surrounding land. Portables and re-purposed buildings present a poor impression to the groups and programs using those facilities. — WBSA WHPB MARINE CREEK LAKE — Create a unified presence for the Public Safety Training Center programs and facilities. — Space to develop new facilities while existing buildings are utilized by current programs. — Capitalize on existing facilities that are unique to the campus. Ongoing bond projects provide a unified central campus, but do not respond to campus outskirts. — — BUILDING 3 Much of campus core addressed by ongoing bond projects establishes a clear campus framework. BUILDING 2 — Plan future development to collaborate with workforce partners. Ongoing and proposed construction efforts lack proper facility support. — BUILDING 4 CAMPUS SITE PLAN Existing Conditions 0' 100' 200' 400' North 266 267 +Tarranl , WCCE55 wm .. A t , College· CORGAN \,"~--_#..,/ H E R I T A G E P A R K W A Y HORIZ O N DRIVE VOLUME I PLANNING VOLUME I PLANNING Alliance West Site Planning Background GOALS — Create a strong presence at the front that this is a community college site. — Capitalize on access to Alliance Airport and the unique programs that students are able to participate in. — Indicate that the site is student focused and provide resources for the student population. SITE FLOOR PLAN Existing Conditions 0' 100' 200' 400' North ISSUES — Students lack dedicated study and breakout spaces for both individuals and small groups. — Facility lacks food service option despite students attending courses all-day. — Interior hangar space is at capacity and lacks acoustical attenuation appropriate for the courses using the space. OPPORTUNITIES — Visible presence for the College to workforce and community partners. — Space is available for Pilot Ramp Extension. — Former corporate identity of the building provides students with an environment that can parallel their potential future professional environment. — Programs are successful and offer unique opportunities for potential students in the College’s service area. 268 269 + { /' .. , '-) 1.--.',, ) ------- \ ! ,. / r i I I l--,~ -- --.._ . .,,./ / \. ------ ffi I I \__ Tarra nt County Coll .. wcms wm.,, '""" egc SOUT H E A S T P A R K W A Y EMOD VOLUME I PLANNING VOLUME I PLANNING ECHS CAMPUS SITE PLAN Existing Conditions Southeast Campus Planning Background GOALS — Provide state-of-the-art space for programs not addressed by existing bond projects. — Continue to prioritize a presence and relationship with local school districts. — Capitalize on the existing standards for quality and character of the extensive campus grounds. — Provide a high quality experience for all students in all programs. ISSUES — Existing Theater in need of increased support space. — Portable and temporary buildings are being used to support important outreach and support programs. — Limited space to grow programs within the existing main building. — Expansion of programs within the main building limit the growth of other programs. — Students are limited in the amount of study/sticky space dedicated to them outside of academic spaces. OPPORTUNITIES — Space to develop new facilities while existing buildings are utilized by current programs. — Much of campus addressed by ongoing bond projects establishes a clear deficiency list. — Campus framework provides a clear pathway for future development. ESSE ESEE ESEB ESEC ESED ESCT EBSP ESAC EART EBSE EBSA EBSB NE W YO R K AV E N U E EBSC 0' 100' 200' 400' North 270 271 + r--- I I L_ ------------~' I \ 7 ,~ T arranl Cou11ty College· WCCE55 wm•• AEACH. CORGAN FO R K (T R W F ) WE S T FOR K ) F CLE A R CRT ( TRPGPARKING TRIN I T Y ) RTR T ( EAST F O R K (TRE F ) TRTRELBOW VOLUME I PLANNING VOLUME I PLANNING TRINITY RIVER STREET MI L L S ST R E E T PEACH STREET BLUFF STREET HE N D E R S O N ST R E E T (H W Y 19 9 ) TA Y L O R ST R E E T IDEA STORE (TRIS) BELKNAP STREET BELKNAP STREET 0' 100' 200' 400' North 272 273 CAMPUS SITE PLAN Existing Conditions Trinity River Campus Planning Background GOALS — Establish a consolidated “One-Stop Shop” for students — Onboarding, student services, and a Welcome Center. — Define the campuses front entry and where to start — for potential students, community members, and visitors. — Provide state-of-the-art space for growing and successful Healthcare Professions programs. — Strengthen the existing campus plazas. — Create new exterior athletic spaces for future growth. — Capitalize on existing facilities that are unique to the campus. ISSUES — Existing Health Professions program space is at capacity and is not appropriately equipped or sized for those programs. — Onboarding process has poor visibility and access and can be confusing. — Entry, circulation, and parking are challenging to articulate the Onboarding process for potential students. — Retrofit of former corporate campus has caused programs to be infilled sporadically. — Previous usage of campus for a corporate entity is at odds with usage by a community college and students. OPPORTUNITIES — Construction of new Health Professions Tower consolidates programming and frees space at Trinity River Campus East for future development. — Visible presence for the College to workforce and community partners. — Programs are successful and offer unique opportunities for potential students in the College’s service area. — Space to develop new Onboarding facility and emphasize the importance of student experience to the campus. + f-- 1 ' --', ·:_-_-- --....:::....-' ---------- -, ',',I ' :ii~--'"'l I ,--~F-'r1 ,-'---if) I ,,d ''10! I.--, ~n -~ ... J~ ,, I ··I ,, 11 ,, I I I ','1, I ,:,:~------' -.J•--··1 11 11 11 11 11 ,~ T arran l Cou11ty College· WCCE55 wm•• AEACH. CORGAN b1·· 1 . l J I I J I I VOLUME I PLANNING VOLUME I PLANNING TRHA TRHN TRHN TRHP BELKNAP STREET TRHT TRHW CA L H O U N ST R E E T 0' 50' 100' 200' North 274 275 CAMPUS SITE PLAN Existing Conditions Trinity River Campus East Planning Background GOALS — Establish the best possible use of the facility and campus. — Define the campuses front entry and where to start — for potential students, community members, and visitors. — Provide state-of-the-art space for growing and successful Healthcare Professions programs. — Strengthen existing campus urban connections. — Capitalize on existing location of facility. ISSUES — Existing Health Professions program space is at capacity and is not appropriately equipped or sized for those programs. — Entry, circulation, and parking are challenging to accommodate the students using the campus. — Retrofit of campus planned for administrative usage has caused Health Profession programs to lack space designed appropriately to their needs. OPPORTUNITIES — Construction of new Health Professions Tower consolidates programming and frees space at Trinity River Campus East for future development. — Visible presence for the College to workforce and community partners. CO M M E R C E ST R E E T — Programs are successful and offer unique opportunities for potential students in the College’s service area. — Existing community partnerships present opportunities to leverage. + L__ I I r j I ' ' L__ E6 0 0 / ···,\ f-------,,,..< \ . '-~--_#" ,~ T arranl Cou11ty College· WCCE55 wm•• AEACH. CORGAN 2060B-X MECH VOLUME I PLANNING VOLUME I PLANNING 24 0 0 A - X CO R R I D O R 2907A OPEN OFFICE 2801A OPEN OFFICE 2703-C 2903A CONFERENCE OFFICE 2905A 2906A 2802A 2803A 2804A 2805A STORAGE 2902A-S 2904A FOCUS FOCUS FOCUS FOCUS FOCUS FOCUS FOCUS 2900A-X 2800A-X CORRIDOR CORRIDOR 2503-R MEN'S 2561A-X 2801-C CONFERENCE 2460A-X 2860A-X 2702A 2901A IDF IDF ELECTRICAL 2602A-S OFFICE OFFICE CAMPUS FLOOR PLAN Existing Conditions STORAGE 2800B-X 2700A-X LOUNGE MECHANICAL 2360A-X CORRIDOR 2207 CORRIDOR 2500A-X 2206-C TRAINING TCC Connect Planning Background GOALS — Prepare for growth in enrollment and additional staff. — Provide state-of-the-art space for faculty and students to be able to engage in and facilitate the functions of providing an online learning experience. ISSUES — Program growth is limited by available space in the other towers at the Trinity River Campus. — Technology is insufficient to provide the standard of education that the College aspires to provide to its student body. OPPORTUNITIES — Re-organization and consolidation of other programs in the Trinity River Campus towers can provide room for program expansion. 2600A-X CONFERENCE CORRIDOR 2601-C 2701A 2210A VIDEO PRODUCTION 2560A-X CONFERENCE OFFICE ELECTRICAL 2300A-X 2502-R CORRIDOR WOMEN'S 2200A-X 2504B-X 1174-X 2301A-X CORRIDOR ELEV. 4 ELEV. LOBBY 2501A-S JANITORIAL2103-C STORAGE — The trend towards online learning and students pursuing academics through a distanced option strengthens the need for a robust online option. CONFERENCE 2101-K BREAK RM. 2204A 2208A 2209A FOCUS FOCUS FOCUS 2211A 2212A 1171-X 1172-X 1173-X FOCUS FOCUS ELEV. 1 ELEV. 2 ELEV. 3 2202A 2203A FOCUS2100C-X FOCUS CORRIDOR 2102-C 2100B-X CONFERENCE LOBBY 2201A OPEN OFFICE 2100A-X STAIR B RECEPTION1181-X 0' 10' 20' 40' North 276 277 +VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Prioritization c 281 + l j 8 ,,,,,... p--- • e - j 100 · "' .c OO 400 " VOLUME I PRIORITIZATION > ITERATIVE CAMPUS PHASING The master plan team explored different iterations for each campus and coordinated the phasing across TCC. College Level Prioritization The college level Prioritization sub-section embraces that master plans are about defining the time and cost that is required to achieve certain goals established by the College or uncovered by the master plan team. The master plan ensures that the development of the planning scenarios are highly-integrated and coordinated with the prioritization at both the campus and college level. The master plan considers the overlapping of a conceptual phasing plan onto each planning scenario. This phasing sequencing results in the establishment of phases for each campus and a deepened understanding of the depth of time that the full phasing that the master plan covers. The preliminary costs that the master plan applies to each planning scenario provide further evaluative depth. The cost models consider escalation factors to provide a relationship between cost and time. The costs for each phase also provide an understanding of what can be included in existing funding sources and what phased projects will need to be planned for the future. These recommended priority projects were cross-referenced with the projects that the College currently has projected to complete from 2023 – 2027. These projects were checked to cross-reference with master plan projects for possible inclusion. The master plan also reviewed potential funding for each year and proposed at what point the priority projects would occur as well as additional stand-alone infrastructure projects. 282 283 + ,~ T arranl Cou11ty College· WCCE55 wm•• AEACH. CORGAN VOLUME I PRIORITIZATION Prioritization Rationales Master Plan Phasing Logic Campus visits, work sessions, and research culminated in sequenced phasing for identified projects at each campus. This sequenced phasing took into account not just the information and research uncovered, but also a set of logical rationales based on the experience of the master plan team and the needs of the College. These principles provided guidance to the sequencing of phases at each campus, but the master plan team also understood that there would be situations where the guidance may need to adjust. The primary parameters that the master plan team utilized in its sequencing of projects for each campus include, but are not limited to the following. PROGRAM RE-LOCATION The master plan has sequenced projects so that enabling projects are constructed, then permanent homes for programs are created. The College and each campus made it clear that the churn that develops from moving programs multiple times can create a drop in morale for the students and faculty. Additionally, moving programs multiple times causes program disruption and can hurt the academic performance of the program and provides a less than stellar experience for students. SWING SPACE Based on the priorities that were discussed with TCC Real Estate and Facilities, TCC staff, faculty, and other building users, the master plan had to consider the need to create “empty chairs” or “swing space” on each campus to allow for the remaining master plan phasing to occur. The usage of either enabling projects or existing facilities to act as swing space to temporarily house programs was crucial to determining the initial projects at each campus and what could be completed. TEMPORARY SOLUTIONS While a popular option, the master plan team strongly advises against using portables to provide swing space for any program during the master plan phasing. The master plan team understands that while these may be considered as a temporary, less costly option, they will more than likely become permanent structures on the campus and that the financial impact of temporary options is not as light as presumed. VOLUME I PRIORITIZATION ENABLING PROJECTS The initial phase sequence of the master plan at each campus is built around establishing enabling projects. These are projects at each campus that work to provide swing space or new permanent homes for existing programs. This allows future development at each campus to proceed without impediments such as overlapping programming space or facilities that are not appropriate to the programming that is utilizing them. PRUDENT RENOVATIONS The master plan team understands that the most valuable asset that the College has are the existing buildings and the demolition of existing buildings is not considered lightly. However, once cost to address existing systems crosses a certain threshold, it is more prudent to demolish the building and build new. RENOVATION SCOPE If a building is being renovated, then it will address all deficiencies that have been identified by the facility condition assessment that Jacobs performed as well as any deficiencies that occur between the completion of the assessment and the time of renovation. This means that the entire building will be fully gutted and there will be a full renovation of all systems and finishes. The choice of renovation to this extent is to resolve the past issue of systems being addressed individually, instead of packaging projects together to save money and to have overlap in projects. PROJECT PACKAGING The master plan project sequencing works to minimize disruption at both the building and campus level. Projects are packaged together in the same phase if possible for increased efficiency. This was reviewed by members of the College’s Real Estate and Facilities staff and Jacobs’ team. PROJECT SEQUENCING The master plan team aligned with the College’s team to discuss the importance of considering construction logic for each phase and its impact on both the existing campus and future phases. Construction logic enabled the master plan team to identify dependencies between projects and break them into separate, sequence phases. While some master plan phases can be completed in parallel, the sequencing is important as certain projects are dependent on the completion of others prior to the phase beginning. Where possible, the master plan worked to minimize this to allow for the master plan framework to be flexible as the College makes decisions in the future. This phasing for each campus was then considered from a college level as the constraints of available funding and projected schedules were integrated. The result of this synthesis of projects, funding, and potential timelines was a list of priority projects that could be accomplished within the constraints of the current bond funding and additional yearly project funding. Based on these principles, the master plan proposed a list of implementable priority projects and a delivery schedule to achieve those. The remaining projects are planned to occur over the course of the 20-year planning horizon. The priority projects have been chosen based on considering factors over the scope of the college. Additionally, with the significant new construction and renovation projects that are ongoing at the Northwest and Southeast Campuses, “Mission Critical” or similar significant deficiencies that were identified at other campuses played a role in the decision to prioritize certain projects. However, these projects were not considered in a vacuum per campus. Based on these principles, the master plan proposed a list of implementable priority projects and a delivery schedule to achieve those. 284 285 + ,~ T arranl Cou11ty College· WCCE55 wm•• AEACH. CORGAN VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Master Plan Recommendation Northeast Campus The master plan team is recommending the inclusion of two projects from the Northeast Campus to be funded through remaining 2019 Bond funding. These two projects have been selected because they are dependent on each other and work in tandem. Additionally, these would be impactful bond projects and would set the campus up for the ability for more intensive projects to be completed as part of a future bond. Focus on these projects and their prioritization in the master plan sequencing is the cumulation of several primary factors: — The Science Labs are original to the campus, circa 1976. — The programs are performing highly and the faculty that use them are nationally recognized. — The state of the facilities is sub-par and are an urgent issue to resolve to improve campus perception and student service. — The projects would improve campus morale and align the facilities for students with the goal to show students that they are deserving of top-notch facilities. — The Dental Hygiene program that is housed in one of the buildings is a top twenty program according to the labor study and is constrained by current space and equipment. — Visible symbol of College investment in campus and programs. Existing aging facilities. Existing aging facilities. Existing aging facilities. 286 287 + VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION  Northeast Campus Phase 1 NEW SCIENCE BUILDING: 60,000 SF — General Programming: 9,786 SF — Entry Lobby — Lecture Hall — Multidisciplinary Area — Collaboration Space — Write-Up Meeting Space — Faculty Workspace: 5,300 SF — Include new faculty neighborhood — Classrooms and labs: 28,100 SF — Core/MEP: 4,986 SF SCHEDULE Phase 1 TOTAL COST $79,000,000     Northeast Campus Phase 2 RENOVATE SCIENCE EAST BUILDING: 40,803 SF — Swing Space, Offices, General Purpose Classrooms RENOVATE SCIENCE WEST BUILDING: 30,828 SF — Swing Space, Offices, General Purpose Classrooms RENOVATE HEALTH SCIENCE BUILDING: 29,394 SF — Expand Dental Hygiene program to entire building — Establish Dental Hygiene faculty neighborhood — Recent renovations to remain as-is SCHEDULE Phase 2 TOTAL COST $71,500,000 288 289 + VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Master Plan Recommendation South Campus The master plan team is recommending the inclusion of one projects from the South Campus to be funded through remaining 2019 bond funding. This project was selected because campus faculty and staff were very vocal about the need to prioritize this project. Additionally, the subsequent projects would be able to be funded through Fund 40 after the project’s completion. Additionally, this would be an impactful bond project and would set the campus up for the ability for more intensive projects to be completed as part of a future bond. Focus on these projects and their prioritization in the master plan sequencing is the cumulation of several primary factors: — Campus faculty and staff were consistently vocal about the need to prioritize students and the Onboarding process. — The project would provide a clear campus front door for enrollment functions to potential and current students, community members, and visitors. — The project would establish a consolidated “One-Stop Shop” for students with easy access to Onboarding, Student Services, and a Welcome Center. — The state of the facilities is sub-par and are an urgent issue to resolve to improve campus perception and student service. Interior of Enrollment Services Building. Enrollment Services Building entry. South Campus Phase 1 CONSTRUCT NEW ONBOARDING BUILDING: 92,000 SF — Student Services: 39,035 SF — Onboarding: 20,745 SF — Support Services: 7,300 SF — Core/MEP: 7,300 SF IMPROVE CAMPUS FRONT ENTRY: 97,000 SF — Focus on the area of campus surrounding the new Onboarding Building — Project to be the first part of a two phase site improvement at the campus front entry SCHEDULE Phase 1 TOTAL COST $79,000,000   290 291 + -,i~ T arranl Cou11ty College· WC:CE55 wm .. AEACH. CORGAN VOLUME I PRIORITIZATION NORTHEAST CAMPUS MASTER PLAN The master plan for the Northeast Campus proposes a new science building and explores its connection to the existing campus framework. Campus Level Prioritization The campus level Prioritization sub-section focuses on defining the time and cost that is required to achieve certain goals established by the College or uncovered by the master plan team. The master plan ensures that the development of the planning scenarios are highly-integrated and coordinated with the prioritization at both the campus and college level. These phases are sequenced to resolve critical issues in the near-term and to envision the future of each campus over the span of the 20-year horizon. The primary parameters that inform the phasing in addition to the prioritization are: — Sequencing of new construction versus remodeling. — Minimizing disruption of campus operations and safety. The preliminary costs that the master plan applies to each planning scenario provide further evaluative depth. The cost models consider escalation factors to provide a relationship between cost and time. The costs for each phase also provide an understanding of what can be included in existing funding sources and what phased projects will need to be planned for the future. These priority projects were cross- referenced with the projects that the College currently has projected to complete from 2023 – 2027. These projects were cross-referenced with master plan projects for possible inclusion. The master plan also reviewed funding for each year and proposed when priority projects would occur as well as stand-alone infrastructure projects. 292 293 + . ., SCLC ... SERS : . : " : SBUS r::}? ACA : CJ~ . -: · .. . . . . ..... .., · SACC SACO· J " d ..... ,. s,,c I ,,,,.., .,,~ ve" MUS I ,~ T arranl C ou11ty College· WCCE55 wm•• AEACH. CORGAN '-~--_#..,/ VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION SOUTH CAMPUS SITE PLAN Master Plan Landscape Plan 0' 100' 200' 400' South Campus KEY CAMPUS STATISTICS KEY MASTER PLAN STATISTICS Year Constructed: 1967 Phases: 18 Campus Size: 145.40 acres in South Fort Worth New Construction: 227,000 SF Building Inventory: 36 Buildings, 687,601 SF New Additions: 0 SF Campus President: Dr. Lufkin Renovation: 653,111 SF Student Enrollment: 7,475 students Sitework: 287,000 SF Signature Programs: Potential Total Cost: $731,262,570.43 — Architecture Technology, Computer-Aided Drafting, Construction Management — Automotive — Electronics Technology — Gaming — Heating, Air Conditioning, and Refrigeration — Teacher Education — Welding North + (' c:-::> ' -, \ '\ \ \ \ CORGAN / '-~-- JOE B . R U S H I N G R O A D C . A . R O B E R S O N B O U L E V A R D CA M P U S D R I V E VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION SECH SBSW SBSA SHPE SBSP SNUR SELT SAUT STEC SACR SHSC SELE SETC SMTH SETC SSCI SBUS SCLC SACA SACB SACCSERS SLIB SACD SMTC SACT SPAC SFOB SFOA SFOD SFOF SFOC SBKS SFOE SSTU SMUS SART SREC 0' 100' 200' 400' North CAMPUS SITE PLAN Existing Conditions South Campus Prioritization Background VISION The master plan programming for the future of the South Campus should include the construction of new facilities aimed at meeting the current and future needs of technical programs, general instruction, and the creation of an Onboarding Building consolidating student enrollment and support services. While the overall square footage of the existing campus buildings is sufficient in quantity to support current enrollment, the size, configuration, and functionality of a portion of the space does not. Changing pedagogy, section size, and program needs has led to the need to evaluate some existing buildings in terms of their ability to be renovated and support changing needs. This evaluation has identified some campus buildings which may be better served by demolition and replacement rather than renovation. The master plan will further enhance the existing cohesiveness on campus by creating and enhancing pedestrian paths, outdoor spaces, and connections between the existing buildings and any new construction. DECISION DRIVERS — Onboarding process is decentralized and can be confusing. — Entry, circulation, and parking do not reinforce campus entry. — Many buildings are older, have poor performing systems, and are undersized. — Faculty Office Building complex limits direct access of faculty to students. — Outdated campus and building infrastructure limit usage and community engagement opportunities. CORE ELEMENTS — Space to develop new facilities while existing buildings are utilized by current programs. — Campus has a strong existing framework to guide potential future expansion and growth. — Visible presence available for high profile and engaging programs. — Ample parking to support re-distributed programming. 294 295 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 1: New Onboarding Building and Campus Entry New Onboarding Building: 92,000 SF — Student Services: 39,035 SF — Onboarding: 20,745 SF — Financial Aid — Business Services — Registrar — Advising — Support Services: 7,300 SF — Core/MEP: 7,300 SF Improve Campus Front Entry: 97,000 SF — Focus on the area of campus surrounding the new Onboarding Building. — Project to be the first part of multi-phased site improvement at the campus front entry focused on increasing definition of main entry location. 1 1 PHASING SITE PLAN Phase 1 0' 100' 200' 400' North Site — The utility conflicts that may occur are a fiber optic line, a water line, and an irrigation line. As far as utility connections to the proposed building, the most challenging will be sanitary sewer and storm drainage. — There is a proposed parking lot for the proposed Onboarding Building. The parking ingress and egress locations should have enough distance from the main drive to the West that connects the college campus to Campus Drive to prevent congestion and allow safe vehicular movements in and out of the proposed parking lot. — The space plan North of the new Onboarding building is an opportunity for a quad, welcome plaza, or similar space to catch the attention of visitors and welcome them into campus. — Existing trees should be preserved in the development of a new campus entry. — Coordination required to protect existing service conduit feed to ensure that there is not an interruption in service. Building — It is anticipated that the existing plant will need to be expanded for this phase or a new, central, stand-alone plant will be required for this phase. Replacement of systems is outlined in Volume II. — If a new plant is considered, campus staff desire it to be located on the West side of campus to serve existing buildings and proposed new construction. — See Volume II for Structural New Construction Narrative. — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 296 297 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 2: Improve Campus Entry and Renovate Enrollment Services Building 1 1 2 2 2 2 Renovate Enrollment Services Building: 9,442 SF — Student Activities — Student Resources Improve Campus Front Entry: 190,000 SF — Focus on the area of campus surrounding the existing Enrollment Services Building and Administration, Testing, Counseling Building. — Project to be the second part of multi-phased site improvement at the campus front entry focused on increasing definition of main entry location. Demolish Administration, Testing, Counseling Building: 12,280 SF — Admissions, Counseling, and Testing program to be distributed to new Onboarding Building prior to demolition. Demolish Testing Portable: 2,070 SF — Testing classrooms to be distributed to new Onboarding Building prior to demolition. PHASING SITE PLAN Phase 2 0' 100' 200' 400' North Site — When demolishing the existing Administration, Counseling, and Testing Building (SACT) as well as the Testing Portable (SMTC), there are several water lines, sanitary sewer lines, storm drain lines, and underground electric lines that connect to both structures. — Also, some of these lines connect from these two buildings to the nearby Library (SLIB). Given this, the lines will need to be determined if they are only for the use of this facility or if used by others. Some of the utilities then will need to remain in service after the buildings have been removed. — Enrollment Services Building (SERS) to undergo landscape and paving updates at Library (SLIB). Incorporate a plaza with shade, site furniture, and enhanced planting. — New campus service feed to be coordinated and routed to avoid areas of new construction and demolition. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT IDF Cooling and UPS Installation — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 298 299 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 3: New Automotive Building New Automotive Building: 135,000 SF — Lobby and student areas: 3,000 SF — Classrooms/labs: 80,800 SF — High-Bay Diesel — High-Bay Automotive 3 — High-Bay Electric Vehicles — Faculty workspaces: 7,380 SF — Support: 8,500 SF 2 1 2 1 PHASING SITE PLAN Phase 3 0' 100' 200' 400' North Site — Within the proposed building and pavement footprints there are only a gas line and storm drain line that could be impacted. — The proposed parking entrance/exit on the East side of the proposed building should line up with the existing parking lot entrance/exit that lies across the drive. — The construction of a new Automotive Building presents an opportunity for including landscape amenities in the design plan. Such amenities could include a gravel maintenance band surrounding the building structure, areas for planting, creating a welcoming building entry environment through strategic lighting, landscape, and hardscape, and using landscape elements to connect the building visually and functionally to the broader campus network. — If space permits, outdoor areas for gathering/study could exist as part of the building surrounds. Coleman and Associates recommends including building screening, especially in/around automotive garage areas, in the design plan. Building — It is anticipated that the existing campus network has capacity to connect this building to existing infrastructure. Replacement of systems is outlined in Volume II. — Coordinate proposed telecomm. manhole and four 4" conduits to be stubbed out for future campus expansion and connectivity. — Extend existing utility lines to building. — See Volume II for Structural New Construction Narrative. — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 300 301 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 4: Renovate Automotive Building and Demolish Faculty Office Cluster Renovate Automotive Building: 34,573 SF — Swing space — Offices — General-purpose classrooms 3 Demolish Faculty Office Cluster: 20,200 SF — Faculty to be distributed to renovated faculty neighborhoods prior to demolition. 4 2 1 2 1 4 PHASING SITE PLAN Phase 4 0' 100' 200' 400' North Site — When demolishing the existing building cluster there are several water lines, sanitary sewer lines, storm drain lines, and underground electric lines that connect to the building cluster. — Also, some of these lines connect from this group of buildings to the nearby Bookstore (SBKS). Given this, the lines will need to be determined if they are only for the use of this facility or if used by others. Some of the utilities then will need to remain in service after the Faculty Office Building Cluster (SFOA – SFOF) has been removed. — Landscape design for the renovated Automotive Building (SAUT) should include removing the existing fence/wall around the building and/or parking areas, or simply making the visual connection between the two spaces more transparent. — Outdoor gathering/break spaces for faculty/staff should be included, with vegetative screening employed to buffer outdoor amenities from back-of-house areas. — Campus mall update to begin with phase 4. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT IDF Cooling and UPS Installation — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 302 303 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 5: Renovate Learning Commons Renovate Library: 48,646 SF — Renovate Library to function as Learning Commons. — Existing program to remain. 3 4 2 5 1 2 1 4 PHASING SITE PLAN Phase 5 0' 100' 200' 400' North Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — The renovation of the Library (SLIB) creates an opportunity to increase outdoor study space on campus. Outdoor improvements in this area should include benches and accessible seating nooks defined by 5’ landscape buffers and sheltered by a combination of shade and ornamental trees. — Additional amenities should include trash/recycling receptacles, bike parking and cart parking. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT IDF Cooling and UPS Installation — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 304 305 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 6: Renovate Performing Arts Center Renovate Performing Arts Center: 21,520 SF — Existing program to remain. 3 4 2 5 1 2 6 1 4 PHASING SITE PLAN Phase 6 0' 100' 200' 400' North Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Performing Arts Center (SPAC) renovation plans should include a retaining wall around the building as well as landscape enhancements (vegetation/shrub planting, ground cover, and ornamental trees where appropriate, quantities and species to be determined) and furniture replacement to the plan East of the building. — A student outdoor gathering space, on the plan West of the building, should include a shade structure with overhead fans, benches, and outdoor lighting. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT IDF Cooling and UPS Installation — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT VB Theatre Lighting and Sound Upgrades — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments — SO SPAC Roof Restoration 306 307 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 7: Renovate Fine and Performing Arts Buildings Renovate Art Building: 7,117 SF — Existing program to remain. Renovate Music Classrooms Building: 12,776 SF — Existing program to remain. 3 4 Renovate Recital Hall: 9,442 SF — Existing program to remain. 2 5 1 2 6 1 7 7 4 7 PHASING SITE PLAN Phase 7 0' 100' 200' 400' North Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — The plaza in the area between the Fine Arts Buildings (SART, SMUS, SREC) should be improved to include landscape amenities such as renovated concrete pathways punctuated by paver bands, upgraded planting, and landscape buffers, ground- mounted furniture, bike parking, and cart parking. — Landscape improvements and site furniture updates in this area should relate to the campus mall improvements described in phase 8. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT IDF Cooling and UPS Installation — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 308 309 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 8: Renovate Student Union and Bookstore Renovate Student Union: 44,780 SF — Existing program to remain. Renovate Bookstore: 10,719 SF — Existing program to remain. 3 4 2 5 1 2 6 1 8 8 7 7 4 7 PHASING SITE PLAN Phase 8 0' 100' 200' 400' North Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — The core campus mall should be strengthened and any open spaces transformed into lawn spaces highlighted by trees planted at intervals that reinforce the linear aspect of the area. — The mall should connect the North and South ends of campus and intersect with existing East /West pathways. The space should welcome visitors to the heart of campus and be an obvious focal point that visually relates to other key spaces. — Pedestrian thoroughfares through/alongside the mall should be paved with concrete and punctuated by paver bands. Planting should include a mix of turf, groundcover, shrubs, and shade and ornamental trees. — Accessible seating nooks defined by 5’ landscape buffers and sheltered by ornamental trees should be incorporated at strategic locations along the mall. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments — SO SBKS Roof Restoration 310 311 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 9: Renovate Electronics and Mathematics Buildings Renovate Electronics Building: 13,345 SF — Existing program to remain. Renovate Mathematics Building: 10,739 SF — Existing program to remain. 3 4 9 9 2 5 1 2 6 1 8 8 7 7 4 7 PHASING SITE PLAN Phase 9 0' 100' 200' 400' North Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Relate landscape improvements to master plan phase 4 campus mall improvements. — Opportunity for student space (gathering/studying). Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments — SO SELE Roof Restoration 312 313 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 10: Renovate Math Emporium and Campus Administration Buildings 3 4 10 10 9 9 Renovate Math Emporium Building: 22,560 SF — Faculty Neighborhood — General-purpose classrooms Renovate Campus Administration Building: 6,519 SF — Faculty Neighborhood 2 5 1 2 6 1 8 8 7 7 4 7 PHASING SITE PLAN Phase 10 0' 100' 200' 400' North Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Address pinch point in between buildings for safety (lighting, visual access, wide sidewalks). — Design landscape and site furniture improvements between Math Emporium (SNUR) and Campus Administration Building (SHSC). Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments — SO SNUR Roof Restoration 314 315 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION 11 3 10 4 10 9 9 11 11 2 5 11 11 1 2 6 1 8 8 7 7 4 7 PHASING SITE PLAN Phase 11 0' 100' 200' 400' North VOLUME I PRIORITIZATION Phase 11: Review Academic Classroom and Physical Education Buildings Review Academic Classroom Building Cluster — Determine efficacy of renovation or demolition and replacement. — Option 1: Renovate Academic Building Cluster. — Gross square footage renovated: 40,960 SF — Option 2: Demolish Academic Building Cluster. Construct new, larger Academic Classroom Building. — Gross square footage proposed to be built: 80,000 SF Renovate Health and Physical Education Building: 64,875 SF — Existing program to remain. Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — If renovation is preferred, improve landscape areas and site furniture between Academic Classroom Building Cluster (SACA – SACD). — If new building(s) is/are built, tie landscape improvements to master plan phase 4 campus mall improvements. Address pinch point from master plan phase 10. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT VB Roofs — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 316 317 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 12: Renovate Building Services Complex 12 11 12 3 10 4 12 10 9 9 11 11 2 5 11 11 1 2 6 1 8 8 7 7 4 7 PHASING SITE PLAN Phase 12 0' 100' 200' 400' North Renovate Automotive Collision Repair Building: 12,996 SF — Existing program to remain. Renovate Building Services Physical Plant: 8,893 SF — Existing program to remain. Renovate Building Services Warehouse: 5,000 SF — Existing program to remain. Renovate Building Services Building: 6,160 SF — Existing program to remain. Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Implement major screening corridor along C.A. Roberson Rd. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Natural Gas Monitoring System Installation — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments — SO INFR Thermal Utilities Upgrades 318 319 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION 1 3 1 4 2 2 13 4 10 10 5 8 11 8 9 11 11 11 11 7 6 7 9 7 12 12 12 Phase 13: Renovate Science Building Renovate Science Building: 50,923 SF — Existing program to remain. PHASING SITE PLAN Phase 13 0' 100' 200' 400' North Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Outdoor improvements for the Science Building (SSCI) renovation should include planting shade trees, installing a landscape buffer, and improving connections to phase 8 campus mall upgrades. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments — SO SSCI Lab Air Damper and Reheat Coil Upgrade 320 321 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION 1 3 1 4 2 2 13 4 10 10 5 8 11 8 9 11 11 14 11 11 7 6 7 9 7 12 12 12 Phase 14: Renovate Business Building Renovate Business Building: 37,751 SF — Existing program to remain. Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — The Business Building (SBUS) renovation should prioritize ADA accessibility. — Additional improvements in this area should include landscape buffering, trash/ recycling receptacles where appropriate, and cart parking. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments PHASING SITE PLAN Phase 14 0' 100' 200' 400' North 322 323 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 15: Renovate Computer Learning Center 3 10 11 12 12 Renovate Computer Learning Center: 14,070 SF — Existing program to remain. Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Buffer/screen off Computer Learning Center’s (SCLC) roof railing. 4 10 12 9 9 13 14 15 11 11 1 1 2 2 4 5 8 8 11 11 7 6 7 7 Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment PHASING SITE PLAN — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments — SO TRIO SCLC 0106 Remodel Phase 15 0' 100' 200' 400' North 324 325 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 16: Renovate Technology Building 3 10 11 12 12 Renovate Technology Building: 42,005 SF — Existing program to remain. Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Connect to student space from master plan phase 9.   4 16 10 12 9 9 13 14 15 11 11 1 1 2 2 4 5 8 8 11 11 7 6 7 7 Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments PHASING SITE PLAN Phase 16 0' 100' 200' 400' North 326 327 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 17: Renovate Center of Excellence for Energy Technology Renovate Center of Excellence for Energy Technology Building: 90,022 SF Site 11 12 — Existing program to remain. — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Existing landscape beds should be replanted with a mix of new shrubs and groundcover (quantities and locations to be determined); shade and ornamental trees should be planted. 12 3 10 4 16 12 — Connections to the student gathering space implemented in phase 1 should be enhanced with the installation of new concrete pathways punctuated by paver bands. 10 17 9 9 17 13 14 15 11 11 2 5 11 11 Building — Replacement of systems is outlined in Volume II. 1 2 6 — Any structural modifications for planned renovations shall be identified. — DT INFR MDF MEP Upgrades 1 8 8 7 7 — DT VB Furniture Replacement/Renewal — DT Access Control 4 7 — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments — SO SETC Texas A&M Lab and Classroom PHASING SITE PLAN Phase 17 0' 100' 200' 400' North 328 329 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 18: Review Early College High School 18 Review Early College High School Site 3 4 10 10 11 16 12 12 12 — Option 1: Renovate ECHS. — Gross square footage renovated: 27,218 SF — Option 2: Review need of local ISDs that utilize the campus and the Early College High School to determine if an addition is needed or if the need could be solved through a new, larger Academic Classroom Building. — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Include outdoor student space to get students excited. — No mow/wildflower area to be incorporated on plan South of campus. Trees should be placed at regular intervals along the trail to provide shade for trail users. — The open space to the west of the pond (south of the main campus area) should be designated as a no-mow zone and planted with a custom wildflower seed mix. 17 17 13 9 14 9 15 11 11 1 1 2 2 4 5 8 8 11 11 7 6 7 7 Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments PHASING SITE PLAN Phase 18 0' 100' 200' 400' North 330 331 +VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION LEGEND New Construction Tarrant County College District 2022 District-wide Masterplan Phasing Tarrant County College District 2022 District-wide Masterplan Phasing Project Renovation TCC SOUTH CAMPUS MASTERPLAN PHASING TCC SOUTH CAMPUS MASTERPLAN PHASING 18 Project Projected Masterplan Phasing Project Costs Projected Masterplan Phasing Project Costs 3 17 1 1 17 4 2 2 10 10 13 15 4 5 8 11 8 9 11 11 16 14 11 11 7 6 7 9 7 12 12 12 Site Project Demo. Project Existing Building Phase Project Project Year Construction Cost Limitation Softs Costs (38%) Project Total Phase 1 Construct new Onboarding Building. 2023 $ 58,449,296.25 $ 22,210,732.58 $ 80,660,028.83 Improve campus front entry. 2023 $ 1,533,256.76 $ 582,637.57 $ 2,115,894.33 Renovate existing Enrollment Services Building (SERS). 2025 $ 5,396,063.40 $ 2,050,504.09 $ 7,446,567.49 Demolish existing Administration, Phase 2 Testing, Counseling Building (SACT).2025 $ 323,271.00 $ 122,842.98 $ 446,113.98 Demolish existing Testing Portable (SMTC). 2025 $ 54,492.75 $ 20,707.25 $ 75,200.00 Improve campus front entry. 2025 $ 3,400,733.70 $ 1,292,278.81 $ 4,693,012.51 Phase 3 Construct new Automotive Building. Future $ 49,878,295.56 $ 18,953,752.31 $ 68,832,047.87 Phase 4 Renovate existing Automotive Building (SAUT). Demolish existing Faculty Building Cluster (SFOA-SFOF). Future Future $ 23,348,754.90 $ 679,023.00 $ 258,028.74 $ 32,221,281.76 $ 937,051.74 Phase 5 Renovate existing Library Building (SLIB). Future $ 28,413,033.93 $ 10,796,952.89 $ 39,209,986.82 Phase 6 Renovate existing Performing Arts Center (SPAC). Future $ 13,628,865.60 $ 5,178,968.93 $ 18,807,834.53 Renovate existing Art Building (SART). Future $ 3,978,223.20 $ 1,511,724.82 $ 5,489,948.02 Phase 7 Renovate existing Music Classrooms Building (SMUS). Future $ 7,730,553.60 $ 2,937,610.37 $ 10,668,163.97 Renovate existing Recital Hall (SREC). Future $ 5,239,458.00 $ 1,990,994.04 $ 7,230,452.04 Phase 8 Renovate existing Student Union (SSTU). Renovate existing Bookstore (SBKS) Future Future $ 27,802,966.50 $ 7,398,553.93 $ 10,565,127.27 $ 2,811,450.49 $ 38,368,093.77 $ 10,210,004.43 Phase 9 Renovate existing Electronics Building (SELE). Renovate existing Mathematics Building (SMTH). Future Future $ 8,878,337.78 $ 6,979,168.71 $ 3,373,768.35 $ 2,652,084.11 $ 12,252,106.13 $ 9,631,252.82 Phase 10 Renovate existing Nursing Building (SNUR). Renovate existing Health Science Building (SHSC). Future Future $ 14,661,518.40 $ 4,236,632.91 $ 5,571,376.99 $ 1,609,920.51 $ 20,232,895.39 $ 5,846,553.42 Review existing Academic Classroom Building Cluster (SACA-SACD). Project presents option to renovate existing Academic Classroom Building Cluster (SACA-SACD). Future $ 21,112,012.80 $ 8,022,564.86 $ 29,134,577.66 Renovate existing Health and Physical Education Building (SHPE). Phase 11 Future $ 39,908,355.48 $ 15,165,175.08 $ 55,073,530.56 . $ 8,872,526.86 Phase Project Project Year Construction Cost Limitation Softs Costs (38%) Project Total Review existing Academic Classroom Building Cluster (SACA-SACD). Project presents option to demolish construct a new, larger Academic Classroom Building Future $ - $ - $ - Renovate existing Automotive Collision Repair Building (SACR). Future $ 9,552,683.81 $ 3,630,019.85 $ 13,182,703.66 Phase 12 Renovate existing Building Services Physical Plant (SBSP). Renovate existing Building Services Warehouse (SBSW). Future Future $ 5,620,038.07 $ 2,005,695.00 $ 2,135,614.47 $ 762,164.10 $ 7,755,652.53 $ 2,767,859.10 Renovate existing Building Services Building (SBSA). Future $ 2,719,498.32 $ 1,033,409.36 $ 3,752,907.68 Phase 13 Renovate existing Science Building (SSCI). Future $ 29,514,698.33 $ 11,215,585.36 $ 40,730,283.69 Phase 14 Renovate existing Business Building (SBUS). Future $ 16,599,535.20 $ 6,307,823.38 $ 22,907,358.58 Phase 15 Renovate existing Computer Learning Center (SCLC). Future $ 9,269,448.30 $ 3,522,390.35 $ 12,791,838.65 Phase 16 Renovate existing Technology Building (STEC). Future $ 26,469,582.71 $ 10,058,441.43 $ 36,528,024.13 Phase 17 Renovate existing Energy Technology Center (SETC). Future $ 60,243,808.00 $ 22,892,647.04 $ 83,136,455.03 Phase 18 Renovate existing Early College High School Building (SECH). Review existing Early College High School Building (SECH). Future Future $ 17,078,750.64 $ - $ 6,489,925.24 $ - $ 23,568,675.88 $ - POTENTIAL TOTAL COST $ 706,704,357.00 COST ESTIMATE NOTES — Escalation percentage added for projects from 2023 – 2027. — No additional escalation is added for projects after 2027. — Escalation percentage used is 1% per month. — Cost Estimates are based on pricing from 2022. CAMPUS SITE PLAN Consolidated Master Plan Phasing 0' 100' 200' 400' North 332 333 334 335 +VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION NORTHEAST CAMPUS SITE PLAN Master Plan Landscape Plan 0' 100' 200' 400' Northeast Campus KEY CAMPUS STATISTICS KEY MASTER PLAN STATISTICS Year Constructed: 1968 Phases: 12 Campus Size: 186.79 acres between North Richland Hills and Hurst New Construction: 171,000 SF Building Inventory: 23 Buildings, 665,862 SF New Additions: 125,000 SF Campus President: Dr. Ayers-Palmore Renovation: 607,613 SF Student Enrollment: 9,968 students Sitework: 166,000 SF Signature Programs: Potential Total Cost: $757,361,901.31 — Child Development — Dental Hygiene — Information Technology — Teacher Education — Visual Arts — World Languages North + HAR W O O D R O A D VOLUME I PRIORITIZATION GRAPEVINE HIGHWAY NBSA NDPP NMPC NDPW NBSA NDSC NDPA NSCW NTAB NHSC NSCE NHPE NACB NFAC NIMC NLIB NBSS NFAB NCAB NADM NSTU CAMPUS SITE PLAN Existing Conditions 0' 100' 200' 400' North VOLUME I PRIORITIZATION Northeast Campus Prioritization Background VISION The master plan programming for the future of the Northeast Campus should take into account the construction of new facilities aimed at meeting the current and future needs of technical programs, Early College High Schools, Student Support Services, and the development of a Learning Commons. Renovations, additions, and new construction should focus on implementing the College initiative of 3 Goals and 8 Principles. The master plan will further enhance the existing cohesiveness on campus by creating and enhancing pedestrian paths, outdoor spaces, and connections between the existing buildings and any new construction. DECISION DRIVERS — Older Science Buildings are nearing end of services life and do not meet the standards that the College has set. — Centralized Faculty Office Building limits direct access of faculty to students. — Onboarding process is decentralized and can be confusing. — Fine arts spaces are undersized and is due for upgrades in both technology and in space provided for performing arts. — Entry, circulation, and parking are challenging to access the Student Union for potential students. CORE ELEMENTS — Improve campus framework and views by demolishing buildings in poor conditions. — Opportunity to create a grand front entry at the Student Union and increase visibility and access. — Space to construct new Science Building to the North of existing Science Buildings. — Construction of new Science Building provides possible swing space or additional classroom space. — Increase parking access for potential students. — Existing community partnerships present opportunities to leverage. 336 337 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION 1 PHASING SITE PLAN Phase 1 0' 100' 200' 400' North VOLUME I PRIORITIZATION Phase 1: New Science Building Demolish Portable Building: 1,672 SF — Demolish to make way for new building. New Science Building: 68,000 SF — General Programming: 9,786 SF — Entry Lobby — Lecture space — Multidisciplinary Area — Collaboration Space — Write-up Meeting Space — Faculty Workspace: 5,300 SF — Include new Faculty Neighborhood. — Classrooms and Labs: 28,100 SF — Core/MEP: 4,986 SF Site — Prior to construction, the existing utilities that lie within the footprint of the proposed building will need to be relocated. The utilities include water, sanitary sewer, gas, telecommunication, and underground electric. A majority of the lines will need to remain in service, so the utility installation/relocation will need to be phased. — Existing underground utilities will need to be relocated. — Bike parking should be located near the building entrance. Masonry and metal panel screening walls should surround the bike parking to define and enhance the space and conceal parked bikes from view. — A student courtyard space design should include paved and landscaped areas. — The Central Plant should be buffered or screened via new landscaping (evergreen trees and tall shrub plantings). — To ensure safety, the Northeast Campus master plan must implement an access management plan. Building — It is anticipated that the existing campus network has capacity to connect this building to existing infrastructure. — Extend existing hydronic lines, power, water, gas, and communications to building. — See Volume II for Structural New Construction Narrative. — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 338 339 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION 1 2 2 2 PHASING SITE PLAN Phase 2 0' 100' 200' 400' North VOLUME I PRIORITIZATION Phase 2: Science Buildings Renovations Renovate Science East Building: 40,817 SF — Swing Space — Faculty Offices — General-purpose classrooms Renovate Science West Building: 30,929 SF — Swing Space — Faculty Offices — General-purpose classrooms Renovate Health Science Building: 29,410 SF — Expand Dental Hygiene program to entire building. — Establish Dental Hygiene faculty neighborhood. — Recent renovations to remain as-is. Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — The existing Science and Health buildings (NSCE, NSCW, NHSC) should be renovated, and designated ambulance parking should be designed and incorporated. The connection(s) between renovated buildings and parking lots should include landscape improvements to create more welcoming and functional spaces. — The existing gathering space between the Science and Health buildings (NSCE, NSCW, NHSC) should be gutted and renovated and all existing flagstone, drain edging treatment, and existing planting removed; drainage should be enhanced, and new paving should be installed. Paving design, layout, and material selection should promote accessibility in the space. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT VB Elevators Upgrades — DT IDF Cooling and UPS Installation — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 340 341 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION 1 2 2 2 3 3 3 PHASING SITE PLAN Phase 3 0' 100' 200' 400' North VOLUME I PRIORITIZATION Phase 3: New Campus Front Entry Renovate Student Union: 69,490 SF — Registrar, Business Services, and other associated Onboarding programming to be relocated from Administration and Business Services Building (NADM). — Expand dock at West side of building. — Addition for new front entry on South. — Entry canopy to provide visibility and a primary front door. Student Union Grand Front Entry Addition: 40,000 SF — Student Services: 14,545 SF — University/Workforce: 13,500 SF — Support Services: 1,650 SF Renovate Administration and Business Services Building: 15,277 SF — Improve building front entry. — Create Campus President’s Conference Center. Expand Parking: 98,000 SF — Construct expansion of parking at South side of NADM Building. — Expand parking at South of campus to East to edge of sidewalk on South edge of NADM Building. Site — There are existing water, sewer, and underground electric lines that lie the in location of the building addition and will need to be relocated prior to construction. — The existing parking lot located at the South side of the Administrative Building (NADM) is to be expanded. The drainage and grading will need to be analyzed to see if additional inlets will need to be installed. The underground electric lines will need to be extended for additional light poles. — Landscape improvements should highlight increased campus access and create a welcoming new campus “front door.” — Connections between the Student Union Building (NSTU)and pond should be strengthened with landscape improvements. — The existing courtyard East of the Student Union Building (NSTU) should be completely renovated. The new courtyard design should promote positive drainage. Furniture replacement/upgrades are also recommended. Building — Replacement of systems is outlined in Volume II. — See Volume II for Structural New Addition Narrative. Any structural modifications for planned renovations shall be identified. — DT VB Elevators Upgrades — DT IDF Cooling and UPS Installation — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 342 343 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION 1 2 2 2 4 4 3 3 3 PHASING SITE PLAN Phase 4 0' 100' 200' 400' North VOLUME I PRIORITIZATION Phase 4: Renovate Learning Commons and Business/Social Sciences Building Renovate Library: 46,324 SF — Renovate Library to conform to Learning Commons standards. — Consolidate Learning Commons functions. — Renovation will have to occur in two phases with each floor occurring separately. Renovate Business and Social Sciences Building: 44,448 SF — Existing program to remain. Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Renovations to these buildings should include plans for outdoor spaces to support building accessibility, functionality, safety, and beautification. — Landscape elements such as renovated hardscape and increased planting should be used to strengthen the connection between the existing parking lot and the renovated Business and Social Sciences Building (NBSS). — Plans should also consider decreasing the existing hardscape adjacent to Business and Social Sciences Building (NBSS) (plan North) or converting the area into a student space that speaks to the proposed quad in master plan phase 6.  Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT VB Elevators Upgrades — DT INFR MDF MEP Upgrades — DT VB Roofs — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 344 345 LEGEND VOLUME I PRIORITIZATION 2 2 3 1 2 5 4 3 3 5 4 LEGEND Current Phase Project Current Phase Site Project Current Phase Telecomm. Line Current Phase Demo. Project Previous Phase Project Previous Phase Site Project Previous Phase Telecomm. Line Existing Building PHASING SITE PLAN Phase 5 0' 100' 200' 400' North VOLUME I PRIORITIZATION + Phase 5: Demolish Academic Classroom and Faculty Offices Buildings Demolish Academic Classroom Building: 27,201 SF — Students to be distributed to renovated academic classrooms prior to demolition. Demolish Faculty Offices Building: 31,048 SF — Faculty to be distributed to renovated faculty neighborhoods prior to demolition. Site — During the demolition of the Faculty Offices Building (NFAC), there are several electrical underground electric lines, sanitary sewer, and fiber optic lines that will either need to be protected or relocated. — Before demolishing the Academic Classroom Building (NACB), the existing services that serve this building will need to be capped and protected, so that they can be used for the proposed Academic Classroom Building. — All areas affected by demolition should be re-vegetated to accommodate future development; implement site preservation strategies where applicable.   Building — Existing utilities shall be capped and staked for reuse later. — Complete removal of foundations adds demolition costs. — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 346 347 LEGEND VOLUME I PRIORITIZATION 2 2 3 1 2 6 5 4 3 3 5 4 6 LEGEND Current Phase Project Current Phase Site Project Current Phase Telecomm. Line Current Phase Demo. Project Previous Phase Project Previous Phase Site Project Previous Phase Telecomm. Line Existing Building PHASING SITE PLAN Phase 6 0' 100' 200' 400' North VOLUME I PRIORITIZATION + Phase 6: New Academic Classroom Building and Campus Mall Improvements New Academic Classroom Building: 105,000 SF — Determine function at time of construction. Building could function as ECHS with ISD touch-down space. — Student Services: 54,028 SF — Entry Lobby — Study Spaces — Cafetorium — Collegiate Administration Offices: 9,350 SF — Administrative Workstations — Conference Rooms — Support Services: 14,400 SF — Construct new bus drive for potential ECHS students. Campus Mall Improvements: 68,000 SF — Strengthen core campus mall and increase campus connectivity with ADA improvements. Site — While the building connections to the old Academic Classroom Building (NACB) are protected, they will need to be analyzed for capacity and if they need to be further extended based on the connections shown on the MEP plans. — The core campus mall should be strengthened and any open space be transformed into a campus quad comprised of an expansive event lawn space highlighted by tree/ shrub planting. — The quad and core mall should intersect and their relationship should be reinforced through landscaping design. — A sub-quad should exist plan South of the remodeled Library (NLIB). The space should welcome visitors to campus and be an obvious focal point with strong connections to other key campus spaces. The quad’s connection to the South parking lot should be improved and strengthened through strategic landscaping so as to create a welcoming campus entry. Building — Existing utilities from phase 5 shall be evaluated for reuse during this phase. — With the demolition in previous phase, review existing buildings for need to re-feed condiut to ensure that they remain operational. — See Volume II for Structural New Construction Narrative. — If existing building foundations are just demolished to a certain depth below grade, a survey of existing foundations will be required to coordinate layout of new foundations. — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 348 349 LEGEND 5 5 VOLUME I PRIORITIZATION LEGEND Current Phase Project Current Phase Site Project 7 7 Current Phase Telecomm. Line Current Phase 1 Demo. Project Previous Phase 2 Project 2 Previous Phase Site Project 2 6 5 6 Previous Phase 5 Telecomm. Line 7 Existing Building 4 7 4 9 3 3 3 PHASING SITE PLAN Phase 7 0' 100' 200' 400' North VOLUME I PRIORITIZATION + Phase 7: Fine Arts Building Renovation and Addition and Early Childhood Education Center Relocation Renovate Fine Arts Building: 48,907 SF — Re-work Theater back-of-house. — Maintain ongoing functionality of building during construction. — Ceramics lab was recently renovated, review at time of future renovation. New Fine Arts Building Addition: 10,000 SF — Addition for new front entry on South. — Enclosed Art Gallery. — Additional Studio space. — Possibly need swing space. Renovate District Physical Plant Building: 14,670 SF — Renovate building for relocated Early Childhood Education Center programming. Site — Within the proposed building addition footprint area there are several utilities that will need to be relocated. The utilities include a water line, sanitary sewer line, and an underground electric line. All of these utilities will need to remain in service while the new utilities are being installed and will have to be relocated in phases. — The Physical Plant Building (NDPP) should be renovated to become a Children’s Center with exterior play space. The existing play equipment could be updated; evergreen trees should be added to further screen the area from the adjacent road. Center renovation and landscape improvements should preserve the existing play area’s excellent visual access from the building. — The new Fine Arts Building Addition (NFAB) should include an area for pre/post event or program functions. This area will be characterized by tree, shrub, and lawn plantings as well as paving and shaded seating nooks. Building — Replacement of systems is outlined in Volume II. — See Volume II for Structural New Addition Narrative. Any structural modifications for planned renovations shall be identified. — DT VB Elevators Upgrades — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT VB Theatre Lighting and Sound Upgrades — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 350 351 LEGEND 5 5 VOLUME I PRIORITIZATION LEGEND Current Phase Project Current Phase Site Project 7 7 Current Phase Telecomm. Line Current Phase 1 Demo. Project Previous Phase 2 Project 2 Previous Phase 8 Site Project 2 6 5 6 Previous Phase 8 5 Telecomm. Line 7 Existing Building 4 7 4 3 3 3 0' 100' 200' 400' North VOLUME I PRIORITIZATION + PHASING SITE PLAN Phase 8 Phase 8: Health and Physical Education Building Renovation and Addition Renovate Health and Physical Education Building: 72,338 SF — Existing program to remain. New Health and Physical Education Building Addition: 75,000 SF — Health classrooms — Dedicated Cardio space — Covered outdoor learning environment Site — The new expansion will need connections to water, sewer, electrical, gas, and possibly storm drain as well as telecommunications. The addition may be able to share utilities with the existing building, however, an analysis of those existing utilities will need to be performed as well as the capacities and adherence to the proper building codes. — The Health and Physical Education Building (NHPE) expansion plan should include a covered outdoor learning environment, designated visually by landscape and paving. Existing fitness equipment should be relocated to accommodate the building’s expanded footprint. — The expanded Health and Physical Education Building (NHPE) should relate more closely to Tarrant County Jr. College Street and existing parking lots; crosswalks connecting the covered outdoor learning environment to the tennis courts across the street should be added. Removable bollards should be used as added protection from vehicular traffic. Building — Replacement of systems is outlined in Volume II. — See Volume II for Structural New Addition Narrative. Any structural modifications for planned renovations shall be identified. — DT VB Elevators Upgrades — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 352 353 LEGEND 5 5 VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION + LEGEND Current Phase Project 8 8 2 2 1 2 6 5 5 6 7 7 Current Phase Site Project Current Phase Telecomm. Line Current Phase Demo. Project Previous Phase Project Previous Phase Site Project Previous Phase Telecomm. Line 7 9 4 Existing Building 7 9 3 3 3 4 0' 100' 200' 400' North 354 355 PHASING SITE PLAN Phase 9 Phase 9: Renovate Communication and Instructional Media Center Buildings Renovate Communication Arts Building: 23,138 SF — Existing program to remain. Renovate Instructional Media Center: 18,128 SF — Existing program to remain. Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Building renovations should incorporate new outdoor spaces for gathering or studying and strengthen connections between new buildings and the existing campus network through renovated or newly constructed pathways, thoroughfares, and landscaped spaces. — Furniture in outdoor spaces can be new or repurposed from other renovated areas. — Designated cart parking should also be incorporated as buildings are renovated.   Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments LEGEND 5 5 VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION + LEGEND Current Phase Project Current Phase 1 7 7 Site Project Current Phase Telecomm. Line Current Phase Demo. Project Previous Phase 2 2 10 Project Previous Phase 8 8 2 6 5 5 6 Site Project Previous Phase Telecomm. Line 7 9 4 Existing Building 7 9 4 3 3 3 0' 100' 200' 400' North 356 357 Phase 10: Renovate Technology and Arts Building Renovate Technology and Arts Building: 71,197 SF — Existing program to remain. — Ongoing construction is just extensive finish upgrades, it includes no envelope upgrades. Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Plans should include a student gathering space and improved connections to the parking lot. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT VB Elevators Upgrades — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment PHASING SITE PLAN Phase 10 — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments LEGEND 5 5 Current Phase VOLUME I PRIORITIZATION LEGEND Project 11 Current Phase Site Project 7 7 Current Phase 11 11 Telecomm. Line Current Phase 1 Demo. Project Previous Phase 2 10 Project 2 Previous Phase 8 Site Project 2 6 5 6 Previous Phase 8 5 Telecomm. Line 7 Existing Building 9 4 7 4 9 3 3 3 0' 100' 200' 400' North VOLUME I PRIORITIZATION + PHASING SITE PLAN Phase 11 Phase 11: Renovate Building Services Complex Renovate Building Services Power Plant: 10,840 SF — Existing program to remain. Renovate District Service Center Warehouse: 5,885 SF — Existing program to remain. Renovate District Service and Print Center: 7,010 SF — Existing program to remain. Renovate Building Services Building: 8,070 SF — Existing program to remain. Renovate Building Services Ground Building: 1,410 SF — Existing program to remain. Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — A landscape buffer/screening (trees and/or tall shrub plantings) should be included around renovated buildings. — The area should be assessed for ADA accessibility and accessible routes improved where they are lacking/nonexistent.   Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Natural Gas Monitoring System Installation — DT VB Roofs — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 358 359 LEGEND 5 5 VOLUME I PRIORITIZATION LEGEND Current Phase Project 11 Current Phase Site Project 7 7 12 12 Current Phase 11 11 Telecomm. Line Current Phase 1 Demo. Project Previous Phase 2 10 Project 2 Previous Phase 8 Site Project 2 6 5 6 Previous Phase 8 5 Telecomm. Line 7 Existing Building 9 4 7 4 9 3 3 3 0' 100' 200' 400' North VOLUME I PRIORITIZATION + PHASING SITE PLAN Phase 12 Phase 12: Renovate Campus Support Buildings Renovate Early College High School Building: 28,710 SF Site — TCC Administration Offices — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Storage — Renovations to these buildings should include plans for outdoor spaces to support building accessibility, functionality, safety, and beautification.Renovate District Warehouse Building: 20,615 SF — Swing Space — Warehouse Storage — Greater Tarrant County Boys and Girls Club space Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments — NE NDPW Classrooms and Boys and Girls Club 360 361 5 5 VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION + LEGEND New Construction Project 11 Renovation 8 8 7 2 7 2 9 9 3 11 1 2 6 5 4 3 3 5 4 10 6 11 7 7 12 12 Project Site Project Demo. Project Existing Building 0' 100' 200' 400' North 362 363 Tarrant County College District 2022 District-wide Masterplan Phasing Tarrant County College District 2022 District-wide Masterplan Phasing TCC NORTHEAST CAMPUS MASTERPLAN PHASINGTCC NORTHEAST CAMPUS MASTERPLAN PHASING Phase Phase 1 Phase 2 Phase 3 Phase 4 Phase 5 Phase 6 Phase 7 Phase 8 Projected Masterplan Phasing Project Costs Project Year Construction Cost Limitation Softs Costs (38%) Project Remove existing portable building (NDPA). 2023 $ 57,060,585.00 $ 21,683,022.30 $ 78,743,607.30 2023 $ 77,625.00 $ 29,497.50 $ 107,122.50 2027 $ 20,773,812.15 $ 7,894,048.62 $ 28,667,860.77 2026 $ 15,949,555.83 $ 6,060,831.22 $ 22,010,387.05 2025 $ 14,968,219.50 $ 5,687,923.41 $ 20,656,142.91 Future $ 43,031,121.75 $ 16,351,826.27 $ 59,382,948.02 Future $ 34,780,320.00 $ 13,216,521.60 $ 47,996,841.60 Future $ 7,463,395.03 $ 2,836,090.11 $ 10,299,485.14 Future $ 2,359,244.12 $ 896,512.77 $ 3,255,756.89 Future $ 30,666,785.22 $ 11,653,378.38 $ 42,320,163.60 Future $ 22,494,709.80 $ 8,547,989.72 $ 31,042,699.52 2026 $ 2,139,496.61 $ 813,008.71 $ 2,952,505.31 2026 $ 892,785.24 $ 339,258.39 $ 1,232,043.63 Future $ 3,133,870.43 $ 1,190,870.76 $ 4,324,741.19 Future $ 93,729,825.00 $ 35,617,333.50 $ 129,347,158.50 Future $ 8,529,402.87 $ 3,241,173.09 $ 11,770,575.96 Future $ 26,304,140.88 $ 9,995,573.53 $ 36,299,714.41 Future $ 7,910,730.00 $ 3,006,077.40 $ 10,916,807.40 Future $ 12,710,683.08 $ 4,830,059.57 $ 17,540,742.65 Future $ 37,123,065.88 $ 14,106,765.04 $ 51,229,830.92 Construct new Science Building. Renovate existing Science East Building (NSCE). Renovate existing Science West Building (NSCW). Renovate existing Health Science Building (NHSC). Renovate existing Student Union Building (NSTU) and infill Onboarding. Construct new grand Front Entry addition and infill interior courtyard at Student Union Building (NSTU). Renovate existing Administration and Business Services Building (NADM). Construct expansion of parking at South side of Administration and Business Services Building (NADM). Renovate existing Library Building (NLIB). Renovate existing Business and Social Sciences Building (NBSS). Demolish existing Faculty Offices Building (NFAC). Demolish existing Academic Classroom Building (NACB). Strengthen core campus mall and increase campus connectivity with ADA improvements. Construct new Academic Classroom Building at site of old Academic Classroom Building (NACB). Renovate existing District Physical Plant Building (NDPP). Renovate existing Fine Arts Building (NFAB). Construct addition for Fine Arts Building (NFAB). Construct addition for Health and Physical Education Building (NHPE). Renovate existing Health and Physical Education Building (NHPE). Project Total Projected Masterplan Phasing Project Costs Project Construction Cost Softs CostsPhase Project Year Limitation (38%) Project Total Renovate existing Communication Arts Building (NCAB). Future $ 11,666,758.05 $ 4,433,368.06 $ 16,100,126.11 Phase 9 Renovate existing Instructional Media Center (NIMC). Future $ 11,781,205.92 $ 4,476,858.25 $ 16,258,064.17 Renovate existing Technology and Arts Building (NTAB). Phase 10 Future $ 35,884,628.78 $ 13,636,158.93 $ 49,520,787.71 Renovate existing Building Services Building (NBSA). Future $ 3,381,870.69 $ 1,285,110.86 $ 4,666,981.55 Renovate existing District Service and Print Center Building (NDSC). Future $ 3,171,844.17 $ 1,205,300.78 $ 4,377,144.95 Renovate existing Building Services Grounds (NBSG). Phase 11 Future $ 628,331.58 $ 238,766.00 $ 867,097.58 Renovate existing District Service Center Warehouse (NDSW). Future $ 2,360,703.02 $ 897,067.15 $ 3,257,770.16 Renovate existing Building Services Power Plant (NBSP). Future $ 6,891,926.58 $ 2,618,932.10 $ 9,510,858.68 Renovate existing Early College High School Building (NMPC). Future $ 14,535,798.30 $ 5,523,603.35 $ 20,059,401.65 Phase 12 Renovate existing District Warehouse Building (NDPW). Future $ 8,269,480.49 COST ESTIMATE NOTES — Escalation percentage added for projects from 2023 – 2027. — No additional escalation is added for projects after 2027. — Escalation percentage used is 1% per month. $ 3,142,402.58 $ 11,411,883.07 POTENTIAL TOTAL COST $ 746,127,250.91 — Cost Estimates are based on pricing from 2022. CAMPUS SITE PLAN Consolidated Master Plan Phasing CORGAN VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION + North 0' 100' 200' 400' NORTHWEST CAMPUS SITE PLAN Master Plan Landscape Plan Northwest Campus KEY CAMPUS STATISTICS KEY MASTER PLAN STATISTICS Year Constructed: 1975 Phases: 10 Campus Size: 187.50 acres in North Fort Worth New Construction: 81,600 SF Building Inventory: 38 Buildings, 523,460 SF New Additions: 22,000 SF Campus President: Dr. Blankenbaker Renovation: 230,361 SF Student Enrollment: 7,372 students (shared with Alliance West Site) Sitework: 1,370,164 SF Signature Programs: Potential Total Cost: $316,406,695.48 — Aviation — Criminal Justice — Dance — Fire Technology — Horticulture — Nondestructive Inspection, Testing, and Evaluation 364 365 DRIVE COLLEGE WFSK W F S C W F S S WACB VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION + WFMP WCJD WCTT WCJC WFSJ WCJR WFSI WPFR WFSF WFSH WFSG WFSA WFSB WFSD WFSE WMBB WMBA WHPE BUILDING 1 WGHB WHPB WBSA MARINE CREEK LAKE BUILDING 3 BUILDING 4 BUILDING 2 WATB WFSV Northwest Campus Prioritization Background WMBD VISION DECISION DRIVERS CORE ELEMENTS WMBC The master plan programming for the future of the Northwest Campus should take into account the construction of new facilities aimed at meeting the current and future needs of the Horticulture program, the Public Safety Training Center, and future enrollment growth. In addition, renovation, expansion, and reprogramming of the WHPE which provides resources for dance, physical education and aquatic programs should be addressed. The master plan will also focus on creating a cohesive campus and working to create paths, outdoor spaces, and connections between the existing buildings and any new construction. — Public Safety Training facilities and infrastructure need updates to match current standards of the professions that they seek to serve. — Removal of facilities nearing end-of-life provides space for landmark Public Safety Training program expansion. — Re-organization and expansion of Public Safety Training programs can established a more unified identity on the campus and for the community. — Horticulture program left without proper home after the ongoing bond projects. — Portables and re-purposed buildings present a poor impression to the groups and programs using those facilities. — Space to develop new facilities while existing buildings are utilized by current programs. — Much of campus core addressed by ongoing bond projects establishes a clear campus framework. — Ongoing bond projects provide a unified central campus, but do not respond to campus outskirts. — Ongoing and proposed construction efforts lack proper facility support. CAMPUS SITE PLAN Existing Conditions 0' 100' 200' 400' North 366 367 LEGEND VOLUME I PRIORITIZATION LEGEND 1 Current Phase Project Current Phase Site Project1 1 Current Phase Telecomm. Line1 Current Phase Demo. Project Previous Phase Project Previous Phase Site Project Previous Phase Telecomm. Line Existing Building 0' 100' 200' 400' North VOLUME I PRIORITIZATION + PHASING SITE PLAN Phase 1 Phase 1: Driving Pad Improvements and New Building Services Building New Building Services Building: 20,000 SF — Locate at construction hub. — Provide additional offices at construction hub. Expand Driving Pad : 102,000 SF — Construct fuel station and car wash area for PSTC vehicles. Renovate Driving Pad Storage : 600 SF — Existing program to remain. Renovate Multi-Purpose Services Building : 5,056 SF — Existing program to remain. Site — Within the new building footprint there are no utilities that appear within the area. Given that, new utilities will need to be extended to the site of the proposed building. — There is a City of Fort Worth sanitary sewer line along the south side of Northwest College Drive that may provide enough capacity to serve the new building. Other services that will/may be required are as follows: water services, electrical services, and storm drainage. — As the Northeast corner of the site becomes a construction hub, the Building Services Department should be relocated to this area. Shade trees should be planted around the perimeter of the building and along major walkways/pedestrian corridors. Building — See Volume II for MEP New Construction Narrative. — See Volume II for Structural New Construction Narrative. Any structural modifications for planned renovations shall be identified. — DT IDF Cooling and UPS Installation — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Natural Gas Monitoring System Installation — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 368 369 LEGEND VOLUME I PRIORITIZATION LEGEND 1 Current Phase Project Current Phase Site Project1 1 2 Current Phase Telecomm. Line12 Current Phase Demo. Project Previous Phase Project Previous Phase Site Project Previous Phase Telecomm. Line Existing Building 2 2 0' 100' 200' 400' North VOLUME I PRIORITIZATION + PHASING SITE PLAN Phase 2 Phase 2: Renovate Building Services Building and Demolish ECHS Buildings New Greenhouses: 9,200 SF — New greenhouses to be located at Criminal Justice Training Center in preparation for final home of Hor ticulture program with surrounding site to support program. Renovate Building Services Building: 16,405 SF — Temporary Horticulture program swing space. Demolish Aeronautical Technology Building: 62,502 SF — Students to be distributed to new ECHS prior to demolition. Demolish Outdoor Firing Range: 22,505 SF — Facility currently un-used. Demolish Greenhouses: 2,945 SF — Greenhouses currently in poor condition. Demolish Tennis Courts: 49,000 SF — Courts currently un-used. Remove Portables: 9,159 SF — Students to be distributed to new ECHS prior to demolition. Site — The new location of the proposed greenhouses does not contain many utilities. — During the demolition of the existing structures that are included in this phase, an evaluation of the existing utilities will need to be performed to determine if other structures will require those utilities to remain active. — Some parking and ADA spaces are also to be removed in this phase of the campus. An evaluation of the amount of ADA spaces that will remain on site will be needed. — Paths connecting the greenhouses to adjacent buildings should be constructed to tie into existing sidewalk networks. — Additionally, the demolition of the existing Outdoor Firing Range (WCJR), tennis courts, and Portable Buildings (WMBA, WMBB, WMBC, WMBD) creates an opportunity to increase recreational outdoor space on campus. New spaces should be landscaped with a mix of shrub plantings, groundcover, and shade and ornamental trees. Building — Replacement of systems is outlined in Volume II. — See Volume II for Structural New Construction Narrative. Any structural modifications for planned renovations shall be identified. — DT IDF Cooling and UPS Installation — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments — NW WBSP Cooling Tower Modifications 370 371 LEGEND VOLUME I PRIORITIZATION LEGEND 1 Current Phase Project Current Phase Site Project1 1 2 Current Phase Telecomm. Line12 Current Phase Demo. Project Previous Phase Project Previous Phase Site Project Previous Phase 3 Telecomm. Line Existing Building3 2 2 0' 100' 200' 400' North VOLUME I PRIORITIZATION + PHASING SITE PLAN Phase 3 Phase 3: New Public Safety Training Center Building New Public Safety Training Center Building: 28,000 SF — Combined First-Responder training — Nourishment Hub — Vehicle and equipment storage — Classrooms and labs — Faculty offices Improve Parking Lot and Landscaping: 150,000 SF — New parking lot and landscaping between new PSTC Building and existing Fire Service Training Center (WFSC). Site — With the new Public Safety Training Center building being proposed at the location of the previous Aeronautical Technology Building (WATB), it should be an easier transition due to the existence utilities and infrastructure. Coordination with the MEP will be useful in aligning the building connections of the proposed building with the locations that are convenient to the existing utilities. The grades and drainage will have to be analyzed for the new parking lot and landscaping as well as extending necessary utilities such as irrigation, underground electric, and storm drain. — A new parking lot should be constructed, with landscape elements included in the design. Landscaping should be installed between the new Public Safety Training Center Building and existing Fire Service Training Center (WFSC). Building — See Volume II for MEP New Construction Narrative. Replacement of systems is outlined in Volume II. — See Volume II for Structural New Construction Narrative. Any structural modifications for planned renovations shall be identified. — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments — NW MV Overcurrent Protection 372 373 LEGEND VOLUME I PRIORITIZATION LEGEND 1 Current Phase Project Current Phase Site Project1 1 2 Current Phase Telecomm. Line12 Current Phase 4 Demo. Project Previous Phase Project Previous Phase Site Project Previous Phase 3 Telecomm. Line Existing Building3 4 2 2 0' 100' 200' 400' North VOLUME I PRIORITIZATION + PHASING SITE PLAN Phase 4 Phase 4: Renovate Criminal Justice Training Center and Improve Amenities New Tennis Courts: 68,000 SF — Locate at site of old portables. Renovate Criminal Justice Training Center: 21,234 SF — Renovate for Horticulture program classrooms and labs. — New front entry. — Renovation to include plumbing upgrade. Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Building construction and renovations should consider connectivity to the broader campus environment. Sidewalks should be implemented to link buildings to existing campus networks, including connections to the Marine Creek Reservoir. — Coleman and Associates recommends continuing sidewalk connections from the Police Firing Range (WPFR) to the trail, parking lot, and Outdoor Firing Range (WCJR) and Criminal Justice Training Center (WCJC) buildings. — Additionally, tennis courts should be constructed on the site of the former portables; they should be surrounded by planted areas (lawn, shrub plantings, medium shade trees and ornamental trees).   Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT IDF Cooling and UPS Installation — DT INFR MDF MEP Upgrades — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments — NW WCJC HVAC/CUP Upgrades — NW WCJC Envelope Leaks 374 375 LEGEND VOLUME I PRIORITIZATION 2 2 4 5 5 3 3 4 2 2 LEGEND 1 Current Phase Project Current Phase Site Project1 1 Current Phase Telecomm. Line1 Current Phase Demo. Project Previous Phase Project Previous Phase Site Project Previous Phase Telecomm. Line Existing Building 0' 100' 200' 400' North VOLUME I PRIORITIZATION + PHASING SITE PLAN Phase 5 Phase 5: New Reality-Based Training Center and Firing Range Renovation New Reality-Based Training Center: 22,000 SF — New Reality-Based Training Center to function as addition to phase 3 PSTC Building and to augment existing functions. Renovate Police Firing Range: 33,843 SF — Existing program to remain. New Police Firing Range Addition: 22,000 SF — 50-yard range — Classroom — Storage Site — With the additions proposed during this phase, modifications to water, sanitary sewer, and electrical lines may be required. — The new Reality-Based Training Center is shown to be attached to the new Public Safety Training Center Building that was proposed in Phase 3. An analysis of the capacities and building code compliance will need to be performed to see if the Reality-Based Training Center can connect to the Training Center utilities or if additional utilities will need to be extended. — Building construction and renovations should consider connectivity to the broader campus environment. Sidewalks should be implemented to link to existing campus networks. — A large student gathering space should be incorporated on the Southeast side of the building. A combination of shade and ornamental trees should be planted around the perimeter of the gathering space to further define the area. Building — See Volume II for MEP New Addition Narrative. Replacement of systems is outlined in Volume II. — See Volume II for Structural New Addition Narrative. Any structural modifications for planned renovations shall be identified. — DT IDF Cooling and UPS Installation — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 376 377 LEGEND VOLUME I PRIORITIZATION 2 2 4 5 5 3 4 2 2 LEGEND 1 Current Phase Project Current Phase 1 1 Site Project Current Phase 1 Telecomm. Line Current Phase Demo. Project Previous Phase Project 6 Previous Phase Site Project Previous Phase 6 Telecomm. Line Existing 3 Building 0' 100' 200' 400' North VOLUME I PRIORITIZATION + PHASING SITE PLAN Phase 6 Phase 6: Upgrade Fire Field and Swift Water Training Areas Upgrade PSTC Fire Training Field: 700,000 SF — Phase to include all buildings and props used as part of the program’s Fire Field. — All associated buildings and props to be renovated, repaired, and upgraded. Upgrade Swift Water Training Area: 157,534 SF — All associated buildings and props to be renovated, repaired, and upgraded. Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Landscape improvements in this area may include street trees; the minimum planting distance between trees should be 40’ on-center to minimize fire hazards in the area. — A student gathering space designed to function as an outdoor classroom extension should be included in the design; the space should be covered by a generous aluminum shade structure on a concrete pavilion. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 378 379 LEGEND VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION + 1 LEGEND Current Phase Project Current Phase 2 4 2 5 5 4 3 3 6 7 1 6 7 1 1 Site Project Current Phase Telecomm. Line Current Phase Demo. Project Previous Phase Project Previous Phase Site Project Previous Phase Telecomm. Line Existing Building 2 2 0' 100' 200' 400' North 380 381 Phase 7: Renovate Fire Service Training Center and Fire Station Renovate Fire Service Training Center: 53,048 SF — Existing to remain. Renovate Fire Station: 7,647 SF — Existing to remain. Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — The Fire Service Training Center (WFSC) and Fire Station (WFSS) entry plaza space should be renovated to create a welcoming and logical entry sequence from the parking lot to the building. The plaza should provide seating and spaces for gathering in small groups as people arrive or leave the building. The reimagined entry plaza should be well-lighted and relate to the building architecture; constructed or renovated pathways should promote greater campus connectivity. — The connection to the parking lot should be improved through the implementation of a sidewalk and central planted areas to add shade and visual interest. — Landscape renovations should include ADA-accessible seating nooks, new shade trees, and concrete pathways punctuated with paver bands. Bike parking and cart parking should also be integrated to promote accessibility to the building. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT IDF Cooling and UPS Installation — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment PHASING SITE PLAN Phase 7 — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments — NW WFSC Plumbing LEGEND VOLUME I PRIORITIZATION LEGEND 1 Current Phase Project Current Phase 8 1 1 Site Project 2 Current Phase 2 1 Telecomm. Line Current Phase 4 Demo. Project Previous Phase 5 Project 6 Previous Phase 5 Site Project Previous Phase 3 6 Telecomm. Line Existing 3 7 Building 4 7 2 2 8 0' 100' 200' 400' North VOLUME I PRIORITIZATION + PHASING SITE PLAN Phase 8 Phase 8: Improve Outdoor Student Spaces New Prairie Restoration Learning Environment and Outdoor Classroom: 57,000 SF Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Build off of existing work completed by campus. — A prairie restoration learning environment and outdoor classroom should be constructed to the West of the existing NW College Drive. — Integrate project with relocated Horticulture program. — The prairie restoration area should include a no-mow zone (square footage to be determine) planted with native wildflowers and grasses. New Boathouse: 2,400 SF — New structure to include space for indoor storage of light watercraft used by students. — The outdoor classroom should include a shade structure with overhead fans, benches, and outdoor lighting.  Demolish old Boathouse: 1,200 SF — Building currently in poor condition. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments 382 383 LEGEND VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION + 1 LEGEND Current Phase Project 8 2 4 2 5 1 1 1 Current Phase Site Project Current Phase Telecomm. Line Current Phase Demo. Project Previous Phase Project 5 6 Previous Phase Site Project 3 6 Previous Phase Telecomm. Line 4 3 7 Existing Building 7 8 9 2 2 0' 100' 200' 400' North 384 385 Phase 9: Renovate Academic Classroom Building Renovate Academic Classroom Building: 26,605 SF — Existing program to remain. — Exterior scope included in ongoing construction effort. Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Renovations to the Academic Classroom Building (WACB) should include an expansive artificial turf lawn outfitted with movable furniture — See site furnishings exhibit for specific furniture recommendations. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments PHASING SITE PLAN Phase 9 LEGEND VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION + 1 LEGEND Current Phase Project 8 2 4 2 5 5 3 3 6 7 1 6 1 1 Current Phase Site Project Current Phase Telecomm. Line Current Phase Demo. Project Previous Phase Project Previous Phase Site Project Previous Phase Telecomm. Line Existing Building 4 7 10 8 9 2 2 0' 100' 200' 400' North 386 387 Phase 10: Renovate Health and Physical Education Building Renovate Health and Physical Education Building: 39,693 SF — Existing program to remain. — Infill pool. Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — The Health and Physical Education Building (WHPE) entry plaza should be renovated to create a welcoming and logical entry sequence from the parking lot to the building; the plaza design should relate to core campus mall connectivity efforts. — The connection to the parking lot should be improved through the implementation of a sidewalk and planted areas to add shade and visual interest. — Landscape renovations should include a lawn/open space to allow for outdoor gathering/recreation and provide students with views of the ponds from the building’s interior. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments — NW WHPE Flooring and Divider Curtain PHASING SITE PLAN Phase 10 VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION + 1 LEGEND New Construction Project Renovation TCC NORTHWEST CAMPUS MASTERPLAN PHASING 8 2 1 1 Project Projected Masterplan Phasing Project Costs Site Project Phase Project Project Year Construction Cost Limitation Softs Costs (38%) Project Total 2 1 4 Demo. Project 5 Existing Building 5 6 Tarrant County College District 2022 District-wide Masterplan Phasing Tarrant County College District 2022 District-wide Masterplan Phasing TCC NORTHWEST CAMPUS MASTERPLAN PHASING Projected Masterplan Phasing Project Costs Phase Project Project Year Construction Cost Limitation Softs Costs (38%) Project Total Construct new Building Services Building. Future $ 7,166,202.57 $ 2,723,156.98 $ 9,889,359.55 Construct Prairie Restoration Learning Environment and Outdoor Classroom. 2024 $ 444,924.90 $ 169,071.46 $ 613,996.36 Construct expansion to existing driving pad. Future $ 2,949,519.04 $ 1,120,817.24 $ 4,070,336.28 Phase 8 Construct new Boathouse. 2024 $ 1,559,865.60 $ 592,748.93 $ 2,152,614.53 Phase 1 Renovate existing Building Services Grounds Building (WCJS). Renovate existing Building Services Grounds Building (WFMP). Future Future $ 240,683.40 $ 1,444,100.40 $ 91,459.69 $ 548,758.15 $ 332,143.09 $ 1,992,858.55 Phase 9 Phase 10 Demolish old Boathouse (WHPB). Renovate Academic Classroom Building (WACB). Renovate Health and Physical Education Building (WHPE). 2024 Future Future $ 48,076.74 $ 18,269.16 $ 12,965,865.75 $ 4,927,028.99 $ 18,622,089.24 $ 7,076,393.91 $ 66,345.90 $ 17,892,894.74 $ 25,698,483.16 Renovate Building Services Building (WBSA). Demolish Aeronautical Technology Building (WATB). 2027 2027 $ 3,016,878.48 $ 1,146,413.82 $ 1,949,124.87 $ 740,667.45 3 6 3 7 4 $ 4,163,292.30 $ 2,689,792.32 POTENTIAL TOTAL COST $ 305,661,456.70 Phase 2 Remove portables (WMBA, WMBB, WMBC, WMBD). Demolish old outdoor Firing Range (WCJR). 2027 2027 $ 331,371.81 $ 49,116.38 $ 125,921.29 $ 18,664.22 $ 457,293.10 $ 67,780.60 Construct new Greenhouses. 2027 $ 1,060,290.00 $ 402,910.20 $ 1,463,200.20 Demolish old Greenhouses (WGHA, WGHB, WGHC). Demolish old tennis courts. 2027 2027 $ 91,735.88 $ 34,859.63 $ 1,069,645.50 $ 406,465.29 $ 126,595.51 $ 1,476,110.79 Construct new PSTC Building. Future $ 26,058,348.00 $ 9,902,172.24 $ 35,960,520.24 10 7 Phase 3 Construct new parking lot and landscaping between new PSTC Building and existing Fire Service Training Center (WFSC) at site of old tennis courts. Future 2 9 2 8 $ 3,367,124.91 $ 1,279,507.47 $ 4,646,632.38 Reskin and renovate Criminal Justice Training Center (WCJC) for programming as Horticulture program home. Phase 4 Future $ 14,441,620.28 $ 5,487,815.70 $ 19,929,435.98 Construct new tennis courts at site of old portables. Future $ 2,984,205.24 $ 1,133,997.99 $ 4,118,203.23 Construct new Reality-Based Training Center. Future $ 19,040,880.60 $ 7,235,534.63 $ 26,276,415.23 Phase 5 Phase 6 Phase 7 Renovate Police Firing Range (WPFR). Construct addition to existing Police Firing Range (WPFR). Renovate and upgrade PSTC training field buildings and props. Repair and upgrade Swiftwater Training area. Renovate Fire Service Training Center (WFSC). Renovate Fire Station (WFSS). Future Future Future Future Future Future $ 40,659,998.09 $ 15,450,799.27 $ -$ - $ 24,776,944.20 $ 9,415,238.80 $ - $ - $ 32,599,266.75 $ 12,387,721.37 $ 4,555,930.59 $ 1,731,253.62 $ 56,110,797.36 $ - $ 34,192,183.00 $ - $ 44,986,988.12 $ 6,287,184.21 COST ESTIMATE NOTES — Escalation percentage added for projects from 2023 – 2027. — No additional escalation is added for projects after 2027. — Escalation percentage used is 1% per month. — Cost Estimates are based on pricing from 2022. CAMPUS SITE PLAN Consolidated Master Plan Phasing 0' 100' 200' 400' North 388 389 CORGAN VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION + North 0' 100' 200' 400' ALLIANCE WEST SITE PLAN Master Plan Landscape Plan Alliance West Site KEY CAMPUS STATISTICS KEY MASTER PLAN STATISTICS Year Constructed: 1991 Phases: 4 Campus Size: 40.41 acres in North Fort Worth New Construction: 0 SF Building Inventory: 2 buildings, 164,060 SF New Additions: 0 SF Campus President: Dr. Blankenbaker Renovation: 71,939 SF Student Enrollment: 7,372 students (shared with Northwest Campus) Sitework: 136,000 SF Signature Programs: Potential Total Cost: $61,534,556,78 — Aviation — Avionics — Logistics and Supply Chain Management — Nondestructive Inspection, Testing, and Evaluation — Welding Technology 390 391 H E R I T A G E P A R K W A Y HORIZ O N DRIVE VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION 0' 100' 200' 400' North + 392 393 Alliance West Site Prioritization Background VISION Master plan programming for the Alliance West Site should be a multi-phase plan, allowing the facility to remain operational while renovations provide necessary updates and expansions. Reorganization and initial renovations should focus on the AMT shop/lab and its supporting facilities. Creating improved flow, additional support spaces, and functional adjacencies are a priority for this renovation. Additional projects should continue the focus on student, staff, and faculty needs, implementing the College initiative of 3 Goals and 8 Principles. Upgrading classrooms to align with IILE standards, providing student success spaces, and creating staff and faculty neighborhoods should be a priority as additional renovations occur. Creating a visible, welcoming, easily accessible main entry and an expanded pilot ramp are also proposed future site projects. SITE FLOOR PLAN Existing Conditions DECISION DRIVERS CORE ELEMENTS — Students lack dedicated study and breakout spaces for both individuals and small groups. — Facility lacks food service option despite students attending courses all-day. — Interior hangar space is at capacity and lacks acoustical attenuation appropriate for the courses using the space. — Visible presence for the College to workforce and community partners. — Space is available for Pilot Ramp Extension. — Former corporate identity of the building provides students with an environment that can parallel their potential future professional environment. — Programs are successful and offer unique opportunities for potential students in the College’s service area. LEGEND VOLUME I PRIORITIZATION LEGEND Current Phase Project Current Phase Site Project Current Phase Telecomm. Line Current Phase Demo. Project Previous Phase Project Previous Phase Site Project Previous Phase Telecomm. Line Existing Building 1 1 0' 100' 200' 400' North VOLUME I PRIORITIZATION + PHASING SITE PLAN Phase 1 Phase 1: Renovate Aviation Maintenance Technology Lab and Breakroom Construct Student Tool Storage Space: 3,852 SF — There is an existing space with lockers for students to use. Project looks to improve access and storage availability. Renovate Aviation Maintenance Technology Lab: 53,361 SF — Construct partitions between workspaces in hangars for acoustical separation. — Existing program to remain. Renovate Breakroom: 392 SF — Provide food service option as possible. Food service option to be at least a vending area with available associated seating. Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — The Aviation Maintenance and Tech Lab should be renovated and a space for student tool storage and separation between student workspaces should be included in the design. — The renovation of these spaces provides an opportunity to increase outdoor connectivity on the exterior and use the space surrounding to contextualize the exterior space visually and functionally within the broader campus framework. — The existing outdoor space should be enhanced to include a shade canopy/sail, shade trees, and additional planting. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT VB Furniture Replacement/Renewal — DT Natural Gas Monitoring System Installation — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments — NW OWTL 1703 Welding Lab Modifications 394 395 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 2: Improve Student Study Spaces and Classrooms Upgrade Classrooms to IILE Standards: 8,136 SF —Existing program to remain Establish Dedicated Student Study Spaces: 4,190 SF 2 —Renovate existing available space for dedicated student study spaces for both individuals and small groups. 2 1 1 Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —Clarify no landscape scope. If there is landscape scope, refer to college level guidelines and standards. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT VB Furniture Replacement/Renewal —DT VB Engaged Learning Institute Training Centers Renovation —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments PHASING SITE PLAN Phase 2 0' 100' 200' 400' North 396 397 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 3: Improve Campus Entry Improve Campus Front Entry: 2,008 SF —Include interior and exterior improvements. —Focus on wayfinding and campus character and quality. —Project seeks to align Alliance West with the identity of a community college campus. 2 2 1 31 Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —The main campus entry, including the parking lot located in front of it, should be renovated to become a welcoming, easily identifiable campus access point. —Site design should extend to the adjacent roads (Heritage Parkway and Horizon Drive), with signage used as an additional indicator of the campus’ presence. —Landscape updates should include repurposing/replacing site furniture, enhancing the landscape around flagpoles, creating landscape islands in the parking lot for trees, turf, and shrubs, landscaping around all major signage, and assessing and addressing inherent drainage issues.   Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments PHASING SITE PLAN Phase 3 0' 100' 200' 400' North 398 399 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 4: New Pilot Ramp Extension New Pilot Ramp Extension: 136,000 SF —Construction of Pilot Ramp Extension to expand program access to tarmac. 2 2 1 31 4 Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —Clarify no landscape scope. If there is landscape scope, refer to college level guidelines and standards. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments PHASING SITE PLAN Phase 4 0' 100' 200' 400' North 400 401 +VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION LEGEND Tarrant County College District 2022 District-wide Masterplan Phasing New Construction Project TCC NORTHWEST CEATL CAMPUS MASTERPLAN PHASING Renovation Project Projected Masterplan Phasing Project Costs Phase Project Project Year Construction Cost Limitation Softs Costs (38%) Project Total Renovate Aviation Maintenance Technology Lab/Shop (AMT). Future $ 47,769,156.00 $ 18,152,279.28 $ 65,921,435.28 Phase 1 Construct space for student tool storage Future $ - $ - $ - Renovate Break Room for Food Service option. Future $ - $ - $ - Phase 2 Renovate classrooms to align with Future $ 6,085,569.96 $ 2,312,516.58 $ 8,398,086.54 IILE standards. Create dedicated student study spaces. Future $ - $ - $ - Phase 3 Improve Front Entry. 2025 $ 1,284,660.00 $ 488,170.80 $ 1,772,830.80 Phase 4 Construct Pilot Ramp Extension. 2027 $ 5,572,135.80 $ 2,117,411.60 $ 7,689,547.40 POTENTIAL TOTAL COST $ 83,781,900.03 Site Project Demo. Project 2 2 Existing Building 1 1 3 4 COST ESTIMATE NOTES SITE FLOOR PLAN Consolidated Master Plan Phasing 402 0' 100' 200' 400' North —Escalation percentage added for projects from 2023-2027. —No additional escalation is added for projects after 2027. —Escalation percentage used is 1% per month. —Cost Estimates are based on pricing from 2022 403 404 405 + VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION SOUTHEAST CAMPUS SITE PLAN Master Plan Landscape Plan 0' 100' 200' 400' Southeast Campus KEY CAMPUS STATISTICS KEY MASTER PLAN STATISTICS Year Constructed: 1996 Phases: 9 New Construction: 85,000 SF New Additions: 49,357 SF Renovation: 436,698 SF Sitework: 305,000 SF Potential Total Cost: $479,944,795.45 Campus Size: 162.15 acres in Southeastern Arlington Building Inventory: 14 Buildings, 635,965 SF Campus President: Dr. Coppola Student Enrollment: 8,537 students Signature Programs: — Culinary Arts — Dietetics — Drama/Theater — Engineering — Hospitality Management North + PARK W A Y SOUT H E A S T EMOD VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION ECHS Southeast Campus Prioritization Background VISION The master plan programming for the future of the Southeast Campus should include the construction of additional academic facilities and student spaces. The construction of the Student Success Building and the Academic Building, scheduled for completion in 2024, provided the campus with additional space, but was unable to bridge the enrollment cap in terms of the overall campus space needs. Future expansion at the campus should focus on creating a college campus atmosphere with outdoor spaces, study spaces, student support areas, outdoor recreational areas, and provide a place for students to be. The overall plan should create a cohesive campus which includes the existing and future early college high school communities. DECISION DRIVERS —Existing Theater in need of increased support space. —Portable and temporary buildings are being used to support important outreach and support programs. —Limited space to grow programs within the existing main building. —Expansion of programs within the main building limit the growth of other programs. —Students are limited in the amount of study/sticky space dedicated to them outside of academic spaces. CORE ELEMENTS —Space to develop new facilities while existing buildings are utilized by current programs. —Much of campus addressed by ongoing bond projects establishes a clear deficiency list. —Campus framework provides a clear pathway for future development. ESSE ESEE ESEB ESEC ESED ESCT EBSP ESAC EART EBSE EBSA EBSB NE W YO R K AV E N U E EBSC CAMPUS SITE PLAN Existing Conditions 0' 100' 200' 400' North 406 407 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 1: Resolve Water Infiltration and Renovate Art Gallery Resolve Water Infiltration at Barrel Vaults: 9,000 SF —Prior work has been done to attempt to resolve but issue is ongoing. —Primary location of concern is the ESEC Wing. Renovate Art Gallery: 518 SF —Art Gallery located in ESEC Wing. —Renovation to include an improved presentation space and lockable art gallery. 11 PHASING SITE PLAN Phase 1 0' 100' 200' 400' North Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —The issue of water infiltration at the ESEC should be resolved, and design plans should ensure positive drainage. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT IDF Cooling and UPS Installation —DT INFR MDF MEP Upgrades —DT VB Furniture Replacement/Renewal —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments 408 409 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION 11 2 2 2 2 PHASING SITE PLAN Phase 2 0' 100' 200' 400' North VOLUME I PRIORITIZATION Phase 2: Performing Arts and Physical Education Renovations and Additions Renovate Physical Education Wing: 39,058 SF —Existing program to remain. —Infill pool. —Create dedicated Cardio and weightlifting space. —Expand Band Hall into Cardio space. New Physical Education Wing Addition: 17,647 SF —Full-size basketball court with space for bleachers on each side. —Demolish South wall of Pool room to connect with new addition. —To include new 130,000 SF outdoor activity space. Renovate Performing Arts Wing: 52,734 SF —Existing program to remain. New Performing Arts Wing Addition: 6,762 SF —Black Box Theater and stage —Associated back-of-house programming and support spaces Renovate Music Program Space: 10,868 SF —Dedicated Band/Orchestra Hall —Music faculty neighborhood —Sound-proofed music practice rooms and storage —Additional Music program support spaces Renovate Physical Plant: 10,015 SF —Existing program to remain. Site —Along with the building addition, a new outdoor activity spaces is to be constructed over existing water and storm drain lines. —Vegetative screening and/or fencing should be employed around the loading dock and other back-of-house elements. —It is also recommended that existing flagpoles be relocated and new landscaping consisting of shrubs and ornamental trees be installed, quantities and species flexible. —Landscape plans for the Physical Education Wing Addition (ESEB) should consider the field to the South of the new building; the field could be replanted with new turf and be utilized as a physical education/sport field. —A new sidewalk should be added to connect the Physical Education Wing Addition (ESEB) and sports field to the trail on the South end of campus. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT VB Elevators Upgrades —DT IDF Cooling and UPS Installation —DT INFR MDF MEP Upgrades —DT VB Furniture Replacement/Renewal —DT VB Theatre Lighting and Sound Upgrades —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments 410 411 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 3: Renovate Ballroom and Food Service and Enclose Academic Building Enclose First Floor of New Student Experience Building: 24,948 SF —Phase to include construction of shell for existing space below overhang of new ESAC Building. —Student Center/Lounge —Student activities space —Outdoor student space Renovate Ballroom and Food Service: 16,365 SF —Ballroom and food service located in ESEC Wing. —Include upgrades to Service Kitchen to cater events. Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —The space Southwest of the Performing Arts Wing (ESEC) should be renovated to create an outdoor study and dining space. Landscape elements should include a patio (concrete or pavers), shade structure, and plantings/vegetation including shrubs, groundcover, and ornamental trees. Furniture in the space should consist of picnic tables and café seating. —All back-of-house elements in the area should be screened with vegetation. —Additional screening around the utility plant may be required to mitigate noise. Building —It is anticipated that the existing plant will need to be expanded for this phase or a new, central, stand-alone plant will be required for this phase. Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT INFR MDF MEP Upgrades —DT VB Furniture Replacement/Renewal —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments 413 3 1 1 2 2 2 2 3 PHASING SITE PLAN Phase 3 0' 100' 200' 400' North 412 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 4: Renovate Fine Arts Building Renovate Fine Arts Building: 13,120 SF —Existing program to remain. 3 1 2 2 1 2 2 4 3 PHASING SITE PLAN Phase 4 0' 100' 200' 400' North Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —Fine Arts Building (EART) renovation plans should include landscape improvements; an outdoor study/gathering space could be created on the plan-West side of the Fine Arts Building (EART) to tie into phase 2. —Landscape enhancements in the space could include a permeable paver or decomposed granite patio with shade structure; furniture throughout should consist of picnic tables, café seating, and benches. —Planting at the edges of the patio/space should consist of shrubs and groundcover planting, species, and quantities to be determined. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT IDF Cooling and UPS Installation —DT INFR MDF MEP Upgrades —DT VB Furniture Replacement/Renewal —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments 414 415 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION 3 2 1 2 1 5 5 2 2 3 4 PHASING SITE PLAN Phase 5 0' 100' 200' 400' North VOLUME I PRIORITIZATION Phase 5: Improve Student Study Spaces and Classrooms Renovate Onboarding and Learning Commons Wing: 98,400 SF —Existing program to remain. —Onboarding programming to have been moved to new ESSE Building as part of ongoing bond project by Perkins and Will. Renovate Tiered Academic Classrooms: 3,207 SF —Tiered academic classrooms located in ESEE Wing. —Renovation to include enlarged steps for increased utilization. —Demolition is not possible because of mechanical spaces below existing classrooms. Establish Dedicated Student Study Spaces: 26,792 SF —Existing program to remain. —Renovation not to include ESEE Wing as it is being renovated as part of the ongoing bond project by Perkins and Will. Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —Onboarding and Learning Commons Wing (ESED) outdoor renovation plans should include a tiered outdoor classroom space; the area should include expanded/ oversized steps to navigate grade change and create an outdoor amphitheater. —Additionally, the campus front entry should be improved to include wayfinding and branding elements. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT VB Elevators Upgrades —DT IDF Cooling and UPS Installation —DT INFR MDF MEP Upgrades —DT VB Furniture Replacement/Renewal —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments 416 417 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION 6 6 3 11 5522 2 2 3 4 6 PHASING SITE PLAN Phase 6 0' 100' 200' 400' North 418 VOLUME I PRIORITIZATION Phase 6: New ECHS and Relocate Community Education and Engagement New Early College High School Building: 85,000 SF —Dedicated space for two ISDs —Touch-down space for four additional ISDs Renovate Early College High School: 28,986 SF —Students to be distributed to new ECHS prior to renovation. —Program to include space for the ASD and Continuing Education programs. Demolish Modular Buildings: 15,600 SF —Programs to be distributed to renovated ECHS prior to demolition. Site —With the demolition of the Modular Buildings (EMOD), the existing parking lot can be expanded to use the space that the building will vacate. After demolition, the parking lot will need to be resurfaced/reconstructed and re-striped. —A capacity analysis will need to be performed to see if they can serve the new structure. —Building renovation plans should include landscape enhancements; hardscape, student outdoor gathering spaces, and planting elements should strengthen the connections between buildings and the broader campus network. —Landscaping throughout should include a mix of shrubs, groundcover, and ornamental trees; quantities and species to be determined. —The butterfly garden (plan-West of new Academic Classroom Building) should be preserved; landscape enhancements such as new plantings or the addition of benches could be included in this phase. Building —Existing plant insufficient for phase and will need expansion. Replacement of systems is outlined in Volume II. —See Volume II for Structural New Construction Narrative. Any structural modifications for planned renovations shall be identified. —DT IDF Cooling and UPS Installation —DT INFR MDF MEP Upgrades —DT VB Furniture Replacement/Renewal —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments 419 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 7: Renovate Science and Technology Building 6 Renovate Science and Technology Building: 111,480 SF —Existing program to remain. 6 3 11 5522 7 2 2 3 4 6 Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —Landscape improvements around the renovated Science and Technology Building (ESCT) should increase the building’s connection to the parking lot. —Ramps and expanded sidewalks/pathways should be included in the design plan to improve accessibility. —Every other tree in the allée/row of trees surrounding the building could be removed for ease of maintenance. —Views from the building entry and parking lot to the lake on the South side of campus should be preserved so as to improve the building’s connection to the lake and trail system. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT INFR MDF MEP Upgrades —DT VB Furniture Replacement/Renewal —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments PHASING SITE PLAN Phase 7 0' 100' 200' 400' North 420 421 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 8: Renovate Building Services Complex 2 2 2 1 4 6 2 3 1 3 5 5 6 7 8 8 6 Renovate Building Services Building "A": 9,000 SF —Existing program to remain. Renovate Building Services Building "B": 4,155 SF —Existing program to remain. Renovate Building Services Building "C": 3,000 SF —Existing program to remain. PHASING SITE PLAN Phase 8 0' 100' 200' 400' North Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —The outdoor space plan East of Building Services Building “B” (EBSB) should be cleared of planting and debris and screened. —Landscape enhancements could include refreshed planting around the pond as well as the addition of benches and medium shade trees. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT INFR MDF MEP Upgrades —DT VB Furniture Replacement/Renewal —DT Natural Gas Monitoring System Installation —DT TCOC/SE VB Emergency Power and UPS Installation —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments 422 423 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line 9 VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 9: Improve Wayfinding and Pedestrian Experience 6 9 6 9 3 11 5522 7 2 2 3 4 8 8 6 Improve Campus Front Entry: 130,000 SF —Focus on wayfinding and campus character and quality. —Project to include usage of monument signage and defining architectural features. Improve Pedestrian Experience: 45,000 SF —Focus is on the connection between the existing Early College High School (ECHS) and the new Onboarding Building (ESSE) Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —Landscaped areas around the monument sign should be refreshed to include new shrubs and tur f; quantities are flexible. Planting and vegetation should not block the sign. —The pedestrian space around the Art Gallery should be improved with landscape and hardscape elements to improve functionality, accessibility, and aesthetic value. —Strengthen the connection between the main campus entry and the existing Early College High School (ECHS) by incorporating a sidewalk connection along the back of curb. —Shade trees should be planted at regular intervals along the sidewalk, quantities, and species to be determined. Building —It is anticipated that there is no MEP scope in this phase. If MEP scope occurs, replacement of systems is outlined in Volume II. —It is anticipated that there is no structural scope in this phase. If structural scope occurs, see Volume II for standards to apply. —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments PHASING SITE PLAN Phase 9 0' 100' 200' 400' North 424 425 + 6 9 6 9 3 1 2 2 1 5 5 7 2 2 4 3 8 8 VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION LEGEND Tarrant County College District New Construction 2022 District-wide Masterplan Phasing Project Renovation TCC SOUTHEAST CAMPUS MASTERPLAN PHASING 6 Project Projected Masterplan Phasing Project Costs 9 Site Project Demo. Project Existing Building 6 9 3 1 2 2 1 5 5 7 2 2 4 3 8 COST ESTIMATE NOTES 6 8 —Escalation percentage added for projects from 2023 – 2027. —No additional escalation is added for projects after 2027. —Escalation percentage used is 1% per month. PO —Cost estimates are based on pricing from 2022. CAMPUS SITE PLAN Consolidated Master Plan Phasing 0' 100' 200' 400' North 426 427 Project Construction Cost Softs CostsPhaseProject Project TotalYearLimitation(38%) Future $ 3,025,350.00 $ 1,149,633.00 $ Phase 1 Future $ 6,302,812.50 $ 2,395,068.75 $ Future $ 14,260,827.60 $ 5,419,114.49 $ Future $ 21,887,398.80 $ 8,317,211.54 $ Future $ 14,706,829.18 $ 5,588,595.09 $ Phase 2 Future $ - $ - $ Future $ - $ - $ Future $ 23,348,138.63 $ 8,872,292.68 $ Future $ 4,196,956.01 $ 1,594,843.28 $ Future $ - $ - $ Future $ 7,563,375.00 $ 2,874,082.50 $ Phase 3 Future $ 11,554,596.00 $ 4,390,746.48 $ Phase 4 Future $ 6,615,432.00 $ 2,513,864.16 $ Future $ - $ - $ Phase 5 Future $ 46,217,227.64 $ 17,562,546.50 $ Future $ - $ - $ Future $ 2,164,918.05 $ 822,668.86 $ Phase 6 Future $ 18,188,135.28 $ 6,911,491.41 $ Future $ 66,378,396.47 $ 25,223,790.66 $ Phase 7 Future $ 72,575,233.20 $ 27,578,588.62 $ Phase 8 2024 $ 3,574,692.00 $ 1,358,382.96 $ 2026 $ 2,425,503.42 $ 921,691.30 $ Phase 9 2026 $ 1,130,771.21 $ 429,693.06 $ TENTIAL TOTAL COST $ 4,174,983.00 8,697,881.25 19,679,942.09 30,204,610.34 20,295,424.27 - - 32,220,431.30 5,791,799.29 - 10,437,457.50 15,945,342.48 9,129,296.16 - 63,779,774.15 - 2,987,586.91 25,099,626.69 91,602,187.13 100,153,821.82 4,933,074.96 3,347,194.72 1,560,464.26 450,040,898.31 Resolve water infiltration at barrel vaults (ESEC). Renovate Art Gallery (ESEC). Construct Physical Education Addition. Renovate Physical Education Wing (ESEB Wing). Construct Performing Arts Addition. Renovate Theater Back-of-House and ancillary spaces (ESEC Wing). Renovate Music program space (ESEC Wing). Renovate Performing Arts Wing (ESEC Wing). Renovate Physical Plant (EBSP). Construct outdoor activity space. Renovate Ballroom and Food Service (ESEC Wing). Enclose First Floor of Student Academic Classroom Building (ESAC). Renovate Fine Arts Building (EART). Renovate main building with study spaces throughout (ESEB Wing, ESEC Wing, ESED Wing). Renovate Onboarding and Learning Commons Wing (ESED Wing). Renovate tiered Academic Classrooms (ESEE). Demolish Modular Building (EMOD). Renovate Early College High School (ECHS). Construct new Early College High School Building. Renovate Science and Technology Building (ESCT). Renovate Building Services cluster (EBSA, EBSB, EBSC). Strengthen campus front entry wayfinding and branding. Improve pedestrian experience between Early College High School and main building. 428 429 + VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION TRINITY RIVER CAMPUS SITE PLAN Master Plan Landscape Plan Trinity River Campus KEY CAMPUS STATISTICS KEY MASTER PLAN STATISTICS Phases: 9 New Construction: 220,000 SF New Additions: 0 SF Renovation: 230,214 SF Sitework: 339,520 SF Potential Total Cost: $434,238,970.00 Year Constructed: 2003 Campus Size: 39.9 acres in downtown Fort Worth Building Inventory: 1 Building Complex, 965,360 SF Campus President: Dr. Madison Student Enrollment: 5,908 students (shared with Trinity River Campus East) Signature Programs: — GIS Technology — Healthcare Professions — Sign Language Interpreting 0' 100' 200' 400' North + T F O R K (T R W F ) WE S FOR K ) F CLE A R CRT ( TRPGPARKING TRIN I T Y ) RTR T ( EAST F O R K (TRE F ) TRTRELBOW VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION TRINITY RIVER Trinity River Campus Prioritization Background STREET VISION Master plan programming for the Trinity River Campus is envisioned as a multi-phase plan, allowing the facility to remain operational while renovations provide necessary updates and improvements. This campus requires multiple building and campus wide improvements including. While the building is beautiful, it is over 15 years old and has some deferred maintenance and functional improvements which need addressed. Trinity River currently has a multi-level “Main Street” in the TRTR Building which provides a number of student services. A major project of the master plan on the campus is the further development of a main, welcoming, accessible entry point which provides easy and direct access to the “Main Street”. The construction of a new fourth wing is recommended to house the Health Care Professions. Development of the new tower and all interior renovations should include the implementation of the College initiative 3 Goals and 8 Principles. DECISION DRIVERS —Existing Health Professions program space is at capacity and is not appropriately equipped or sized for those programs. —Onboarding process has poor visibility and access and can be confusing. CORE ELEMENTS —Construction of new Health Professions Tower consolidates programming and frees space at Trinity River Campus East for future development. —Visible presence for the College to workforce and community partners. MI L L S ST R E E T PEACH STREET BLUFF STREET HE N D E R S O N ST R E E T (H W Y 19 9 ) TA Y L O R ST R E E T —Entry, circulation, and parking are challenging to articulate the Onboarding process for potential students. —Retrofit of former corporate campus has caused programs to be infilled sporadically. —Programs are successful and offer unique opportunities for potential students in the College’s service area. —Space to develop new Onboarding facility and emphasize the importance of student experience to the campus. —Previous usage of campus for a corporate entity is at odds with usage by a community college and students. IDEA STORE (TRIS) BELKNAP STREET BELKNAP STREET CAMPUS SITE PLAN Existing Conditions 0' 100' 200' 400' North 430 431 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 1: New Onboarding Center New Onboarding Center: 85,000 SF —Onboarding Center Addition to connect to TRTR floor 3, TREF floor 2, and TRIS floor 1. —Phase to include sitework for new Student Entry near existing drop-off/circle drive. —Welcome Center: 8,900 SF —Student Services: 49,160 SF —Campus Support Spaces: 2,950 SF —Core/MEP: 7,600 SF 1 PHASING FLOOR PLAN Phase 1 0' 100' 200' 400' North Site —Within the footprint of the new addition, there are sanitary sewer, telecommunication, irrigation, and underground electric lines that will have to be relocated. —This phase will also impact ADA parking spaces and regular parking spaces. The rest of the parking spaces on campus will need to be counted to see the required amount of ADA parking spaces have been provided. —The exterior plaza landscaping should be simplified (groundcover replaced with turf/ lawn where appropriate) for ease of maintenance. —Additional landscape enhancements in the space could include the addition of outdoor furniture (tables, chairs, benches) at the Rotunda/drop-off area and other exterior plazas to increase functional gathering and study space. —Will need to coordinate with service provider to protect and relocate service feeds within proposed project footprint. Building —It is anticipated the existing campus network has capacity to connect this building to the existing infrastructure. Further detail is outlined in Volume II. —See Volume II for Structural New Construction Narrative. —DT VB Furniture Replacement/Renewal —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments 432 433 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 2: New Health Professions Innovation Center Tower New Health Professions Innovation Center Tower: 135,000 SF —New Health Professions Innovation Center Tower to include programming for Physical Therapy, Radiology, Respiratory, Nursing, Surgical Tech. and other existing Health Science programs at the Trinity River Complex. —General programming: 34,175 SF —Faculty Workspace: 4,280 SF —Classrooms/labs: 45,865 SF 2 —Core/MEP: 15,600 SF 1 PHASING FLOOR PLAN Phase 2 0' 100' 200' 400' North Site —For this phase, standard parking and ADA parking spaces will need to be removed. The existing utilities that will be affected by the new building will be irrigation, telecommunication, and underground electric. —The construction of this new building may impact the walkability/pedestrian connectivity to the rest of the campus. —The exterior plaza landscaping should be simplified (groundcover replaced with turf/ lawn where appropriate) for ease of maintenance. —Additional landscape enhancements in the space could include the addition of outdoor furniture (tables, chairs, benches) at the Rotunda/drop-off area and other exterior plazas to increase functional gathering and study space. —Will need to coordinate with service provider to protect and relocate service feeds within proposed project footprint. Building —It is anticipated the existing campus network has capacity to connect this building to the existing infrastructure. Further detail is outlined in Volume II. —See Volume II for Structural New Construction Narrative. —DT VB Furniture Replacement/Renewal —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments 434 435 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 3: Renovate Trinity River Tower Renovate Rotunda and Community Education Area: 13,259 SF —New student entry. —Renovate space for program use by Community Education. —Located at TRTR floor 3. Renovate Science Labs: 16,296 SF —Renovate space for program use as Synergy Labs. —Located at TRTR floor 3. 3C Renovate Healthcare Workforce Annex: 6,968 SF —Renovate space for program use by Health Professions programs. —Located at TRTR floor 3. 3A 3B PHASING FLOOR PLAN Phase 3 0' 100' 200' 400' North Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —Clarify no landscape scope. If there is landscape scope, refer to college level guidelines and standards. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT VB Furniture Replacement/Renewal —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments —TR Healthcare Workforce Development Annex Remodel 436 437 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 4A: Renovate Study Rooms Renovate Study Rooms: 2,174 SF —Renovate space for program use as Writing Lab. —Located at TREF floor 2. Current location is TREF floor 1. Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —Clarify no landscape scope. If there is landscape scope, refer to college level guidelines and standards. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT VB Furniture Replacement/Renewal —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments 4A PHASING FLOOR PLAN Phase 4A 0' 100' 200' 400' North 438 439 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 4B: Renovate Writing Center Renovate Writing Center: 2,040 SF —Renovate space for program use as Physics and general-purpose classroom. —Located at TREF floor 1. Current location is TREF floor 2. Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —Clarify no landscape scope. If there is landscape scope, refer to college level guidelines and standards. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT VB Furniture Replacement/Renewal —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments 4B PHASING FLOOR PLAN Phase 4B 0' 100' 200' 400' North 440 441 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 4C: Renovate Physics Classroom Renovate Physics Classroom: 1,635 SF —Renovate space for program use as Media Viewing space. —Located at TREF floor 2. Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —Clarify no landscape scope. If there is landscape scope, refer to college level guidelines and standards. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT VB Furniture Replacement/Renewal —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments 4C PHASING FLOOR PLAN Phase 4C 0' 100' 200' 400' North 442 443 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 4D: Renovate Media Viewing Renovate Media Viewing: 1,445 SF —Renovate space for program use as Study Rooms and Photo Studio. —Located at TREF floor 2. Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —Clarify no landscape scope. If there is landscape scope, refer to college level guidelines and standards. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT VB Furniture Replacement/Renewal —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments 4D PHASING FLOOR PLAN Phase 4D 0' 100' 200' 400' North 444 445 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 4E: Renovate Learning Commons Renovate Learning Commons: 13,657 SF —Existing program to remain. —Located at TREF floor 2. Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —Clarify no landscape scope. If there is landscape scope, refer to college level guidelines and standards. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT VB Furniture Replacement/Renewal —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments —TR TRTR Learning Commons Digital Emporium 4E PHASING FLOOR PLAN Phase 4E 0' 100' 200' 400' North 446 447 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 5: Improve Outdoor Student Spaces New Outdoor Fitness Area: 202,574 SF —Project to include basketball court. New Outdoor Learning Environment: 8,540 SF —Project to include outdoor classroom. Improve Exterior Plazas and Student Areas: 128,406 SF 5 2 —Phase to include all outdoor student spaces. 5 1 5 PHASING FLOOR PLAN Phase 5 0' 100' 200' 400' North Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —Areas for outdoor learning environments on campus should be identified and created. —These spaces should include amenities such as shade structures, overhead fans/ lighting, site furniture, trash and recycling bins, and electrical amenities including Wi-Fi coverage, charging stations, and electrical outlets. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT VB Furniture Replacement/Renewal —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments —TR TR/TRCE Exterior Lighting Upgrades —TR Henderson Bridge Lighting and Security 448 449 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 6: Renovate Pharmacy Technician Lab Renovate Pharmacy Technician Lab: 4,201 SF —Existing program to remain. 6 —Located at TRWF floor 5. Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —Clarify no landscape scope. If there is landscape scope, refer to college level guidelines and standards. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT VB Furniture Replacement/Renewal —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments PHASING FLOOR PLAN Phase 6 0' 100' 200' 400' North 450 451 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 7: Renovate and Upgrade Faculty Offices Renovate and Upgrade Faculty Offices: 121,160 SF — Upgrade technology for lecture capture and recording. — Existing program to remain. — Located at TRCF floor 4, 5, 6, 7. 7 Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Clarify no landscape scope. If there is landscape scope, refer to college level guidelines and standards. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT VB Furniture Replacement/Renewal — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments PHASING FLOOR PLAN Phase 7 0' 100' 200' 400' North 452 453 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 8: Renovate Data and Building Systems Center Renovate Data and Building Systems Center: 30,290 SF —Existing program to remain. —Located at TRCF floor 1. 8 Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —Clarify no landscape scope. If there is landscape scope, refer to college level guidelines and standards. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT VB Furniture Replacement/Renewal —DT Natural Gas Monitoring System Installation —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments —TR INFR Medium Voltage Distribution and Emergency Power Upgrades —TR Plant/Replace Chiller PHASING FLOOR PLAN Phase 8 0' 100' 200' 400' North 454 455 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 9: Renovate Chancellor's Office Suite Renovate Chancellor's Office Suite: 17,089 SF 9 —Focus of renovation is on soundproofing of conference and huddle rooms. —Existing program to remain. —Located at TRWF floor 1. Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —Clarify no landscape scope. If there is landscape scope, refer to college level guidelines and standards. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT VB Furniture Replacement/Renewal —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments PHASING FLOOR PLAN Phase 9 0' 100' 200' 400' North 456 457 +VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION LEGEND Tarrant County College District New Construction 2022 District-wide Masterplan Phasing Project Renovation TCC TRINITY RIVER CAMPUS MASTERPLAN PHASING Project Projected Masterplan Phasing Project Costs Site Project Phase Project Project Year Construction Cost Limitation Softs Costs (38%) Project Total Phase 1 Construct new Onboarding Center addition. Future $ 80,988,732 $ 30,775,718 $ 111,764,450 5 Demo. Project Phase 2 Construct new Health Professions Innovation Center Tower. Future $ 127,898,800 $ 48,601,544 $ 176,500,344 Existing Building Phase 3 Renovate existing Rotunda and Community Education space (TRTR Floor 3). Renovate existing Science Labs (TRTR Floor 3). Future Future $ $ 8,616,892 $ 10,364,266 $ 3,274,419 3,938,421 $ $ 11,891,310 14,302,688 2 Renovate existing Healthcare Workforce Annex (TRTR Floor 3). Renovate existing Study Rooms TREF Floor 2). Future Future $ $ 4,528,434 $ - $ 1,720,805 - $ $ 6,249,238 - Renovate existing Writing Center (TREF Floor 1). Future $ - $ - $ - Phase 4 Renovate existing Physics Classroom (TREF Floor 2). Future $ - $ - $ - Renovate existing Media Viewing (TREF Floor 2). Future $ - $ - $ - Renovate Learning Commons (TREF Floor 2). Future $ - $ - $ - Strengthen exterior plazas and improve outdoor student spaces. Future $ 4,395,957 $ 1,670,464 $ 6,066,421 5 Phase 5 Contruct outdoor Learning Environment and Classroom. Future $ 185,322 $ 70,422 $ 255,745 Construct outdoor Fitness Area and Basketball Court. Future $ 2,786,474 $ 1,058,860 $ 3,845,335 Phase 6 Renovate Pharmacy Tech. Lab (TRWF Floor 4). Future $ - $ - - Renovate existing Faculty Offices Phase 7 and upgrade technology for lecture capture and recording (TREF Floor 4-Future $ 10,418,220 $ 3,958,924 $ 14,377,144 7). 1 Phase 8 Phase 9 Renovate existing Data Center and Building Systems (TRCF Floor 1). Renovate existing Chancellor's Office Suite (TRWF Floor 1). Future Future $ $ 19,748,207 11,340,047 $ $ 7,504,319 4,309,218 $ $ 27,252,526 15,649,265 5 POTENTIAL TOTAL COST $ 388,154,465 COST ESTIMATE NOTES —Escalation percentage added for projects from 2023 – 2027. —No additional escalation is added for projects after 2027. —Escalation percentage used is 1% per month. —Cost estimates are based on pricing from 2022. CAMPUS SITE PLAN Consolidates Master Plan Phasing 0' 100' 200' 400' North 458 459 +VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION TRHN TRHA Trinity River Campus East TRHN BELKNAP STREET TRHT TRHP KEY CAMPUS STATISTICS Year Constructed: 2011 Campus Size: 8.75 acres in downtown Fort Worth Building Inventory: 5 Buildings, 134,364 SF Campus President: Dr. Madison KEY MASTER PLAN STATISTICS Phases: 1 New Construction: 0 SF New Additions: 0 SF Renovation: 134,364 SF Sitework: 0 SF Potential Total Cost: $123,728,094.53 CO M M E R C E ST R E E T TRHW CA L H O U N ST R E E T Student Enrollment: 5,908 students (shared with Trinity River Campus) Signature Programs: — Healthcare Professions — Nursing TRINITY RIVER CAMPUS EAST SITE PLAN Master Plan Site Plan 0' 50' 100' 200' North 460 461 463 +VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION TRHN TRHN BELKNAP STREET TRHT TRHA TRHP Trinity River Campus East Prioritization Background VISION Master plan programming for Trinity River Campus East should be a multi-phase plan, allowing the facility to remain operational while renovations provide necessary updates and improvements. Trinity River East is the newest Tarrant County College physical campus and as a result does not have a significant amount of deferred maintenance. However, while in physically good condition, the facilities are not particularly suited for health care education. Multiple levels, exterior access classrooms, long linear buildings, and minimal room for future expansion suggest this location is not the best fit for the TCC health care professions. Master planning for TRCE looks slightly different from the other campuses, as it is the recommendation of the team to repurpose the campus for a higher and better use. The Health Care Professions should be located in a newly constructed tower on the Trinity River Campus. Development of the new tower should include the implementation of the College initiative 3 Goals and 8 Principles. DECISION DRIVERS — Existing Health Professions program space is at capacity and is not appropriately equipped or sized for those programs. — Entry, circulation, and parking are challenging to accommodate the students using the campus. CORE ELEMENTS — Construction of new Health Professions Tower consolidates programming and frees space at Trinity River Campus East for future development. — Visible presence for the College to workforce and community partners. — Retrofit of campus planned for administrative usage has caused Health Profession programs to lack space designed appropriately to their needs. — Programs are successful and offer unique opportunities for potential students in the College’s service area. — Existing community partnerships present opportunities to leverage. CO M M E R C E ST R E E T TRHW CA L H O U N ST R E E T CAMPUS SITE PLAN Existing Conditions 0' 50' 100' 200' North 462 465 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION 1 1 11 1 PHASING SITE PLAN Phase 1 0' 50' 100' 200' North VOLUME I PRIORITIZATION Phase 1: Renovate Trinity River Campus East Renovate Physical Plant: 3,645 SF — Existing program to remain. Renovate Classroom Building: 67,782 SF — Existing program to remain. Renovate Nursing Building: 48,515 SF — Existing program to remain. Renovate Testing Building: 4,601 SF — Existing program to remain. Renovate Faculty Offices Building: 9,821 SF — Existing program to remain. Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Clarify no landscape scope. If there is landscape scope, refer to college level guidelines and standards. Building — Replacement of systems is outlined in Volume II. — Any structural modifications for planned renovations shall be identified. — DT VB Furniture Replacement/Renewal — DT Natural Gas Monitoring System Installation — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments — TR TR/TRCE Exterior Lighting Upgrades — TR Waterfall Modifications — TR Gamma Camera Room 464 +VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION LEGEND Tarrant County College District 2022 District-wide Masterplan Phasing New Construction Project TCC TRINITY RIVER EAST CAMPUS MASTERPLAN PHASING Renovation Project Projected Masterplan Phasing Project Costs Site Project Phase Project Project Year Construction Cost Limitation Softs Costs (38%) Project Total Renovate existing Trinity River East Physical Plant (TRH). Future $ 1,330,538 $ 505,604 $ 1,836,142 Demo. Project Renovate existing Trinity River East Classroom Building (TRHA). Future $ 50,809,050 $ 19,307,439 $ 70,116,489 Phase 1 Renovate existing Trinity River East Nursing Building (TRHN). Future $ 30,362,663 $ 11,537,812 $ 41,900,475 1 Existing Building Renovate existing Trinity River East Testing Building (TRHT). Renovate existing Trinity River East Faculty Offices (TRHW). Future Future $ $ 2,637,128 4,852,648 $ $ 1,002,109 1,844,006 $ $ 3,639,237 6,696,654 1 POTENTIAL TOTAL COST $ 124,188,997.19 11 1 COST ESTIMATE NOTES CAMPUS SITE PLAN Consolidated Master Plan Phasing 466 0' 50' 100' 200' North — Escalation percentage added for projects from 2023 – 2027. — No additional escalation is added for projects after 2027. — Escalation percentage used is 1% per month. — Cost estimates are based on pricing from 2022. 467 + 2060B-X MECH VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION 24 0 0 A - X CO R R I D O R 2907A OPEN OFFICE 2801A OPEN OFFICE TCC Connect 2703-C 2903A CONFERENCE OFFICE 2905A 2906A 2802A 2803A 2804A 2805A STORAGE 2902A-S 2904A FOCUS FOCUS FOCUS FOCUS FOCUS FOCUSFOCUS 2900A-X 2800A-X CORRIDOR CORRIDOR 2503-R MEN'S 2561A-X 2801-C CONFERENCE 2460A-X 2860A-X 2702A 2901A IDF IDF ELECTRICAL 2602A-S OFFICE OFFICE KEY CAMPUS STATISTICS Year Constructed: 2015 Campus Size: Single floor of Trinity River Campus West Fork Building Inventory: TRWF floor 2 — 30,290 SF Campus President: Dr. Morales Student Enrollment: 14,763 students across the college Signature Programs: KEY MASTER PLAN STATISTICS Phases: 5 New Construction: 0 SF New Additions: 0 SF Renovation: 69,017 SF Sitework: 0 SF Potential Total Cost: $59,912,274.00 STORAGE 2800B-X 2700A-X LOUNGE MECHANICAL 2360A-X CORRIDOR 2207 CORRIDOR 2500A-X 2206-C TRAINING 2600A-X CONFERENCE CORRIDOR 2601-C 2701A 2210A 2560A-X CONFERENCE VIDEO PRODUCTION OFFICE ELECTRICAL 2300A-X 2502-R CORRIDOR WOMEN'S 2200A-X 2504B-X 1174-X 2301A-X CORRIDOR ELEV. 4 ELEV. LOBBY 2501A-S JANITORIAL2103-C STORAGE CONFERENCE 2101-K BREAK RM. 2204A 2208A 2209A FOCUS FOCUS FOCUS 2211A 2212A 1171-X 1172-X 1173-X FOCUS FOCUSELEV. 1 ELEV. 2 ELEV. 3 2202A 2203A FOCUS2100C-X FOCUSCORRIDOR 2102-C 2100B-X CONFERENCE LOBBY 2201A OPEN OFFICE — eLearning 2100A-X STAIR B RECEPTION1181-X — Weekend College TCC CONNECT FLOOR PLAN Master Plan Floor Plan 0' 10' 20' 40' North 468 469 + 2060B-X MECH VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION 24 0 0 A - X CO R R I D O R 2907A OPEN OFFICE 2801A OPEN OFFICE TCC Connect Prioritization Background 2703-C 2903A CONFERENCE OFFICE 2902A-S 2905A 2906A 2802A 2803A 2804A 2805A STORAGE 2904A FOCUS FOCUS FOCUS FOCUS FOCUS FOCUS FOCUS 2900A-X 2800A-X CORRIDOR CORRIDOR 2503-R MEN'S 2561A-X 2801-C CONFERENCE 2460A-X 2860A-X 2702A 2901A IDF IDF ELECTRICAL 2602A-S OFFICE OFFICE VISION DECISION DRIVERS — Program growth is limited by available space in the other towers at the Trinity River Campus. — Technology is insufficient to provide the standard of education that the College aspires to provide to its student body. CORE ELEMENTS — Re-organization and consolidation of other programs in the Trinity River Campus towers can provide room for program expansion. — The trend towards Online learning and students pursuing academics through a distanced option strengthens the need for a robust Online option. STORAGE 2800B-X CORRIDOR 2700A-X LOUNGE MECHANICAL 2500A-X 2360A-X 2207 CORRIDOR 2206-C TRAINING The master plan programming for the Connect Campus should account for the faculty and staff needed to support current and future student growth. Although most student services are virtual, there is and will continue to be a need for additional space for the staff which support these functions. Student growth also requires additional faculty and faculty resources. Spaces to support the development of Online course work, faculty collaboration, tech support, and administrative development are needed to support this unique college. The master plan should be mindful of the College initiative of 3 Goals and 8 Principles, applying them as possible to any renovations or expansions to the staff and faculty spaces of the Connect Campus. 2600A-X CONFERENCE CORRIDOR 2601-C 2701A 2210A 2560A-X CONFERENCE VIDEO PRODUCTION OFFICE ELECTRICAL 2300A-X 2502-R CORRIDOR WOMEN'S 2200A-X 2504B-X 1174-X 2301A-X CORRIDOR 2103-C ELEV. 4 ELEV. LOBBY 2501A-S JANITORIAL CONFERENCE STORAGE 2101-K BREAK RM. 2204A 2208A 2209A FOCUS FOCUS FOCUS 2211A 2212A 1171-X 1172-X 1173-X FOCUS FOCUSELEV. 1 ELEV. 2 ELEV. 3 2202A 2203A FOCUS2100C-X FOCUSCORRIDOR 2102-C 2100B-X CONFERENCE LOBBY 2201A OPEN OFFICE 2100A-X 1181-X STAIR B RECEPTION CAMPUS FLOOR PLAN Existing Conditions 0' 10' 20' 40' North 470 471 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line 2060B-X MECH VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 1: Upgrade Touch-Down Space and Presentation Technology 24 0 0 A - X CO R R I D O R Upgrade Touch-Down Space: 908 SF — Provide additional workstations for employee hoteling. — Located at TRWF floor 2. — Existing program to remain. Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Clarify no landscape scope. If there is landscape scope, refer to college level guidelines and standards. Upgrade Lounge Presentation Technology: 4,001 SF 2907A OPEN OFFICE 2801A OPEN OFFICE 1 — Located at TRWF floor 2. — Existing program to remain. 2703-C 2903A CONFERENCE OFFICE 2902A-S 2905A 2906A 2802A 2803A 2804A 2805A STORAGE 2904A FOCUS FOCUS FOCUS FOCUS FOCUS FOCUSFOCUS 2900A-X 2800A-X CORRIDOR CORRIDOR 2503-R MEN'S 2561A-X 2801-C CONFERENCE 2460A-X 2860A-X 2702A 2901A IDF IDF ELECTRICAL 2602A-S OFFICE OFFICE STORAGE 2700A-X 2800B-X CORRIDOR LOUNGE MECHANICAL 2360A-X 1 2207 CORRIDOR 2500A-X 2206-C TRAINING 2600A-X CORRIDOR CONFERENCE 2601-C 2210A 2701A 2560A-X CONFERENCE OFFICE VIDEO PRODUCTION ELECTRICAL 2300A-X 2502-R CORRIDOR WOMEN'S 2200A-X 2504B-X 1174-X 2301A-X CORRIDOR 2103-C ELEV. 4 ELEV. LOBBY 2501A-S JANITORIAL CONFERENCE STORAGE 2101-K Building 2204A 2208A 2209A FOCUSBREAK RM. FOCUS FOCUS 2211A 2212A 1171-X 1172-X 1173-X FOCUS FOCUSELEV. 1 ELEV. 2 ELEV. 3 — Replacement of systems is outlined in Volume II. 2202A 2203A FOCUS2100C-X FOCUSCORRIDOR 2102-C 2100B-X CONFERENCE — Any structural modifications for planned renovations shall be identified. LOBBY 2201A OPEN OFFICE — DT VB Furniture Replacement/Renewal 2100A-X 1181-X STAIR B RECEPTION — DT TCOC/SE VB Emergency Power and UPS Installation — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments PHASING FLOOR PLAN Phase 1 0' 10' 20' 40' North 472 473 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line 2060B-X MECH VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION 24 0 0 A - X CO R R I D O R Phase 2: Expand Workstations to Trinity River Expand Workstations: 2,199 SF — Workstations to be expanded from existing location to edge of tower along Trinity River. — Located at TRWF floor 2. — Existing program to remain. Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Clarify no landscape scope. If there is landscape scope, refer to college level guidelines and standards. 2907A OPEN OFFICE 2801A OPEN OFFICE 1 2 2703-C 2903A CONFERENCE OFFICE 2902A-S 2905A 2906A 2802A 2803A 2804A 2805A STORAGE 2904A FOCUS FOCUS FOCUS FOCUS FOCUS FOCUSFOCUS 2900A-X 2800A-X CORRIDOR CORRIDOR 2503-R MEN'S 2561A-X 2801-C CONFERENCE 2460A-X 2860A-X 2702A 2901A IDF IDF ELECTRICAL 2602A-S OFFICE OFFICE STORAGE 2700A-X 2800B-X CORRIDOR LOUNGE MECHANICAL 2360A-X 1 2207 CORRIDOR 2500A-X 2206-C TRAINING 2600A-X CORRIDOR CONFERENCE 2601-C 2210A 2701A 2560A-X CONFERENCE OFFICE VIDEO PRODUCTION ELECTRICAL 2300A-X 2502-R CORRIDOR WOMEN'S 2200A-X 2504B-X 1174-X 2301A-X CORRIDOR 2103-C ELEV. 4 ELEV. LOBBY 2501A-S JANITORIAL CONFERENCE STORAGE 2101-K Building 2204A 2208A 2209A FOCUSBREAK RM. FOCUS FOCUS 2211A 2212A 1171-X 1172-X 1173-X FOCUS FOCUSELEV. 1 ELEV. 2 ELEV. 3 — Replacement of systems is outlined in Volume II. 2202A 2203A FOCUS2100C-X FOCUSCORRIDOR 2102-C 2100B-X CONFERENCE — Any structural modifications for planned renovations shall be identified. LOBBY 2201A OPEN OFFICE — DT VB Furniture Replacement/Renewal 2100A-X 1181-X STAIR B RECEPTION — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments PHASING FLOOR PLAN Phase 2 0' 10' 20' 40' North 474 475 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line 2060B-X MECH VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 3: Expand Workstations along Lounge 24 0 0 A - X CO R R I D O R Expand Workstations: 1,419 SF Site — Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. — Clarify no landscape scope. If there is landscape scope, refer to college level guidelines and standards. — Workstations to be expanded from existing location to edge of Lounge along Trinity River. — Workstations to include full-height partitions to manage acoustics from Lounge leaking to rest of floor. — Located at TRWF floor 2. — Existing program to remain. 2907A OPEN OFFICE 2801A OPEN OFFICE 1 2 2703-C 2903A CONFERENCE OFFICE 2902A-S 2905A 2906A 2802A 2803A 2804A 2805A STORAGE 2904A FOCUS FOCUS FOCUS FOCUS FOCUS FOCUSFOCUS 2900A-X 2800A-X CORRIDOR CORRIDOR 2503-R MEN'S 2561A-X 2801-C CONFERENCE 2460A-X 2860A-X 2702A 2901A IDF IDF ELECTRICAL 2602A-S OFFICE OFFICE STORAGE 2700A-X 2800B-X CORRIDOR LOUNGE MECHANICAL 2360A-X 1 2207 CORRIDOR 2500A-X 2206-C TRAINING 2600A-X CORRIDOR CONFERENCE 2601-C 2210A 2701A 2560A-X CONFERENCE OFFICE VIDEO PRODUCTION ELECTRICAL 2300A-X 2502-R CORRIDOR WOMEN'S 2200A-X 2504B-X 1174-X 2301A-X CORRIDOR 2103-C ELEV. 4 ELEV. LOBBY 2501A-S JANITORIAL CONFERENCE STORAGE 2101-K 3 Building 2204A 2208A 2209A FOCUSBREAK RM. FOCUS FOCUS 2211A 2212A 1171-X 1172-X 1173-X FOCUS FOCUSELEV. 1 ELEV. 2 ELEV. 3 — Replacement of systems is outlined in Volume II. 2202A 2203A FOCUS2100C-X FOCUSCORRIDOR 2102-C 2100B-X CONFERENCE — Any structural modifications for planned renovations shall be identified. LOBBY 2201A OPEN OFFICE — DT VB Furniture Replacement/Renewal 2100A-X 1181-X STAIR B RECEPTION — DT Access Control — DT Security Master Plan — DT Arc Flash and Coordination Assessment — DT Flooring Replacement — DT Smart Building Program Services — DT Sustainability Master Plan — DT Continuous Commissioning Program Services — DT Mechanical, Electrical, Plumbing Assessments PHASING FLOOR PLAN Phase 3 0' 10' 20' 40' North 476 477 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 4: Relocate College IT and Support Services Relocate College IT and Support Services: 30,290 SF —Renovate space for program use by College IT and Support Services. —Located at TRCF floor 7. Current location is TRWF floor 3. 4 Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —Clarify no landscape scope. If there is landscape scope, refer to college level guidelines and standards. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT VB Furniture Replacement/Renewal —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments PHASING FLOOR PLAN Phase 4 0' 100' 200' 400' North 478 479 + LEGEND LEGEND Previous Phase Site Project Previous Phase Project Current Phase Telecomm. Line Current Phase Site Project Current Phase Project Existing Building Current Phase Demo. Project Previous Phase Telecomm. Line VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Phase 5: Expand TCC Connect Expand TCC Connect Program Space: 30,290 SF —Renovate space for program use by TCC Connect. 5 —Located at TRWF floor 3. Current location is TRWF floor 2. Site —Clarify no civil/traffic scope. If there is civil/traffic scope, refer to college level guidelines and standards. —Clarify no landscape scope. If there is landscape scope, refer to college level guidelines and standards. Building —Replacement of systems is outlined in Volume II. —Any structural modifications for planned renovations shall be identified. —DT VB Furniture Replacement/Renewal —DT Access Control —DT Security Master Plan —DT Arc Flash and Coordination Assessment —DT Flooring Replacement —DT Smart Building Program Services —DT Sustainability Master Plan —DT Continuous Commissioning Program Services —DT Mechanical, Electrical, Plumbing Assessments PHASING FLOOR PLAN Phase 5 0' 100' 200' 400' North 480 481 482 483 + VOLUME I PRIORITIZATION VOLUME I PRIORITIZATION Tarrant County College District 2022 District-wide Masterplan Phasing TCC CONNECT CAMPUS MASTERPLAN PHASING Projected Masterplan Phasing Project Costs Phase Project Project Year Construction Cost Limitation Softs Costs (38%) Project Total Phase 1 Renovate existing touch-down space with additional workstations for employee hoteling. Future $ 590,100 $ 224,238 $ 814,338 Renovate and upgrade technology used for presentation in Lounge. Future $ 3,003,590 $ 1,141,364 $ 4,144,954 Phase 2 Expand workstations to edge of tower facing Trinity River. Future $ 1,429,108 $ 543,061 $ 1,972,169 Phase 3 Expand workstations along edge of Lounge. Future $ 922,194 $ 350,434 $ 1,272,628 Phase 4 Renovate swing space for IT and relocate IT department. Future $ 15,458,080 $ 5,874,070 $ 21,332,150 Phase 5 Infill existing IT space for TCC Connect expansion. Future $ 19,665,022 $ 7,472,708 $ 27,137,730 POTENTIAL TOTAL COST $ 56,673,969 LEGEND New Construction Project Renovation Project Site Project Demo. Project Existing Building COST ESTIMATE NOTES — Escalation percentage added for projects from 2023 – 2027. — No additional escalation is added for projects after 2027. CAMPUS SITE PLAN — Escalation percentage used is 1% per month. Consolidated Master Plan Phasing 0' 10' 20' 40' North — Cost estimates are based on pricing from 2022. VOLUME I ACKNOWLEDGMENTS VOLUME I ACKNOWLEDGMENTS + Acknowledgments ,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN VOLUME I ACKNOWLEDGMENTS Acknowledgments Board of Trustees Teresa Ayala — President Shannon Wood Jeannie Deakyne — Secretary Bill Greenhill Leonard Hornsby — Assistant Secretary Dr. Gwendolyn Morrison, Ph.D. Kenneth Barr — Vice President Administration Team Dr. Elva Concha LeBlanc, Ph.D. — Interim Chancellor Dr. Kenya Ayers-Palmore, Ed.D. — President, Northeast Campus Dr. Zarina Blankenbaker, Ph.D. — President, Northwest Campus Dr. Bill Coppola, Ph.D. — President, Southeast Campus Dr. Dan Lufkin, Ed.D. — President, South Campus Dr. S. Sean Madison, Ed.D. — President, Trinity River Campus Dr. Carlos Morales, Ph.D. — President, TCC Connect Campus Tia Cole — Chair, Joint Consultation Committee 2022 – 2021 Shewanda Riley — Chair-Elect, Joint Consultation Committee 2022 – 2023 Susan Alanis, MPA — Chief Operating Officer Carol Bracken — Associate General Counsel Shannon Bryant, M.Ed., CWDP — Executive Vice President for Corporate Solutions and Economic Development Reginald Gates, M.Ed. — Vice Chancellor for Communications and External Affairs Robert Pacheco, M.Ed. — Chief Technology Officer VOLUME I ACKNOWLEDGMENTS 3G8P Champions Learning Commons Dr. S. Sean Madison, Ed.D Integrated Instructional Learning Environments Dr. Zarina Blankenbaker, Ph.D. Integrated Student Success Model — Student Experience Dr. Kenya Ayers-Palmore, Ed.D. High Schools Dr. Bill Coppola, Ph.D. Scheduling and Facility Utilization Dr. Elva Concha LeBlanc, Ph.D. Campus Character and Quality Reginald Gates, M.Ed. Workspace Environments Dr. Carlos Morales, Ph.D. Northeast Campus Leadership and Stakeholders Dr. Kenya Ayers-Palmore, Ed.D. — Campus President Dr. Terri Ford, Ph.D. — Assistant to the President Dr. Ritu Raju, Ph.D. — Vice President of Academic Affairs Terese Tann Craig — Vice President of Student Affairs Terra Frost, MLA — Dean of Community Education and Engagement Dr. Hwiman Chung, Ph.D. — Dean of Communication, Arts, and Entertainment Charlene Cole, M.S. — Dean of Mathematics and Sciences Dr. Stephanie Scroggins, Ph.D. — Dean of Social and Human Sciences Rebecca Balcarcet Kevin Barrett + Mary Lou Bledsoe Matthew Broyles Kristin Byrd Catherine Carter Jan Clayton Betty Dalton Mark Dolive Pete Fiannaca Terri O’Neal Fond Murray Fortner Kevin Harper Chris Hunt Laura Jones Christy Klemink Peter Martinez Rosa Mendez Carol Merchant Terry Moak Condoa Parrent Shewanda Riley 487 486 ,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN VOLUME I ACKNOWLEDGMENTS Northeast Campus Leadership and Stakeholders (cont.) Thomas Rinzeler Gerald Ringe Stacy Stuewe Ann Triplett Richard Vela Cara Walker Mary Williams Northwest Campus Leadership and Stakeholders Dr. Zarina Blankenbaker, Ph.D. — President, Northwest Campus Dr. Serafin Garcia, Ph.D. — Assistant to the President Dr. Thomas Sosa, Ph.D. — Vice President of Academic Affairs Dr. Jan Clayton, Ed.D. — Vice President of Student Affairs James Clinton Grant, M.B.A. — Dean of Aviation, Business, and Logistics Division Lisa Benedetti, M.A. — Dean of Humanities Division Dr. Greta Bowling, Ph.D. — Dean of Mathematics and Sciences Dr. Sonya L. Brown, Ed.D. — Dean of Public Services, Social, and Behavioral Sciences; Interim Dean of Community Education and Engagement Eric Camarillo, M.A. — Dean of Learning Commons Tom Fraire, M.Ed. — Principal of Marine Creek Collegiate High School Jennifer Cargill Ryan Ferguson Kathleen Galindo Vanessa Harrison Lynn Heisey Ebony Howard Steve Keller Leon Minerr Jasmine Quezada Samantha Taylor Robin Washington White VOLUME I ACKNOWLEDGMENTS South Campus Leadership and Stakeholders Dr. Dan Lufkin, Ed.D. — Campus President Dr. Gabriela Borcoman, Ph.D. — Assistant to the President Dr. Shannon S. Ydoyaga, Ph.D. — Vice President of Academic Affairs Dr. Michael DuPont, Ph.D., LMFT, LSSP — Vice President of Student Affairs Dr. Terry Aaron, Ph.D. — Dean of Community Education and Engagement Arthur James Jr., M.S., CHE — Dean of Business and Technology Mehrnaz Ghaffarian — Interim Dean of Mathematics and Natural Sciences Dr. Vicki Ansorge, Ed.D. — Dean of Humanities Dr. Shereah Taylor-Love, Ed.D. — Dean of Behavioral and Social Sciences Dr. Quanda Collins, Ed.D. — Principal of TCC South/Fort Worth ISD Collegiate High School Southeast Campus Leadership and Stakeholders Dr. Bill Coppola, Ph.D. — Campus President Allen Powell — Assistant to the President Dr. Zena K. Jackson, Ph.D. — Vice President of Academic Affairs Dr. Michael DuPont, Ph.D., LMFT, LSSP — Vice President of Student Affairs Dr. Carrie Tunson, Ed.D. — Dean of Community Education and Engagement Ann Machen, M.B.A. — Dean of Business and Technology Division Josué Muñoz, M.A. — Dean of Humanities Division Dr. Jerry Coats, Ph.D. — Dean of Liberal Arts Division Dr. Thomas Awtry, Ph.D. — Dean of Mathematics, Sciences, and HPE Division Mike Cinatl Renetta Wright + Trinity River Campus Leadership and Stakeholders Dr. S. Sean Madison, Ed.D. — Campus President Dr. Hughes George, Ph.D. — Assistant to the President Dr. Stephanie Scroggins, Ph.D. — Interim Vice President of Academic Affairs Dr. Deidra Turner, Ph.D. — Interim Vice President of Student Affairs Richard Chance, M.S. — Dean of Community Education and Engagement Dr. Sheldon Smart, Ph.D. — Interim Dean of Humanities Dr. Taylor Hughlett, Ph.D. — Interim Dean of Mathematics, Science, and Business Dr. Jose Alejandro, Ph.D. — Dean of Nursing Dr. Brandon Hernandez, Ed.D. — Dean of Health Sciences Jack Henson, M.Ed. — Principal of Texas Academy of Biomedical Sciences Tom Mills 489 488 ,~ T arranl Cou11ty College· ~ WCCE55 wm•• AEACH. CORGAN VOLUME I ACKNOWLEDGMENTS TCC Connect Leadership and Stakeholders Dr. Carlos Morales, Ph.D. — Campus President Alma Martinez-Egger, M.S. — Assistant to the President Dr. Shelley Pearson, Ed.D. — Vice President of Academic Affairs Dr. Deshonta Holmes, Ed.D. — Vice President of Student Affairs Dr. Kristen Kelton, Ph.D. — Director of Academic Affairs Dr. Cristina Sullivan, Ed.D. — Dean of Academic Affairs Matthew Taylor, M.S. — Director of Student Development Services Dr. Audra G. Barrett, Ed.D. — Director of Weekend College Kim Estes, M.Ed. — Senior Instructional Designer 3G8P Principle Advisory Panels Members Dr. S. Sean Madison, Ed.D. — Learning Commons Champion Dr. Zarina Blankenbaker, Ph.D. — Integrated Instructional Learning Environments Champion Dr. Kenya Ayers-Palmore, Ed.D. — Student Experience Champion Dr. Bill Coppola, Ph.D. — High Schools Champion Dr. Elva Concha LeBlanc, Ph.D. — Scheduling and Facility Utilization Champion Reginald Gates, M.Ed. — Campus Character and Quality Champion Dr. Carlos Morales, Ph.D. — Workspace Environments Champion Dr. Vicki Ansorge, Ed.D. — Dean of Humanities Lisa Benedetti, M.A. — Dean of Humanities Division Dr. Greta Bowling, Ph.D. — Dean of Mathematics and Sciences Dr. Jan Clayton, Ed.D. — Vice President of Student Affairs Dr. Sonya L. Brown, Ed.D. — Dean of Public Services, Social, and Behavioral Sciences; Interim Dean of Community Education and Engagement Dr. Serafin Garcia, Ph.D. — Assistant to the President Alma Martinez-Egger, M.S. — Assistant to the President Josué Muñoz, M.A. — Dean of Humanities Division Dr. Shelley Pearson, Ed.D. — Vice President of Academic Affairs Dr. Ritu Raju, Ph.D. — Vice President of Academic Affairs Dr. Shannon S. Ydoyaga, Ph.D. — Vice President of Academic Affairs Dr. Deidra Turner, Ph.D. — Interim Vice President of Student Affairs Ray Allison Berky Alvarez-Valentin Sara Ansley Patricia Bass Felisha Battles VOLUME I ACKNOWLEDGMENTS 3G8P Principle Advisory Panels Members (cont.) Yutanzia Berryhill Tara Bradford Edward Brassart Adriana Cavitt Candy Center Tina Chen Alicia Coleman Kimberley Cox Chanissa Dietrich Kim Estes Leah Fenner Ryan Ferguson Tara Firmin Judith Gallagher Suzanne Groves Jay Hall Allegra Hanna Kevin Harper Stephanie Hawkins Janet Rodriguez Daiju Hoshino Kenneth Rogers Ebony Howard Brenna Sanders Vicki Hutto Carroll Savant Deshun Jackson Debra Scheiwe Colin Jenney Laura Schlauderaff Dawn Lovelace Jorge Serralta Margaret Lutton Dantrayl Smith A'isha Malone Ramiro Sosa Rachael McCloskey John Spencer Carol Merchant Holly Stovall Cherie Mitchell Paula Stubblefield Marlon Mote Michael Tankersley Traci Nielsen Noemi Vela Melissa Perry Richard Vela Wendy Pierce Hung Vu Julia Quarles Walter Williams Jeffrey Ramirez Kelly Willing Christine Reaganloh Renetta Wright Sarabeth Reed Victoria Yen Kristina Robisheaux + 490 491 492 493 +VOLUME I ACKNOWLEDGMENTS TCC Real Estate and Facilities Michael Brantley Tina Chen Okang Hemmings Jonathan Jackamonis Farhat Yasmeen Khan Margaret Lutton Paul Mitchell Traci Nielsen Thomas Vanover Walter H. Williams Million Gebre TCC Information Technology Vicki Hutto Richard Sullivan Nelson McMicken David Rubio Wayne Hughes Ephraim Kadima Paul Cogdell Program Management Team — Jacobs Rigo Cisneros Jairus McDavid Meredith McElmurry Leo McKinley Jonathan Oltmann John Posch Matt Smith VOLUME I ACKNOWLEDGMENTS Master Planning Team Corgan Terral Carpenter Grant Huska Sangeetha Karthik Trent Loomis Eliu Paredes John Risi Dana Truong Kelsey Wagner David Zatopek CCS Vinayak Lalwani Jim Nuckolls Coleman & Associates Aan Garrett-Coleman Jan Giles Adriana Hernandez-Aguirre Claire Kelly Marissa McKinney DataCom Design Group John Rob Hicks Steve Benefield Facility Programming Doug Lowe Bryan Sibille Shelly Whidby Jones DBR Erik MacDonald Ronjan Mathur Kenneth Roland Manning Rachel Billings Andy Kim Craig King Wm. Raymond Manning Carson Piontek Kevin Simon Dominic Willard, Jr. Pacheco Koch Ron Ramirez Steve Stoner Tim Wallace Ponce Fuess Rene Avila Lucas Ponce